LALUBAI ALIAS LATABAI GEMA RATHOD – Appellant
Versus
THE UNION OF INDIA AND OTHERS – Respondent
WP 11746/2021
['Ingale Vivekanand V', 'TALHAR AJAY G', '', 'COPY SERVED ON UOI']
1 wp11746.21.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
5 WRIT PETITION NO.11746 OF 2021
LALUBAI ALIAS LATABAI GEMA RATHOD
VERSUS
THE UNION OF INDIA AND OTHERS
Mr. Vivekanand V. Ingale, Advocate for the petitioner;
Mr. A.G. Talhar, A.S.G.I. for respondent nos.1 & 2;
Mr. P.S. Patil, AGP for respondent no.3
CORAM : DIPANKAR DATTA, CJ
AND
MANGESH S. PATIL, J.
DATE : October 22, 2021
P.C.
1.
A piece and parcel of land at Talmode, Taluka Omerga, District
Osmanabad has been acquired for the purpose of National Highway No.9
(New 65). The competent authority has determined compensation payable to
the owners, i.e., the respondent nos. 4 to 6. Claiming to be aggrieved by the
amount of compensation determined by the competent authority, such
respondents have raised an objection resulting in the dispute being referred to
an Arbitrator for determination of the amount of compensation.
2.
The petitioner, claiming to be a co-owner of the acquired land, sought to
intervene in the proceedings before the Arbitrator by filing an application dated
9th March 2020 for intervention/addition of party. It is her claim in the writ
petition that the Arbitrator has refused to accept the application on the ground
that it is not maintainable. We have been informed by Mr. Ingale, learned
advocate appearing for the petitioner that no formal order has been passed by
2 wp11746.21.odt
the Arbitrator. Accordingly, this writ petition has been presented seeking a
direction on the Arbitrator, respondent no.3, to accept the application of the
petitioner for intervention/addition of party.
3.
We have heard Mr. Ingale, and Mr Talhar, learned A.S.G.I. for the
respondent nos.1 and 2.
4.
It is not disputed at the Bar that the petitioner did not raise any
objection in terms of the enabling provision contained in Section 3-C of the
National Highways Act, 1956 (hereafter ‘the Act’). It is further not disputed that
the petitioner did not raise any dispute of the nature referred to in section 3-H
(4) of the Act. Also, the undisputed position is that there is no independent
proceeding pending at the instance of the petitioner for enhancement of
compensation. On the contrary, the petitioner has instituted a civil suit for
partition in respect of the acquired land and such suit is pending.
5.
Given such facts and circumstances, the right that the petitioner claims
of being a co-owner of the acquired land is yet to be determined. Obviously,
the Arbitrator is not required by law to determine the shares of the parties in
the acquired land. His task is to determine whether the amount of
compensation awarded by the competent authority in favour of the respondent
nos. 4 to 6 is just and fair. Although the Arbitrator has not passed a formal
order rejecting the petitioner’s application dated 9th March 2020, we do not
see any reason to grant relief on this writ petition as prayed for to the
petitioner.
3 wp11746.21.odt
6.
All contentions of the petitioner with regard to her claim of ownership of
the acquired land is left open for being agitated in the civil suit instituted by
her.
7.
The writ petition stands disposed of with the aforesaid observations.
No costs.
[MANGESH S. PATIL, J.]
[CHIEF JUSTICE]
amj