SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1995 Supreme(Online)(Bom) 15

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Unknown, J
Dinshaw and Dinshaw (M/s.) and Others v. Indoswe Engineers Pvt. Ltd.
Special Civil Suit No.215 of 1972



Advocates:
For the Appellants/Petitioners: Unknown
For the Respondents: Unknown

The court upheld that a party may be compensated for work done despite absence of a written contract when the other party benefits, reinforcing principles of unjust enrichment under Section 70 of the Indian Contract Act.

Headnote:(A) Indian Contract Act, 1872 - Section 70 - Appeal against judgment in a civil suit regarding a building contract - Plaintiffs claimed Rs. 32,000/- for work done, alleging non-payment by the defendant for completed work - The trial court found the plaintiffs' work to be substandard and inflated, awarding only Rs. 966.93/- - Plaintiffs appealed, contending they were entitled to amounts for additional work as per accepted estimates - Court framed issues including entitlement to recovery, quality and measurements of work, and contractual obligations -

Findings of Court:
It was held that the plaintiffs did undertake additional work directed by the defendant and were entitled to compensation under Section 70 of the Indian Contract Act, despite some assertions of inflated claims - The court decided that deductions for some errors in measurement were valid, and awarded the plaintiffs Rs. 10,500/- with 6% interest from the date of the suit. (Paras 1, 4, 5, 27, 28)

Facts of the case:
The plaintiffs performed construction works on a contract basis but faced issues with alleged quality and measurement discrepancies from the defendant, leading to non-payment claims totaling Rs. 32,000/-. The dispute resulted in a lawsuit because of these unpaid bills.

Issues: The main issues included determining the validity of claims for payment, quality of work performed, defendants’ alleged objections to measurements, and the overall contractual obligations - The court addressed whether the plaintiffs could recover based on assertions of undue enrichment and benefits enjoyed by the defendant.

Ratio Decidendi: The court determined that the plaintiffs were entitled to compensation for the additional work performed as the defendant had benefited from it, invoking principles of unjust enrichment, while applying appropriate deductions for inflated claims where evidence supported the defendants' assertions.

Result: Appeal partly allowed; the plaintiffs awarded Rs. 10,500/- plus interest.

Table of Content
1. introduction of appeal against trial court judgment. (Para 1 , 2)
2. defendant's claims regarding breach and dispute. (Para 3)
3. identifying issues framed by the trial court. (Para 4 , 5 , 6)
4. analysis of evidence regarding claims and defenses. (Para 7 , 8 , 9)
5. evaluating quality of materials and measurements. (Para 10 , 11 , 12 , 13)
6. assessment of disputed claims regarding tiles and pipes. (Para 14 , 15 , 16)
7. determining liability for additional work not explicitly contracted. (Para 17 , 18)
8. application of s.70 of the indian contract act. (Para 19 , 20)
9. implications of unjust enrichment in contract law. (Para 21)
10. final deductions summarized from various statements. (Para 22 , 23 , 24 , 25 , 26)
11. final decision and ordering of payment. (Para 27 , 28)

1. This is an appeal against the judgment and decrees dated 26th October, 1978 in Special Civil Suit No.215 of 1972 on the file of Joint Civil Judge, Senior Division, Pune. I have heard the learned Counsel appearing for both the parties.

2. The appellants - plaintiffs filed a suit in the trial Court for recovery of money in respect of a building contract. The plaintiffs' case is that defendant company entrusted construction of a bungalow and a factory to the plaintiffs. It appears the construction had been done by a previous contractor and then work was entrusted to the plaintiffs. The plaintiffs submitted their estimates and also rates which were accepted by defendant with some modification. The work was entrusted to the plaintiffs sometime in February 1970. It is also plaintiffs' case that part of the work done by previous contractor was not of good quality and the matter was examined by the Architect Mr. Nene. When the work was in progress, the defendant also entrusted some additional work to the plaintiffs. The understanding was that plaintiffs should go on giving running bills and defendant should go on making payments. Accordingly, plaintiffs started the work and was giving running bills and the defendant was making payments. In all plaintiffs have done work of the value of Rs. 1,53,446.20ps., for which bills have been issued. The defendant has made part payment to the extent of Rs. 1,25,000/-. The defendant has not paid the balance of Rs. 28,446.20ps. in spite of repeated demands and exchange of letters. The work was almost complete by the end of February 1971. For the first time during March 1971, the defendant raised an objection regarding quality of the work and also about the measurements. The defendant had never raised any such objection till then. Defendant's letter of objection was suitably replied by the plaintiffs. Apprehending that defendant may entrust the work to some other contractor, plaintiffs rushed to Court and filed a suit for injunction in Regular Civil Suit No.292 of 1971. The said suit later came to be withdrawn. The defendant appears to have completed the remaining work departmentally and as a result the plaintiffs have lost profit to that extent. Hence on these allegations the plaintiffs have filed a suit, for recovery of Rs. 32, 000/- as detailed in para 16 of the plaint.

3. The defence is as follows : -

The suit building contract is admitted. It is stated that plaintiffs abandoned the contract, and therefore, committed a breach of the contract. It is admitted that plaintiffs has submitted estimates and rates and they were accepted by the defendant subject to some modification. It is not admitted that defendant entrusted additional work to the plaintiffs. According to the defendant, the agreement was that for the running bills the defendant should pay 90 per cent, five per cent to be paid after the work is found satisfactory and then remaining five per cent to be paid only after the expiry of first rainy season or after six months whichever is longer. It is alleged that the work of the plaintiffs was not good. The quantities like measurements etc. are inflated. The material used was substandard. The work done was not ac

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top