BOMBAY HIGH COURT - ORIGINAL SIDE,BOMBAY
M/S AJAY DEEP CONSTRUCTION PVT.LTD – Appellant
Versus
MAHARASHTRA STATE POLICE HJOUSING and WELFARE CORPN. LTD – Respondent
S 1418/2003
sat
S 1418-2003.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
SUIT NO. 1418 OF 2003
M/s.Ajay Deep Construction Pvt.Ltd.
...Plaintiff
vs.
Maharashtra State Police Housing & Welfare
Corporation Ltd.
...Defendants
Mr.Devrat Singh with Mr.Arthav Sanghvi i/b. Praxis Legal for Plaintiff.
Mr.Narayan Sahu with Ms.Khursheed Vajifdar and Ms.Rahat Kalpatri i/b.
Legasis Partners for Defendants.
CORAM : S.C. GUPTE, J.
DATE : 28 JUNE 2021
JUDGMENT :
The Plaintiff has filed the present suit for recovery of
Rs.1,09,78,024 together with pendente lite and post decree interest. The
claim arises out of a construction contract.
2
The Defendants had invited tenders for construction of 650
quarters for policemen of SRPF Group IX at Amravati, with infrastructural
amenities. The Plaintiff was the successful bidder. The construction
contract was evidenced by work order dated 7 November 1996 and a
formal contract agreement of the same date, i.e. 7 November 1996. Under
the contract, the date of commencement of work was 7 November 1996,
whereas the time for completion of the contract work was 36 months.
Based on the revised quantum of scope of work, the original contract value
of Rs.15,29,54,891 was revised by the Defendants to Rs.21,50,35,706. The
original stipulated date of completion was extended upto 19 December
1999. These facts are not in dispute. It is also not in dispute that the
1 / 20
sat
S 1418-2003.doc
Plaintiff completed the entire work within the stipulated date of
completion. There is no dispute as to the quality of the work carried out by
the Plaintiff. The bills submitted by the Plaintiff from time to time, both as
running bills and as final bill, were recommended for payment by the
project management consultant, whose job was to oversee the work. The
grievance of the Plaintiff pertains to three individual items of work for
which payment was not made by the Defendants and a claim for excess
amount recovered by the Defendants from mobilisation advance given by
the Defendants to the Plaintiff and diverse claims of interest, i.e. interest on
delayed payments on three items, namely, (i) running account bills, which
were paid by the Defendants with delay, (ii) Escalation bills (labour,
material, POL) paid with delay, and (iii) Escalation bills (star rate) paid
with delay, and interest till filing of the suit on unpaid amounts.
3
The claims are contested by the Defendants on merits. So far
as the unpaid items of work are concerned, it is the case of the Defendants
that the amounts were not due or payable having regard to the terms of the
contract. So far as the claim for amount of interest recovered from
mobilisation advance is concerned, it is contested by the Defendants on
merits on the basis of the relevant stipulation in the construction contract.
As regards interest for delayed payments, it is the case of the Defendants
that there was no stipulated date of payment save and except for the final
bill; the period mentioned in the contract in respect of payment of running
account bills was an approximate period, requiring simply payment within
the indicated period, if possible.
4
The following issues were framed by this court by its order
dated 10 September 2014:
2 / 20
sat
S 1418-2003.doc
(1) Whether the Plaintiffs prove that they have carried out extra
work under the contract and they were entitled to be paid for
the extra work?
(2) If the answer to issue no.1 is in the affirmative, then at what
rate is the Plaintiffs entitled to be paid?
(3) Whether the Plaintiffs prove that the Defendants delayed in
paying the running account bills and therefore, the Plaintiffs
are entitled to interest on those delayed bills?
(4) If the answer to issue no.3 is in the affirmative, then at what
rate interest is the Plaintiffs entitled to be paid?
(5) Whether the Plaintiffs prove that the Defendants have
deducted excess interest on the mobilisation advance and the
amount of excess
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.