2024 Supreme(Online)(Bom) 10667

HIGH COURT OF BOMBAY
HON'BLE SHRI JUSTICE SANDEEP V. MARNE
BALAJI CONSTRUCTION COMPANY – Appellant
Versus
ANJUSHA AJIT KADAM – Respondent
IA/366/2024



2024:BHC-AS:8201 IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION SECOND APPEAL NO. 731 OF 2023 WITH INTERIM APPLICATION NO. 18286 OF 2023 IN SECOND APPEAL NO. 731 OF 2023 WITH INTERIM APPLICATION NO. 366 OF 2024 Balaji Construction Company ... Appellant Versus Anjusha Ajit Kadam & Ors. ... Respondents

1 WITH SECOND APPEAL NO. 727 OF 2023 WITH INTERIM APPLICATION NO. 18143 OF 2023 IN SECOND APPEAL NO. 727 OF 2023 Balaji Construction Company ... Appellant Versus Jayantilal Makwana ... Respondent WITH SECOND APPEAL NO. 734 OF 2023 WITH INTERIM APPLICATION NO. 18290 OF 2023 IN SECOND APPEAL NO. 734 OF 2023 Balaji Construction Company ... Appellant Versus Vikram B Shah ... Respondent

1/20 Digitaly signed by MANE M SOA NN AE LI SONALIDILIP DILIP D 20a 2te 4: .02.21

00:04:24 +0530 WITH SECOND APPEAL NO. 737 OF 2023 WITH INTERIM APPLICATION NO. 18295 OF 2023 IN SECOND APPEAL NO. 737 OF 2023 Balaji Construction Company ... Appellant Versus Achala Abhijit Patil and Anr. ... Respondents WITH SECOND APPEAL NO. 736 OF 2023 WITH INTERIM APPLICATION NO. 18294 OF 2023 IN SECOND APPEAL NO. 736 OF 2023 WITH INTERIM APPLICATION NO. 364 OF 2024 Balaji Construction Company ... Appellant Versus Prashant Sukhadev Mahajan ... Respondent WITH SECOND APPEAL NO. 733 OF 2023 WITH INTERIM APPLICATION NO. 18289 OF 2023 IN SECOND APPEAL NO. 733 OF 2023 Balaji Construction Company ... Appellant Versus Chintan Mahesh Shah ... Respondent WITH SECOND APPEAL NO. 735 OF 2023 WITH INTERIM APPLICATION NO. 18288 OF 2023 IN SECOND APPEAL NO. 735 OF 2023 WITH INTERIM APPLICATION (ST) NO. 3239 OF 2024 IN SECOND APPEAL NO. 735 OF 2023 Balaji Construction Company ... Appellant Versus Shashikumar Mishra ... Respondent WITH SECOND APPEAL NO. 732 OF 2023 WITH INTERIM APPLICATION NO. 18287 OF 2023 IN SECOND APPEAL NO. 732 OF 2023 Balaji Construction Company ... Appellant Versus Hetal B Shah ... Respondent …

Mr. Gauraj Shah a/w Mr. Keyur Adhvaryu i/b Mr. Yatin R. Shah, for the Appellants in all Second Appeals.

Mr. Harshad Bhadbhade a/w Ms. Arya Sapre, for Respondents in SA/731/2023, SA/734/2023, SA/737/2023, SA/736/2023, SA/733/2023, SA/735/2023, SA/732/2023.

Mr. Mutahhar Khan a/w Ms. Nehaa Shah i/b Mr. Dhiren H. Shah, for Respondent in SA/727/2023.

…

CORAM : SANDEEP V. MARNE J.

RESERVED ON : 6 FEBRUARY 2024.

PRONOUNCED ON : 20 FEBRUARY 2024.

JUDGMENT :-

1) These Second Appeals filed by the Appellant challenge common Order dated 27 October 2023 passed by Maharashtra Real Estate Appellate Tribunal (Appellate Tribunal) directing Appellant to pre-deposit the specified amounts towards compliance with proviso to Section 43 (5) of Real Estate (Regulation and Development) Act, 2016 (RERA).

2) Briefly stated, facts of the case are that Appellant is a promoter who is developing a project named ‘Gajanan Plaza’. Respondents are the allotees of various flats, with whom the promoter has executed Agreements for Sale agreeing to deliver possession of respective flats on various agreed dates. Respondents approached Maharashtra Real Estate Regulatory Authority (MahaRERA) by filing their respective complaints against Appellant seeking possession of their respective flats along with interest for delayed delivery of possession. MahaRERA proceeded to allow the complaints filed by Respondents by Order dated 31 October 2022 and set aside the termination letters issued by Appellants terminating the allotment letter/agreements with a further direction for execution of supplementary agreements in accordance with terms and conditions of the MOU executed with other allotees of the project. Appellant was directed to handover possession of commercial premises allotted to the Respondents as per supplementary agreements to be executed with them. Appellant was further directed to pay interest for delayed possession to the Respondents from 1 April 2019 till grant of possession. However, MahaRERA directed that the amount of interest shall be paid by the Appellant to the Respondents after obtaining f