2023 Supreme(Online)(Bom) 26563

HIGH COURT OF BOMBAY
HON'BLE SHRI JUSTICE N. J. JAMADAR
SHREE KHAMBHATI MODH VANIK SAMAJ THR. TRUSTEE KAUSHIK H CHANDAWALLA – Appellant
Versus
THE STATE OF MAHARASHTRA THR. GP AND ORS – Respondent
WP/13384/2022



2023:BHC-AS:38570 IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION WRIT PETITION NO.13384 OF 2022 Shree Khambhati Modh Vanik Samaj ...Petitioner vs.

The State of Maharashtra and Others ...Respondents Mr. Vishal Kanade a/w. Mr. Shashikant Chaudhari, Ms. Tanaya Patankar, Ms. Varsha Mishra, Ms. Snehal Chaudhari, Ms. Pranot Pawar and Ms. Preshita Parab i/b. Maharashtra Law Associates, for the Petitioner.

Mr. C.D. Mali, AGP for the State.

Ms. Charmie Gandhi a/w. Mr. Chirag Unadkat, for Respondent Nos.

4 and 5.

Mr. Shravan Giri, for Respondent No. 2.

Ms. P.M. Bhansali a/w. Ms. Dharini Jain, for Respondent Nos. 6 & 7.

Mr. Aditya Pimple and Mr. Sangharsh Jadhav i/b. Mr. Naresh Pai, for Respondent No. 8.

Mr. Aseem Naphade a/w. Mr. Sulaiman Bhimani i/b. The Law Suits, for Respondent No. 9.

CORAM : N. J. JAMADAR, J.

RESERVED ON : AUGUST 3, 2023 PRONOUNCED ON : DECEMBER 20, 2023 JUDGMENT :

1. Rule. Rule made returnable forthwith. With the consent of the parties, heard finally at the stage of admission.

2. The challenge in this petition is to an order dated 6th September, 2022 passed by the learned Charity Commissioner on Applications (Exhibits 7, 10, 14, 17, 24 and 29) in Application No.

CC/16/2021/Misc filed by respondent Nos. 2 to 9 seeking intervention in the said applications preferred by the petitioner/trust for grant of permission under section 36(1)(a) of the Maharashtra Public Trust Act, 1951 (the Trust Act, 1951), whereby the learned Charity Commissioner was persuaded to allow the intervention applications and direct the petitioner to add the interveners as respondents to the said application.

3. The background facts leading to this petition which assails seemingly an innocuous order of intervention deserves to be noted in a little detail to appreciate the legality, appropriate and correctness thereof, in a proper perspective.

a} The petitioner is a public charitable trust registered under the Public Trust Act, 1950. The petitioner/trust owns a property “Samaj Darshan” situated at CTS No. 84B and 84C at Kandivali(w), Mumbai (the subject property). The petitioner/trust had resolved to redevelop the subject property.

b} An application No. 115 of 2014 was filed before the Charity Commissioner under section 36 of the Trust Act, 1950 seeking permission to redevelop the property and enter into a Development cum Sale Agreement with M/s. Bhakti Enterprises, the respondent No. 2. By an order dated 8th June, 2015, the learned Charity Commissioner was persuaded to accord sanction under section 36(1)(a) of the Act, 1950 to the trustees of the petitioner-trust to redevelop the trust property. It was, inter alia, noted that the decision of the trust to redevelop the trust property was justifiable. Pursuant thereto, the petitioner/trust and respondent No. 2 entered into a Development Agreement on 7th December, 2015.

c} Asserting that the respondent No. 2 committed breach of terms and conditions of the Development Agreement, the petitioner terminated the Development Agreement vide notice dated 15th July, 2017.

d} In the wake of the dispute, the petitioner instituted Commercial Arbitration Petition No. 147 of 2018. In the said petition by moving Commercial Arbitration Application No. 54 of 2018 the petitioner sought interim relief. In the said proceeding on 21st February, 2019 the consent terms were executed between the petitioner and respondent No. 2. Pursuant thereto, by an order dated 3rd April, 2019 Commercial Arbitration Petition No. 147 of

2018 came to be disposed, inter alia, on the following terms :-

I. The Court Receiver, High Court, Bombay as appointed as receiver of the suit project by an order dated 28 August 2018 stands discharged, subject to payment of cost as set out by the Court Receiver which shall be paid by the respondent within a period of two weeks of such intimation.

II. The Court Receiver shall accordingly hand over the suit project to the respondent within one week from today and place a report to that effect on the pr

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top