2023 Supreme(Online)(Bom) 1602
HIGH COURT OF BOMBAY
MADHAV J. JAMDAR, J
M/s Man Global Ltd. Mumbai – Appellant
Versus
Mr. Jitendra Jain – Respondent
CIVIL APPEAL | SECOND APPEAL NO.108 OF 2023 | SECOND APPEAL NO. 155 OF 2023 | SECOND APPEAL NO. 667 OF 2022 | SECOND APPEAL NO. 696 OF 2022 | SECOND APPEAL NO.453 OF 2022 | SECOND APPEAL NO. 660 OF 2022 | SECOND APPEAL NO. 685 OF 2022 | SECOND APPEAL NO. 668 OF 2022 | SECOND APPEAL NO.897 OF 2022 | SECOND APPEAL NO.857 OF 2022 | SECOND APPEAL NO.504 OF 2022 | SECOND APPEAL NO.882 OF 2022 | SECOND APPEAL NO.933 OF 2022 | SECOND APPEAL NO.675 OF 2022 | SECOND APPEAL NO.455 OF 2022 | SECOND APPEAL NO.880 OF 2022 | SECOND APPEAL NO.669 OF 2022 | SECOND APPEAL NO.454 OF 2022 | SECOND APPEAL NO.918 OF 2022 | SECOND APPEAL NO.692 OF 2022 | SECOND APPEAL NO. 114 OF 2023 | SECOND APPEAL NO. 109 OF 2023 | SECOND APPEAL NO.138 OF 2023 | SECOND APPEAL NO. 113 OF 2023 | SECOND APPEAL NO. 123 OF 2023 | SECOND APPEAL NO. 119 OF 2023 | SECOND APPEAL NO. 110 OF 2023 | SECOND APPEAL NO.121 OF 2023 | SECOND APPEAL NO. 117 OF 2023 | SECOND APPEAL NO. 112 OF 2023 | SECOND APPEAL NO. 118 OF 2023 | SECOND APPEAL NO. 120 OF 2023 | SECOND APPEAL NO. 115 OF 2023 | SECOND APPEAL NO. 122 OF 2023 | SECOND APPEAL NO. 116 OF 2023 | SECOND APPEAL NO. 111 OF 2023 | SECOND APPEAL NO.307 OF 2023 | SECOND APPEAL NO.313 OF 2023 | SECOND APPEAL (ST) NO.29289 OF 2022 | SECOND APPEAL (ST) NO.29309 OF 2022
Important Points
Subject
Real Estate - Regulatory Compliance
Act Referred
Headnote
(B) Statutory compliance - Requirement under Section 43(5) of the Act mandates pre-deposit for maintainability of appeals against orders concerning consumer rights in real estate - Non-compliance leads to dismissal of appeals. (Paras 54, 56)
Facts of the case:
The appeals involved a challenge to orders passed by the Maharashtra Real Estate Appellate Tribunal concerning delays in possession of real estate projects and the obligation of promoters to pay interest for delays caused, primarily involving actual possession dates significantly later than agreed upon dates in the sale agreements. (Paras 1, 12, 18)
Findings of Court:
The court found that the statutory right to interest is mandatory due to the non-compliance of possession dates as per agreements and established the need for mandating the fulfillment of obligations by promoters under the Act. Further, it emphasized the importance of safeguarding consumer interests in the real estate sector. (Paras 24, 28)
Issues: The key issue addressed was whether the promoters could absolve liability for delays in handing over possession to allottees by attributing said delays to external factors such as government approvals and whether allottees maintained their right to claim interest. (Paras 5, 50)
Ratio Decidendi: The court asserted that the rights established under the Real Estate (Regulation and Development) Act constitute an unqualified right for allottees to claim interest for delays in possession, which cannot be negated due to delays caused by statutory approvals. The obligation to pay interest for delayed possession is obligatory, irrespective of external factors leading to delays. (Paras 20, 25, 47)
Result: All appeals from promoters dismissed; Tribunal's orders affirmed. (Para 58)
Mr. Vineet Naik, Senior Advocate, Mr. Vinod G. Talreja, Avinash Undhare, Gobindram D. Talreja
Mr. Naresh Pai, Ms. Rupali Padgulekar
Mr. Arun Panickar, Mr. Vinay Nair
Mr. Sanjay Chaturvedi, Ms. Pooja Gaikwad, Mr. Nikhil Waje, Mr. Gaurav Beri
Ms. Sana Subedar, Jayesh S. Sapra
Mr. Chandrakant Sutrave, Respondent No.2 in person
“O R D E R
1. Appeal Nos. AT00 600 00000 21201, AT00 600 00000 21257, AT00 600 00000 21262, AT00 600 00000 21267, AT00 600 00000 21270, AT00 600 00000 21273, AT00 600 00000 21279, AT00 600 00000 21286, AT00 600 00000 21287, AT00 600 00000 21300, AT00 600 00000 21313, AT00 600 00000 21315, AT00 600 00000 21323, AT00 600 00000 21326, AT00 600 00000 31743, AT00 600 00000 31599, AT00 600 00000 21269, AT00 600 00000 21243, AT00 600 00000 21299 and AT00 600 00000 21306 are partly allowed.
2. Impugned orders dated 04.02.2019, 09.05.2019 and 19.07.2019 to the extent of Appeals under consideration are set aside.
3. Respondent Promoter is directed to pay Appellants Allottees interest @ 2% above the highest MCLR of the State Bank of India prevailing at the time of passing the impugned orders w.e.f. the next day of the date of possession as stipulated in the agreements for sale till the date of date of actual possession within a period of two months from the date of this order failing which further interest at the aforesaid rate shall be payable by Respondent Promoter on the total amount payable on the date of actual possession till the payment of amount as directed.
4. Liberty to Allottees to approach appropriate Forum for redressal of the grievance relating to parking or compensation therefor and/or any other issue raised in the complaints / Appeals as per law.
5. Promoter to pay costs of Rs.20,000/- to Appellants in each appeal.
6. Copy of this order be sent to the parties and the Authority as per Section 44(4) of RERA."
(Emphasis added)
(vii)The learned Appellate Tribunal passed similar order on 10th December 2022 in 2 Appeals.
13. The Appellant-Promoter has challenged the said common Orders dated 10th June 2022 and two Orders dated 10th December 2022 by filing the first set of 18 Second Appeals under Section 58 of the said Act. As noted herein above, Mr. Vineet Naik, learned Senior Counsel has raised the above referred substantial questions of law in this set of
18 Second Appeals.
14. The relevant details of most of the flat purchasers i.e. the respective Respondents are noted herein below:-
| Sr. No. | Seco nd Appe al No. | Name of Allottee | Flat No. | Build- i ng No. | Phase | Date of Agreement f or sale | Possession as per the Agreemen t | Actual possession | Amt. paid prior to J une 2015 | P e r c e n- t age of t he amt paid |
| 1 | 108/ 2023 | J i t e | ndra Jain 1502 | 5 | 1 | 25/01/2014 | J | une-15 23/11/2019 | ||
| 2 | 109/ 2023 | Amreen Bhimani | 1403 | 2 | 1 | 29/12/2014 | J | une-15 27/09/2019 | 39,58,650 | 95 |
| 3 | 110/ 2023 | Meenal M. Parab | 1602 | 6 | 2 | 05/09/2015 Dec-2016 08/05/2021 | 24,67,202 | 72 | ||
| 4 | 111/ 2023 | Deepak Agarwal | 702 | 5 | 1 | 22/06/2014 | J | une-15 07/12/2019 | 32,23,265 | 95 |
| 5 | 112/ 2023 | Neha Chaube 1106 | 4 | 1 | 13/03/2014 | J | une-15 28/08/2019 | 55,11,216 | 95 | |
| 6 | 113/ 2023 | Brijesh Mathur | 1001 | 3 | 1 | 26/04/2017 | Dec-16 | 05/09/2019 | 47,06,079 | 95 |
| 7 | 114/ 2023 | Sangeeta U. Ved | 1501 | 2 | 1 | 31/12/2013 | J | une-15 09/11/2019 |
| 8 | 115/ 2023 | Azim Qureshi 1101 | 4 | 1 | 18/02/2014 | J | une-15 02/09/2019 | 38,43,938 | 95 | |
| 9 | 116/ 2023 | Sadiqali Mankar | 1103 | 2 | 1 | 21/04/2014 | J | une-15 04/10/2019 | 1,28,52,090 | 100 |
| Sadiqali Mankar | 1703 | 2 | 1 | 21/04/2014 | J | une-15 04/10/2019 | ||||
| 10 117/ 2023 | Rakesh H. Parmar | 202 | 2 | 1 | 14/10/2013 | J | une-15 09/09/2019 | 22,22,570 | 95 | |
| 11 118/ 2023 | Rakesh Kumar Jha | 203 | 5 | 1 | 25/02/2015 | J | une-15 17/10/2019 | 43,35,827 | 95 | |
| 12 119/ 2023 | Simin Aasif | 1902 | 5 | 1 | 17/12/2014 | J | une-15 04/09/2019 | 39,97,100 | 95 | |
| 13 120/ 2023 | J i t e | ndra Jain 1501 | 5 | 1 | 25/01/2014 | J | une-15 23/11/2019 | |||
| 14 121/ 2023 | Vikas Khanna 1003 | 4 | 1 | 25/11/2013 | J | une-15 03/11/2019 | 40,38,654 | 95 | ||
| 15 122/ 2023 | Anthony D'Souza | 2101 | 2 | 1 | 31/12/2013 | J | une-15 05/09/2019 | 54,17,098 | 95 | |
| 16 123/ 2023 | Monali C. Sutrave | 1101 | 5 | 1 | 31/07/2010 14 Jan-15 03/12/2019 41,72,883/- | 95 | ||||
| 17 138/ 2023 | Nikhil K. Kathane | 803 | 8 | 1 | 28/05/2015 | Dec-16 | 05/10/2019 | 41,98,011 | 94 | |
| 18 155/ 2023 | Alok Ravindranath Chaturvedi | 1404 | 4 | 1 | 29/01/2014 | J | une-15 23/11/2019 | 34,42,400 | 95 |
Even, if details in a few cases are not furnished, it is undisputed that even in those cases the respective allottees have made substantial payments.
15. The First substantial question of law raised by Mr. Naik, learned Senior Counsel appearing for the Appellant, is as follows :
First substantial question of law:
Whether delay in handing over possession on account of delays