Writ Petition No.8440 of 2022 | Writ Petition No.2755 of 2022 | Writ Petition No.8431 of 2022 | Writ Petition No.8432 of 2022 | Writ Petition No.8430 of 2022 | Writ Petition No.8433 of 2022 | Writ Petition No.8434 of 2022 | Writ Petition No.8435 of 2022 | Writ Petition No.2758 of 2022 | Writ Petition No.8436 of 2022 | Writ Petition No.8437 of 2022 | Writ Petition No.8438 of 2022 | Writ Petition No.8439 of 2022 | Writ Petition No.2757 of 2022
For the Appellants/Petitioners: Mr. Tushal Sonawane, Ms. Pooja Satpute
For the Respondents: Mr. S.D. Rayrikar, Ms. G.S. Godbole, Ms. Manjiri Parasnis
Proceedings under Section 101 of the Maharashtra Co-operative Societies Act are inappropriate for resolving genuine disputes regarding the authenticity of documents; such matters must be adjudicated under Section 91.
Headnote:(A) Maharashtra Co-operative Societies Act, 1960 - Section 101 - Recovery of dues - Petitions challenging orders remanding recovery proceedings for fresh decision by Assistant Registrar, wherein claims of borrowers about repayment and issuance of 'No Dues Certificates' were disregarded - Court found remand inappropriate as Registrar lacked jurisdiction to resolve disputes regarding genuineness of documents, highlighting need for proceedings under Section 91 instead. (Paras 21-25)
(B) Jurisdiction and Procedure - Summary proceedings under Section 101 are limited to quantification of dues without adjudicating disputed facts; complex issues necessitate recourse to Section 91 where evidence can be presented. (Paras 18-20)
Facts of the case:
Borrowers claimed complete repayment of loans with 'No Dues Certificates' and Release Deeds issued by Credit Society. Society later alleged these documents were unauthorized and sought recovery under Section 101, which Assistant Registrar initially rejected. Following appeal, orders were remanded back for reconsideration.
Findings of Court:
The orders of remand were quashed as the Assistant Registrar could not decide on genuine disputes and should not proceed under Section 101 for recovery claims.
Issues: Whether proceedings under Section 101 were appropriate given the existence of disputed facts relating to document validity and loan repayment.
Ratio Decidendi: The court ruled the Assistant Registrar lacked authority to adjudicate on disputes regarding document authenticity; hence, a cooperative dispute under Section 91 was mandated for proper resolution.
Result: Writ petitions allowed; remand orders quashed.
| Table of Content |
|---|
| 1. challenge to recovery process based on payment claims. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7) |
| 2. enquiry limitations under section 101 versus section 91. (Para 10 , 15 , 18 , 19 , 20) |
| 3. arguments over procedural validity and authority. (Para 11 , 12) |
| 4. distinction between registrar's limited scope and court's expansive jurisdiction. (Para 16 , 17) |
| 5. court's ruling on remand and procedural fairness. (Para 22 , 23 , 24 , 25) |
JUDGMENT
1. These Petitions are filed challenging orders dated 31st December 2021 passed by the Divisional Joint Registrar allowing Revision Applications filed by Respondent Credit Society and remanding the proceedings before the Assistant Registrar for a fresh decision. The Assistant Registrar had rejected proceedings filed by Respondent-Credit Society for issuance of recovery certificate under Section 101 of the Maharashtra Co-operative Societies Act 1960 (Act of 1960).
2. Petitioners are borrowers who have availed credit facilities from Respondent No.3-Credit Society. They claim that the entire amount due under said Credit facilities have been repaid by them with interest, on account of which the Credit Society issued various ‘No Dues Certificates’ to Petitioners. It is further contended that after issuance of ‘No Dues Certificates’, the Respondent-Credit Society executed Release Deeds in their favour. Facts in all the Petitions are similar. For brevity, facts in Writ Petition No.8440/2022 are narrated as follows.
3. Chatrapati Sambhaji Maharaj Sahakari Patsanstha, Baramati (Respondent No.3) is a Credit Society registered under the provisions of the Act of 1960. Petitioners are members of the Respondent-Society which granted and disbursed loan of Rs. 14,000,00/- to them for business purposes. In pursuance of the loan transaction, Petitioners executed promissory note, acceptance letters, consent letter of sureties, loan agreement, etc. in favour of the Respondent- Society. Petitioners also offered agricultural property admeasuring 10 Acre out of Survey No.45/5/B at Baramati as well as residential Unit No.3 in the building ‘Kate Pride’ at Baramati, District Pune towards security for the loan.
Petitioners also executed Mortgage Deed in favour of the Respondent-Society on 28th August 2015, which came to be registered in the office of Sub-Registrar of Assurances, Baramati.
4. Petitioners claim that they have repaid the entire amount availed by them towards loan along with interest to the Respondent-Society. They contend that the Respondent- Society accordingly issued ‘No Dues Certificate’ on 24th October 2016 certifying that no amount was due or payable by the Petitioners in the loan account. Petitioners also claim that on account of repayment of the entire loan amount, Respondent-Society executed Release Deed dated 11th July 2016 in favour of the Petitioners releasing their charge over the two mortgaged properties.
5. The Respondent-Society later claimed that the Petitioners had neither repaid the loan amount, nor any ‘No Dues Certificate’ was issued by the Society. The Respondent- Society also denied having executed any Release Deed in favour of Petitioners. The Respondent-Society claims that its Branch Manager unauthorizedly issued ‘No Dues Certificate’ and executed Release Deed without any decision to that effect being taken in the managing committee meeting of the Society.
6. The Respondent-Society has accordingly filed Special Civil Suit No.51/2019 seeking a declaration that various Release Deeds unauthorizedly executed by the Branch Manager are ab initio void and not binding on the Respondent- Society. It has also sought a declaration that it continues to have the charge over mortgaged properties in pursuance of various Mortgage Deeds executed in his favour. Some of the subsequent Sale Deeds executed by the borrowers/guarantors/mortgagor are also sought to be cancelled in the said suit. The Respondent-Society sought temporary injunction against the Defendants in Special Civil Suit No.51/2019 to re