2023 Supreme(Online)(Bom) 1596
HIGH COURT OF BOMBAY
MADHAV J. JAMDAR, J
M/s Man Global Ltd. Mumbai – Appellant
Versus
Mr. Jitendra Jain – Respondent
SECOND APPEAL NO.108 OF 2023 | SECOND APPEAL NO. 155 OF 2023 | SECOND APPEAL NO. 667 OF 2022 | SECOND APPEAL NO. 696 OF 2022 | SECOND APPEAL NO.453 OF 2022 | SECOND APPEAL NO. 660 OF 2022 | SECOND APPEAL NO. 685 OF 2022 | SECOND APPEAL NO. 668 OF 2022 | SECOND APPEAL NO.897 OF 2022 | SECOND APPEAL NO.857 OF 2022 | SECOND APPEAL NO.504 OF 2022 | SECOND APPEAL NO.882 OF 2022 | SECOND APPEAL NO.933 OF 2022 | SECOND APPEAL NO. 455 OF 2022 | SECOND APPEAL NO. 880 OF 2022 | SECOND APPEAL NO. 669 OF 2022 | SECOND APPEAL NO. 918 OF 2022 | SECOND APPEAL NO. 114 OF 2023 | SECOND APPEAL NO. 109 OF 2023 | SECOND APPEAL NO.138 OF 2023 | SECOND APPEAL NO. 113 OF 2023 | SECOND APPEAL NO. 123 OF 2023 | SECOND APPEAL NO. 119 OF 2023 | SECOND APPEAL NO. 110 OF 2023 | SECOND APPEAL NO.121 OF 2023 | SECOND APPEAL NO. 117 OF 2023 | SECOND APPEAL NO. 112 OF 2023 | SECOND APPEAL NO. 118 OF 2023 | SECOND APPEAL NO. 120 OF 2023 | SECOND APPEAL NO. 115 OF 2023 | SECOND APPEAL NO. 122 OF 2023 | SECOND APPEAL NO. 116 OF 2023 | SECOND APPEAL NO. 111 OF 2023 | SECOND APPEAL NO.307 OF 2023 | SECOND APPEAL NO.313 OF 2023 | SECOND APPEAL (ST) NO.29289 OF 2022 | SECOND APPEAL (ST) NO.29309 OF 2022
Important Points
Subject
Real Estate - Regulatory Compliance
Act Referred
Headnote
(B) Legal Standards - The court confirmed that the requirement to deposit amounts as per Section 43(5) before appealing is mandatory, ensuring compliance is observed to uphold the proceedings fairly. No exceptions can apply in cases involving delays exceeding four years. (Paras 56, 57)
Facts of the case:
A series of Second Appeals initiated by the promoter against orders from the Maharashtra Real Estate Appellate Tribunal favoring various allottees due to delays in possession, citing reasons including the need for municipal approvals. The allottees consistently sought interest for late possession according to the agreements, with the original possession dates spanning from June 2015 to December 2016, with actual handover occurring significantly later. (Paras 1-3, 12)
Findings of Court:
Interest was awarded to allottees effective immediately following the agreed possession date, and the failure of the promoter to comply with timelines resulted in no viable defense against claims raised. The tribunal's decisions were upheld, emphasizing the importance of adherence to timelines stipulated within the agreements for the developer's obligations. (Paras 10-11, 22)
Issues: The primary inquiries addressed were whether delays in delivery of possession due to pending municipal clearances can be attributed to the promoter, and whether extensions in delivery dates absolve the obligation to pay interest to the allottees. (Paras 5, 6)
Ratio Decidendi: The court ruled that statutory regulations do not mitigate a promoter’s contractual obligations. Even with regulatory delays, the entitlement of allottees to timely possession remains intact, providing them an unqualified right to interest on delayed handovers. The court emphasized compliance with RERA provisions, asserting that the prescribed timelines must be honored irrespective of external delays influenced by regulatory bodies. (Paras 19-27, 31, 53)
Result: Second Appeals dismissed; Appellant mandated to pay due interests. No orders on costs due to dismissal. (Paras 57)
For the Appellants/Petitioners:Mr. Vineet Naik, Senior Advocate, Mr. Vinod G. Talreja, Avinash Undhare, Mr. Gobindram D. Talreja
For the Respondents: Mr. Naresh Pai, Ms. Rupali Padgulekar, Mr. Arun Panickar, Mr. Vinay Nair, Mr. Sanjay Chaturvedi, Ms. Pooja Gaikwad, Ms. Sana Subedar, Mr. Jayesh S. Sapra, Mr. Chandrakant Sutrave
“O R D E R
1. Appeal Nos. AT00 600 00000 21201, AT00 600 00000 21257, AT00 600 00000 21262, AT00 600 00000 21267, AT00 600 00000 21270, AT00 600 00000 21273, AT00 600 00000 21279, AT00 600 00000 21286, AT00 600 00000 21287, AT00 600 00000 21300, AT00 600 00000 21313, AT00 600 00000 21315, AT00 600 00000 21323, AT00 600 00000 21326, AT00 600 00000 31743, AT00 600 00000 31599, AT00 600 00000 21269, AT00 600 00000 21243, AT00 600 00000 21299 and AT00 600 00000 21306 are partly allowed.
2. Impugned orders dated 04.02.2019, 09.05.2019 and 19.07.2019 to the extent of Appeals under consideration are set aside.
3. Respondent Promoter is directed to pay Appellants Allottees interest @ 2% above the highest MCLR of the State Bank of India prevailing at the time of passing the impugned orders w.e.f. the next day of the date of possession as stipulated in the agreements for sale till the date of date of actual possession within a period of two months from the date of this order failing which further interest at the aforesaid rate shall be payable by Respondent Promoter on the total amount payable on the date of actual possession till the payment of amount as directed.
4. Liberty to Allottees to approach appropriate Forum for redressal of the grievance relating to parking or compensation therefor and/or any other issue raised in the complaints / Appeals as per law.
5. Promoter to pay costs of Rs.20,000/- to Appellants in each appeal.
6. Copy of this order be sent to the parties and the Authority as per Section 44(4) of RERA."
(Emphasis added)
(vii)The learned Appellate Tribunal passed similar order on
10th December 2022 in 2 Appeals.
13. The Appellant-Promoter has challenged the said common Orders dated 10th June 2022 and two Orders dated 10th December 2022 by filing the first set of 18 Second Appeals under Section 58 of the said Act. As noted herein above, Mr. Vineet Naik, learned Senior Counsel has raised the above referred substantial questions of law in this set of
| Sr. No. | Second Appeal No. | Name of Allottee | Flat No. | Building No. | Phase | Date of Agreement for Sale | Possession as per the Agreement | Actual Possession | Amount Paid Prior to June 2015 | Percentage of the Amount Paid | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 108/2023 | Jitendra Jain | 1502 | 5 | 1 | 25/01/2014 | June-15 | 23/11/2019 | ||||
| 2 | 109/2023 | Amreen Bhimani | 1403 | 2 | 1 | 29/12/2014 | June-15 | 27/09/2019 | 39,58,650 | 95 | ||
| 3 | 110/2023 | Meenal M. Parab | 1602 | 6 | 2 | 05/09/2015 | Dec-2016 | 08/05/2021 | 24,67,202 | 72 | ||
| 4 | 111/2023 | Deepak Agarwal | 702 | 5 | 1 | 22/06/2014 | June-15 | 07/12/2019 | 32,23,265 | 95 | ||
| 5 | 112/2023 | Neha Chaube | 1106 | 4 | 1 | 13/03/2014 | June-15 | 28/08/2019 | 55,11,216 | 95 | ||
| 6 | 113/2023 | Brijesh Mathur | 1001 | 3 | 1 | 26/04/2017 | Dec-16 | 05/09/2019 | 47,06,079 | 95 | ||
| 7 | 114/2023 | Sangeeta U. Ved | 1501 | 2 | 1 | 31/12/2013 | June-15 | 09/11/2019 | ||||
| 8 | 115/2023 | Azim Qureshi | 1101 | 4 | 1 | 18/02/2014 | June-15 | 02/09/2019 | 38,43,938 | 95 | ||
| 9 | 116/2023 | Sadiqali Mankar | 1103 | 2 | 1 | 21/04/2014 | June-15 | 04/10/2019 | 1,28,52,090 | 100 | ||
| Sadiqali Mankar | 1703 | 2 | 1 | 21/04/2014 | June-15 | 04/10/2019 | ||||||
| 10 | 117/2023 | Rakesh H. Parmar | 202 | 2 | 1 | 14/10/2013 | June-15 | 09/09/2019 | 22,22,570 | 95 | ||
| 11 | 118/2023 | Rakesh Kumar Jha | 203 | 5 | 1 | 25/02/2015 | June-15 | 17/10/2019 | 43,35,827 | 95 | ||
| 12 | 119/2023 | Simin Aasif | 1902 | 5 | 1 | 17/12/2014 | June-15 | 04/09/2019 | 39,97,100 | 95 | ||
| 13 | 120/2023 | Jitendra Jain | 1501 | 5 | 1 | 25/01/2014 | June-15 | 23/11/2019 | ||||
| 14 | 121/2023 | Vikas Khanna | 1003 | 4 | 1 | 25/11/2013 | June-15 | 03/11/2019 | 40,38,654 | 95 | ||
| 15 | 122/2023 | Anthony D'Souza | 2101 | 2 | 1 | 31/12/2013 | June-15 | 05/09/2019 | 54,17,098 | 95 | ||
| 16 | 123/2023 | Monali C. Sutrave | 1101 | 5 | 1 | 31/07/2010 | 14 Jan-15 | 03/12/2019 | 41,72,883/- | 95 | ||
| 17 | 138/2023 | Nikhil K. Kathane | 803 | 8 | 1 | 28/05/2015 | Dec-16 | 05/10/2019 | 41,98,011 | 94 | ||
| 18 | 155/2023 | Alok Ravindranath Chaturvedi | 1404 | 4 | 1 | 29/01/2014 | June-15 | 23/11/2019 | 34,42,400 | 95 |
18 Second Appeals.
14. The relevant details of most of the flat purchasers i.e. the respective Respondents are noted herein below:-
| Sr. No. | Second Appeal No. | Name of Allottee | Flat No. | Building No. | Phase | Date of Agreement for Sale | Possession as per the Agreement | Actual Possession | Amt. Paid Prior to June 2015 | Percentage of the Amt Paid | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 108/2023 | Jitendra Jain | 1502 | 5 | 1 | 25/01/2014 | June-15 | 23/11/2019 | ||||
| 2 | 109/2023 | Amreen Bhimani | 1403 | 2 | 1 | 29/12/2014 | June-15 | 27/09/2019 | 39,58,650 | 95 | ||
| 3 | 110/2023 | Meenal M. Parab | 1602 | 6 | 2 | 05/09/2015 | Dec-2016 | 08/05/2021 | 24,67,202 | 72 | ||
| 4 | 111/2023 | Deepak Agarwal | 702 | 5 | 1 | 22/06/2014 | June-15 | 07/12/2019 | 32,23 | |||