APPELLATE SIDE,BOMBAY
SANDEEP V. MARNE, J
M/s. Nanded City Development and Construction Company Ltd. – Appellant
Versus
Laxman Eknath Dedge and Ors. – Respondent
| Table of Content |
|---|
| 1. dispute arose from joint development and the legality of injunctions against ongoing development. (Para 2 , 3 , 4) |
| 2. arguments presented by both parties concerning possession and rights under the joint agreement. (Para 5 , 6) |
| 3. nature of agreements and implications for profit-sharing arrangements affecting project sustainability. (Para 7 , 8 , 10 , 12 , 14) |
| 4. guidelines for granting interim injunction leading to a focus on irreparable harm and maintenance of project integrity. (Para 16 , 19 , 23) |
| 5. final decision reversing the trial court's order and granting injunction to the plaintiff. (Para 24 , 26) |
JUDGMENT :
2. This Appeal is fled challenging order dated 3 October 2022 passed by the 11th Joint Civil Judge Senior Division, Pune rejecting Appellant-Plaintiff’s application at Exibit-5 for grant of temporary injunction and allowing application fled by the Respondents-Defendants at Exhibit-34 granting temporary injunction in favour of the Defendants by restraining Plaintiff from obstructing Defendants’ possession of the suit property.
3. The Appellant-Plaintiff
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.