2025 Supreme(Online)(Bom) 6066
BOMBAY HIGH COURT
R. N. Laddha, J
Mr. Dhanesh Nathalal Vora – Appellant
Versus
State of Maharashtra – Respondent
Criminal Writ Petition No.3050 of 2022
For the Appellants/Petitioners: Mr Ashok Kumar Dubey
For the Respondents: Mr RM Pethe, APP for State
Prosecutions under penal statutes like the MMC Act require solid evidence linking actions to violations of explicit statutory provisions, which were absent in this case.
Headnote:(A) Mumbai Municipal Corporation Act, 1888 - Sections 381-A and 471 - Challenge to issuance of process by Metropolitan Magistrate in a complaint alleging unauthorized construction - The allegations did not satisfy the requirements for violation of the specified sections. (Paras 3, 8)
(B) Malicious Prosecution - The prosecution initiation was linked to disputes involving the builder and lacked necessary legislative foundation for proceeding against the petitioner. (Paras 5, 6, 8)
Facts of the case:
The petition challenged an order issued against the petitioner regarding an alleged unauthorized water tank, which was claimed to pose mosquito breeding issues.
Findings of Court:
The court concluded that the essential elements for prosecution under the MMC Act were not present and the allegations did not fulfill legal requirements.
Issues: The main issue was whether the petitioner violated Section 381-A of the MMC Act.
Ratio Decidendi: The court reasoned that allegations of unauthorized construction were unfounded and did not warrant prosecution per the stipulations of the MMC Act.
Result: Petition allowed, process quashed.
| Table of Content |
|---|
| 1. the complaint alleges unauthorized construction. (Para 2 , 3) |
| 2. the prosecution arises from disputes among society members. (Para 4 , 5) |
| 3. inspection and complaint lacked necessary details for prosecution. (Para 6 , 7) |
| 4. prosecution for violation of municipal act sections is not supported by allegations. (Para 8) |
| 5. petition allowed; magistrate's process quashed. (Para 9) |
Coram : R. N. Laddha, J.
Date : 6 November 2023.
P.C. :
Heard Mr Ashok Kumar Dubey, the learned Counsel appearing on behalf of the petitioner and Mr RM Pethe, the learned Additional Public Prosecutor for the State.
2. The petitioner has challenged the order dated 16.9.2019 passed by the learned Metropolitan Magistrate, 55th Court, Vile Parle, Mumbai, in CC No.555242 under Sections 381-A read with 471 of the Mumbai Municipal Corporation Act, 1888 (for short ‘MMC Act’).
3. It reveals from the record that the Assistant Law Officer of Mumbai Municipal Corporation filed a complaint alleging that the petitioner, who is a member of the society, located near Punjab National Bank, Kandivali (West), Mumbai, kept an unauthorised single LDPE water storage tank in his bathroom. The WC loft was not mosquito-proof, which made it a potential breeding ground for mosquito. The inspection was carried out by Rajendra Sunil Sankhe, who was delegated the powers by the Deputy Municipal Commissioner under Section 68 of the MMC Act. The complaint alleges that the petitioner committed an offence punishable under Section 381-A , read with 471 of the MMC Act. The complaint was filed on 16.9.2019, and on the same day, the learned Magistrate issued a process under Sections 381-A and 471 of the MMC Act. The said order of issuance of a process is under challenge.
4. The learned Counsel for the petitioner submitted that the order itself shows a total non-application of mind on the part of the learned Magistrate. The complaint was filed in a casual manner and was intended to cause harassment to the petitioner, as is evident from the affidavit in reply filed by the respondent in other companion matters.
5. The material placed on record demonstrates that the inspection was conducted, and the subsequent prosecution was initiated at the request of a particular individual. Learned Counsel for the petitioner submitted that two societies are currently embroiled in a dispute with the builder in question, and there are other pending suits in the City Civil Court at Dindoshi regarding conveyance. The present prosecution is a result of this dispute, and therefore, it is a malicious prosecution.
6. After reviewing the material placed on record, it reveals that the entire process was initiated after the builder filed a complaint with the municipal corporation. The allegations are vague and suggest that an unauthorised storage tank was kept in a non-mosquito-proof condition, which could lead to mosquitoes breeding.
7. In the instant case, the process is issued under Section 381A of the MMC Act, not under Section 381B, which deals with the apprehension of mosquito breeding due to water collection. The learned Counsel for the petitioner stated that the petitioner will take necessary precaution to prevent mosquito breeding. The municipal corporation has the right to inspect the flats to ensure that the flat owners have taken necessary safety precautions. However, this part of the complaint is not relevant to the issuance of the process.
8. The only remaining question is whether Section 381A of the MMC Act has been violated. The allegation is not that the petitioner is drawing water without authorisation and storing it in a water tank. There are no allegations that the storage tank in the flat is causing any damage to the stability of the structure. As per Section 381A of the MMC Act, no new well, tank, pond, cistern or fountain can be dug or constructed without the prior written permission of the Commissioner. However, in this case, there are no allegations that any tank was constructed or that the l