2022 Supreme(Online)(Bom) 4923
THE MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD THROUGH ADDITIONAL EXECUTIVE ENGINEER – Appellant
Versus
BADRINATH PEMA RATHOD – Respondent
WP 3425/2019
3425.19wp
(1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO.3425 OF 2019
The Maharashtra State Electricity
Distribution Company Ltd.,
Sub Division-1, Shahganj,
Aurangabad, Tq. & Dist. Aurangabad,
Through Additional Executive Engineer ….PETITIONER
VERSUS
Badrinath Pema Rathod,
Age: 57 years, Occu: Service,
R/o: Plot No.48, Bhakti Nagar,
Pisadevi Road, Aurangabad
….RESPONDENT
….
Mr A. S. Shelke, Advocate for petitioner;
Mr S. P. Koli, Advocate for respondent
CORAM : SMT. BHARATI DANGRE, J.
Date of reserving the Judgment : 10th January, 2022
Date of pronouncing the Judgment : 14th January, 2022
JUDGMENT :
1.
By the present writ petition, the Maharashtra State
Electricity Distribution Company Ltd. (MSEDCL), a licensee
under the provisions of the Electricity Act, 2003 (hereinafter
referred to as ‘the 2003 Act’), question the legality of the award
passed by the Permanent Lok Adalat, Aurangabad, in Prelitigation
Application Dispute No.44/2018, under which the petitioner has
3425.19wp
(2)
been directed to issue regular bills to the applicant Shri. Badrinath
Pema Rathod, who had instituted the said application. Further
direction is issued to the applicant to clear the bills and on
payment of the same, the petitioner is directed not to disconnect
his electricity supply.
2.
Heard the learned Counsel Shri. A. S. Shelke for the
petitioner and the learned Counsel Shri. S. P. Koli for the
respondent.
Rule. Rule is made returnable forthwith and heard finally
by consent of the parties.
3.
Before the merits of the award impugned can be
appreciated, it is apposite to refer to the brief facts leading to the
passing of the impugned award by the Permanent Lok Adalat.
Shri. Badrinath Pema Rathod, resident of Plot No. 48,
Bhakti Nagar, Aurangabad, is the owner of the house property
situated on the plot and is availing the electricity supply with the
consumer number being allotted, for his residential house. On
06/12/2016, the Flying Squad, Jalna, checked his electricity meter,
which was found to be tampered, installed a new meter. He was
3425.19wp
(3)
served with the assessment bill of Rs.9,490/-. The assessment
was disputed by the respondent and he raised grievance with the
petitioner. The Flying Squad, which had checked the meter, since
noticed that the respondent was indulged in theft of electricity and
an offence came to be registered against him under Section 135 of
the 2003 Act. His existing meter was seized as per the prescribed
process and a bill was issued to him as per assessment sheet.
4.
The respondent being aggrieved by the action of the
petitioner, filed an application under Section 22 (C) of the Legal
Services Authorities Act,1987 (hereinafter referred to as ‘the 1987
Act’), which was made over to the Permanent Lok Adalat,
Aurangabad, being registered as Prelitigation Application Dispute
No.44/2018.
In the said application, he sought the relief of cancellation
of the assessment bill issued to him, since it calculated the excess
units. Pending hearing of the application, he sought directions to
the authority, to issue regular bills to him and not to disconnect his
electricity supply. He also prayed for compensation of
Rs.10,000/- on account of the harassment faced by him at the
3425.19wp
(4)
instance of MSEDCL, Shahaganj Division, for mental harassment
and economic loss.
The application was contested by the MSEDCL, by
submitting that there is no valid, legal and existing cause of action
to file the present application and since the application is not
maintainable, it should be dismissed. It was specifically pleaded
that the applicant was found guilty of theft of electricity and
therefore, aft