SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(APTEL) 37

APPELLATE TRIBUNAL FOR ELECTRICITY
Chettinad Power Corporation Private Ltd. VERSUS Power Grid Corporation of India Limited & Ors
APPEAL No. 99 of 2017 (PDF)



The word 'may' in Regulation 12(5) of the Connectivity Regulations, 2009 is directory, not mandatory. Nodal agency has discretion to encash an LTA bank guarantee based on facts of each case, including genuine hardship.

Headnote:(A) Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Mid-term Open Access in the Inter-State Transmission and related matters) Regulations, 2009 - Regulation 12(5) - Interpretation of word "May" - Whether mandatory or directory - Bank Guarantee - Encashment - Discretion of nodal agency.

(B) Interpretation of Statutes - The use of the word 'may' in a statutory provision does not by itself make it directory; the court must consider the object, scheme, context, and purpose of the Act to determine if it conveys a mandatory force. Where interpreting 'may' as directory would defeat the very object of the Act, it must be read as 'shall'. (Paras 25, 26)

Facts of the case:
The Appellant applied for Long-Term Access (LTA) for a thermal power project and furnished a Bank Guarantee. LTA was granted, but the Appellant failed to sign the LTA agreement within 30 days due to pending litigation before the National Green Tribunal challenging its environmental clearance. The nodal agency (CTUIL) sought to encash the Bank Guarantee. The Central Electricity Regulatory Commission held that Regulation 12(5) of the Connectivity Regulations mandates encashment of the Bank Guarantee if the LTA agreement is not signed within the stipulated period, even if the delay is due to force majeure or reasons beyond the applicant's control.

Findings of Court:
The Appellate Tribunal for Electricity (APTEL) held that the word "may" in Regulation 12(5) is directory, not mandatory. The purpose of the Bank Guarantee is only to ensure that serious applicants apply, not to serve as a penal provision. The nodal agency has the discretion to decide on encashment based on the facts and circumstances of each case, including cases of genuine hardship. The impugned order of the Commission was set aside.

Issues: Whether the word "May" in Regulation 12(5) of the Connectivity Regulations, 2009 is directory, merely conferring discretion on the nodal agency, or whether it is mandatory, requiring the nodal agency to necessarily encash the Bank Guarantee upon the occurrence of the specified events (withdrawal, relinquishment, or failure to sign the LTA agreement).

Ratio Decidendi: The court ruled that Regulation 12(5) is directory, relying on the Statement of Reasons for the Regulations, which indicates that the Bank Guarantee's purpose is to ensure seriousness of applicants, not to impose a penalty. The court also noted the Commission's own submission to the Delhi High Court that the Regulation was not intended to be mandatory. The decision to encash must be determined by the nodal agency based on the facts of each case, considering genuine hardship or reasons beyond the applicant's control. Result : Appeal allowed. Impugned order set aside. Matter remanded to the Commission to determine whether CTUIL was justified in encashing the Bank Guarantee, to be decided within one month of the judgment. Held and declared that Regulation 12(5) is directory/discretionary. (Para 37) Matter remanded. (Para 38)

Legal Category Hierarchy

  • administrative law
    • statutory interpretation
  • energy law
  • banking and finance
    • bank guarantees
      • encashment discretion (Para 34, 35, 37)

Table of Contents

1. Appeal against CERC order that force majeure cannot prevent encashment of bank guarantee for failure to sign LTA agreement. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 )

2. Appellant: Regulation 12(5) 'may' is directory, discretion; CTUIL: 'may' is mandatory, encashment required. (Para 21 , 22 , 23 )

3. Appeal allowed; impugned order set aside; Regulation 12(5) declared directory; matter remanded to CERC. (Para 36 , 37 , 38 )

4. Is the word 'may' in Regulation 12(5) of the Connectivity Regulations mandatory or directory?

The word 'may' is directory; encashment of bank guarantee is discretionary, not mandatory, and must be determined case by case. (Para 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 )

5. What is the purpose of the bank guarantee furnished with a long-term access application?

The sole purpose is to bring seriousness to applications and screen applicants; it is not a penal or liquidated damages provision. (Para 28 , 29 , 30 , 31 , 32 , 33 , 34 )

6. Does the nodal agency have discretion to decide whether to encash the bank guarantee?

Yes, the nodal agency must consider facts and circumstances, including genuine hardship or reasons beyond applicant's control, before encashing. (Para 34 , 35 , 37 )

JUDGMENT

PER HON’BLE MR. VIRENDER BHAT, JUDICIAL MEMBER

1. The order dated 8th March, 2017 passed by 2nd Respondent – Central Electricity Regulatory Commission (in short “Commission” or “CERC”), vide which it held that as per Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Mid-term Open Access in the Inter-State Transmission and related matters) Regulations, 2009, (herein after referred to as “Connectivity Regulations”), the Long-term access applicant being effected by Force Majeure or reasons beyond its control cannot be a ground for non- signing of the Long Term Access Agreement and the failure to sign the LTA agreement within the stipulated period would necessarily result in encashment of Bank Guarantee submitted along with LTA application, has been assailed in this appeal.

2. The brief facts of the case which are necessary for the disposal of the instant appeal are that the Appellant proposed to set up 2x600 MW sub-critical thermal plant at Erukkatanchery, Kazhippanallur and Manickapangu villages in Tharangambadi Taluk of Nagapattinam district in Tamil Nadu. The project was scheduled to be commissioned in the year 2015. The Appellant applied for connectivity on 23rd September 2010 and for Long-Term Access (LTA) on 15th February, 2011 for 1110 MW. The application was accompanied by a Bank Guarantee of 1.10 crores in accordance with the connectivity Regulations. In the 13th meeting of the Southern Region Constituents (SRC) regarding connectivity and LTA applications, the Appellant was granted connectivity as well as LTA for 1110 MW and was advised by the 1st Respondent Power Grid Corporation of India Limited (now CTUIL i.e. the Central Transmission Utility India Limited), vide letter 23rd December, 2011, to sign the LTA agreement within a period of 30 days from the date of the letter. The Appellant was granted environmental clearance for the power project on 20th January, 2011 on the basis of the recommendations of Environment and Assessment Committee, Ministry of Environment and Forests, Government of India. The said environmental clearance was challenged before National Green Tribunal (NGT) and vide order dated 30th May, 2012, NGT observed that the Appellant was in substantial compliance and directed the Appellant to rectify certain procedural errors. Upon compliance with these directions of the NGT, Ministry of Environment and Forest (MoEF) issued a corrigendum dated 13th June, 2013 to the environment clearance granted to the Appellant. Even the said corrigendum dated 13th June, 2013 was challenged by certain organizations before NGT Southern Zone. The matter was transferred to the NGT, Principal Bench and was numbered as Appeal No. 87 of 2014. The matter is still stated to be subjudice before NGT.

3. Meanwhile, in the 17th Meeting of Southern Region Constituents held on 31st July, 2014, the Appellant and CTUIL agreed that CTUIL may encash the Bank Guarantee of the Appellant on or after 1st February, 2015 if the Appellant did not get environmental clearance from NGT by that date. The relevant portion of the said meeting is extracted herein below :-

“6.5 DGM (CTU) informed that LTA was granted to Chettinad Power Corporation Ltd. (2x600 MW) ON 27.12.2011 but the generation developer failed to sign LTA agreement and furnish Bank Guarantee till date. The representative from Chettinad Power Corporation informed that they have received all necessary clearances but the final hearing of NGT order on environment clearance for their project has not yet received and so, they requested for time extension of six months for execution of the LTA Agreement and furnishing of construction stage BG. In this regard, Director, CEA suggested that Chettinad Power may submit a letter within say one week mentioning that CTU may encash their BG on after 1.2.2015 if they still do not get environmental clearance from NGT, which was agreed by CTU and M/s Chettinad Power.

4. In pursuance to the discussion held in the s

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top