CHAYA BHIKAN KACHOLE – Appellant
Versus
LOKVIKAS NAGAR SAHAKARI BANK LTD. THR ITS CHIEF EXECUTIVE OFFICER – Respondent
WP 5264/2021
1
906wp5243.21
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD
906 WRIT PETITION NO.5243 OF 2021
TUSHAR VINAYAKRAO GAVHANE
VERSUS
M/S LOKVIKAS NAGAR SAHAKARI BANK LTD AURANGABAD
...
Advocate for Petitioner : Mr. Thombare S.S. h/f Mr.Karad Murlidhar S.
...
AND
907 WRIT PETITION NO.5244 OF 2021
ASHWINI DEVIDASRAO ADHANE
VERSUS
M/S LOKVIKAS NAGAR SAHAKARI BANK LTD AURANGABAD THR ITS
CHIEF EXECUTIVE OFFICER
AND
908 WRIT PETITION NO.5264 OF 2021
CHAYA BHIKAN KACHOLE
VERSUS
LOKVIKAS NAGAR SAHAKARI BANK LTD. THR ITS CHIEF EXECUTIVE
OFFICER
CORAM : N. J. JAMADAR , J.
Date :- 24th March, 2021.
P. C. :
1.
Heard the learned counsels for the petitioners.
2.
The challenge in these petitions is to the orders passed by the
Industrial Court, on 17th February, 2021, in Revision Petition Nos. (ULP) No.
38 of 2020, (ULP) No. 41 of 2020 and (ULP) No. 33 of 2020, whereby the
Industrial Court dismissed the Revision Petitions, preferred by the petitioners
herein, against the orders dated 2nd December, 2020 passed by the Labour
Court on the applications for interim relief (Exh. U-2) in the complaint (ULP)
2
906wp5243.21
No. 34 of 2020, (ULP) No.44 of 2020 and (ULP) No. 46 of 2020, whereby, the
prayer of the respective petitioners herein for the reinstatement till the fnal
disposal of the complaints came to be rejected.
3.
Mr. Tushar, the petitioner in Writ Petition No. 5243 of 2021 came
to be appointed as an ‘Ofcere with the respondent Bank, with efect from 6th
November, 2018. He was made permanent with efect from 1st February,
2020, by order dated 3rd February, 2020. Ms. Ashwani and Mrs. Chhayya, the
petitioners in Writ Petition No. 5244 of 2021 and Writ Petition No. 5264 of
2021 respectively, were appointed as ‘Clerkse with efect from 9th November,
2018, and 6th November, 2018 and permanency was conferred on them with
efect from 1st February, 2020.
4.
The services of the petitioners were, however, terminated by
order dated 7th November, 2020, solely on the basis of the letter dated 4th
November, 2020, issued by the Commissioner and Registrar of Co-Operative
Societies Pune, whereby, it was directed that the appointments of employees
who were recruited by the respondent -Bank in the recruitment process,
2018, be cancelled.
5.
The petitioners contend that the said action of the respondent-
Bank is legally unsustainable. The petitioners, thus, fled the above numbered
complaints before the Labour Courts, wherein, interim-relief in the nature of
reinstatement was sought.
6.
The interim relief was refused as it would amount to granting the
fnal relief as the legal position is crystallieed to the efect that the
3
906wp5243.21
reinstatement by way of interim relief is not permissible. The Industrial Court
declined to interfere with the orders passed by the Labour Court.
7.
No fault can be found with the orders passed by the Labour and
Industrial Court. Grant of interim relief of reinstatement, at this stage, would
amount to granting the main relief in the complaints.
8.
In the aforesaid backdrop, the learned counsel for the petitioners
submits that the interest of the petitioners, who are out of the employment,
on account of unsustainable order passed by the respondent, would be
served, if the Labour Court is directed to hear and decide the complaints fled
by the petitioners, expeditiously.
9.
Having regard to the nature of the impugned order, which
singularly draws support and sustenance from the communication of the
Commissioner and Registrar of Co-Operative Societies, Pune, it appears
expedient that the complaints be heard and decided expeditiously. The
controversy seems to be in a narrow compass.
10.
In view of the above, the petitions stand disposed of with a
request to the Labour Court to hear and decide the aforesaid complaints, as
expeditiously as possible, and pr