SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Article Pause Article
judgment-img

2022 Supreme(Online)(Bom) 3081

HIGH COURT OF BOMBAY
HON'BLE SHRI JUSTICE A.S. CHANDURKARHON'BLE SMT. JUSTICE MUKULIKA SHRIKANT JAWALKAR
M/S. GUPTA FREIGHT CARRIER THR. PROP. SHRI. VISHAL PANNALAL GUPTA – Appellant
Versus
THE EXECUTIVE DIRECTOR WEST ZONE MUMBAI AND ANOTHER – Respondent
WP/2055/2021



IN THE HIGH COURT OF JUDICATURE AT BOMBAY NAGPUR BENCH, NAGPUR.

WRIT PETITION NO.2055 OF 2021 M/s. Gupta Freight Carrier, through its Proprietor-Shri Vishal Pannalal Gupta, Near Pathyapustak Office, Pravin Nagar, Amravati.

Tq. And District Amravati.

.... PETITIONER // V E R S U S //

1. The Executive Director, West Zone, Zonal Office (West), Third Floor, Datta Pada Road, Rajendra Nagar, Boriwali(E), Mumbai-400 066

2. Food Corporation of India (FCI), Through its General Manager, Having its regional office at Chetak Bhavan, Maharana Pratap Nagar, Bhopal-462 011.

... RESPONDENTS ------------------------------------------------------------------------------------------------------

Shri S.P.Dharmadhikari, Senior Advocate with Shri S.M.Vaishnav, Advocate for petitioner.

Shri S.R.Deshpande, Advocate for respondents.

------------------------------------------------------------------------------------------------------

CORAM : A. S. CHANDURKAR AND SMT. M.S.JAWALKAR, JJ.

ARGUMENTS WERE HEARD ON :08/03/2022 JUDGMENT IS PRONOUNCED ON : 05/04/2022 J U D G M E N T (Per : A.S.CHANDURKAR, J.)

RULE. Rule made returnable forthwith and heard the learned counsel for the parties.

2. The challenge raised in this writ petition is to the order dated 02.03.2021 passed by the Food Corporation of India (for short, FCI) terminating the contract that was issued to the petitioner for transportation of foodgrains from Hoshangabad (Madhya Pradesh) to Badnera (Maharashtra) as well as from Hoshangabad to Dhamangaon (Maharashtra) for a period of two years. Besides such termination of the contract, the earnest money deposited by the petitioner has been forfeited. The petitioner has also been debarred from participating in any future tender of the FCI for a period of five years. The grievance raised by the petitioner against the aforesaid order was considered by the Grievance Redressal Committee constituted by the FCI and the same was also rejected on 28.05.2021. That order is also under challenge in this writ petition.

3. The facts relevant for adjudicating the writ petition are that on 13.10.2019 a tender notice was issued by the FCI inviting bids for transportation of foodgrains from Hoshangabad (MP) to Badnera(MS)

and Hoshangabad (MP) to Dhamangaon(MS). The bid of the petitioner being the lowest, it was accepted by the FCI and on 20.03.2020 work order was issued to it. As per Clause 7 of the Model Tender Format (MTF) that was published by the FCI, a successful bidder was required within a period of fifteen working days of acceptance of the tender to furnish security deposit for due performance of the obligations under the contract. As per that Clause on failure to submit such Bank Guarantee within a period of fifteen working days of acceptance of tender, a further extension of fifteen working days was permissible subject to levy of penalty. In the event of further failure to submit the Bank Guarantee within the extended period, it was stated that the contract would be summarily terminated and earnest money was liable to be forfeited. The contractor was also to be debarred from participating in any future tender of the FCI for a period of five years. On 01.10.2020 the FCI issued notice to the petitioner in which it was stated that on 08.06.2020 the petitioner had submitted various documents but the Bank Guarantees had not been furnished. It was stated that submission of the Bank Guarantee was a pre-requisite of the contract and the same was required as per Clause 7 of the MTF. In view of Covid-2019 pandemic, the FCI by that notice granted final opportunity to furnish Bank Guarantees within a period of three days of issuance of the said notice failing which it was stated that a decision would be taken as per the provisions of the MTF.

4. The petitioner on 28.12.2020 replied to the aforesaid notice and conveyed to the FCI various difficulties faced by it as the reason for not being able to furnish the Bank Guarantees. It also referred to an order passed by the Collector, Amrav

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top