IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
FIRST APPEAL NO. 1202/2022
ALONGWITH
INTERIM APPLICATION NO. 19349 OF 2022
ALONGWITH
INTERIM APPLICATION NO. 702 OF 2026
IN
FIRST APPEAL NO. 1202/2022
SHAIKH TAHIR ALI IBRAHIM ALI ….. APPELLANT/
APPLICANT
VS
THE MUNICIPAL CORPORATION OF
GREATER MUMBAI ….. RESPONDENT
Adv. P. J. Thorat a/w. Adv. J. S. Yadav i/b. Adv. B.S.Shukla for the
Appellant.
Adv. Pradeep M. Patil for the Respondent.
CORAM : RAJESH S. PATIL, J.
DATE : 30 JANUARY, 2026
P.C. :-
1) The present First Appeal is filed by the original plaintiff,
challenging the judgment and order dated 1 October, 2022 passed by
the Bombay City Civil Court, Greater Bombay in L.C.Suit No. 1257 of
2014.
2) The Municipal Corporation had issued a notice to the
::: Uploaded on - 09/02/2026 ::: Downloaded on - 28/04/2026 01:30:15 :::
##PAGE2##KVM
2/6
1 - FA 1202 of 2022.doc
plaintiff under Section 55 of the Maharashtra Regional and Town
Planning Act, 1966 (in short ‘MRTP Act’) dated 26 June, 2013. To the
said notice, the plaintiff filed his reply. Pursuant thereto, the Assistant
Engineer (Building and Factories) M/E Ward, passed an order
directing the plaintiff to remove the unauthorized construction
immediately, failing which the same would be removed by the
Corporation.
3) Being dissatisfied with the issuance of notice under
Section 55 of the MRTP Act and the order passed thereon by the
Officer of the Corporation, the plaintiff filed L.C.Suit No. 1257 of 2014
before the City Civil Court at Bombay. In the said suit, evidence was
led by the parties. The plaintiff examined himself and the defendant
Corporation examined their officer. After hearing both the parties, the
trial court/Bombay City Civil Court passed its judgment and order
dated 1 October, 2022 dismissed the suit of the plaintiff.
4) Being dissatisfied with the said judgment and order
passed by the City Civil Court, Bombay, the plaintiff has filed the
present proceeding before this Court.
4A) Points for determination
(i) Whether the judgment and order dated 1 October,
2022 passed in L.C.Suit No. 1257 of 2014, requires
::: Uploaded on - 09/02/2026 ::: Downloaded on - 28/04/2026 01:30:15 :::
##PAGE3##KVM
3/6
1 - FA 1202 of 2022.doc
interference ?
(ii) Whether notice dated 26 June, 2013 issued under
Section 55 of the M.R.T.P. Act and order dated 31 July,
2014 passed by the designated officer of the Municipal
Corporation are null and void ?
5) I have heard learned advocates for both the sides and I
have gone through the documents on record.
6) The issue raised by the plaintiff is that the structure of he
plaintiff was a permanent structure. Therefore notice under section
55 of the MRTP could not have been issued. Section 55 of the MRTP
Act reads as under :-
55. Removal or discontinuance of unauthorised temporary
development summarily.—
(1) Notwithstanding anything hereinbefore contained in this
Chapter, where any person has carried out any development of a
temporary nature unauthorisedly as indicated in sub-section (1) of
section 52, the Planning Authority may by an order in writing direct
that person to remove any structure or work erected, or discontinue
the use of land made, unauthorisedly as aforesaid, within fifteen days
of the receipt of the order; and if thereafter, the person does not
comply with the order within the said period, the Planning Authority
may request the District Magistrate or the Commissioner of Police, as
the case may be, [or authorise any of its officers or servants,] to have
such work summarily removed or such use summarily discontinued
without any notice as directed in the order; and any development
unauthorisedly made again, shall be similarly removed or discontinued
summarily without making any order as aforesaid.
::: Uploaded on - 09/02/2026 ::: Downloaded on - 28/04/2026 01:30:15 :::
##PAGE4##KVM
4/6
1 - FA 1202 of 2022.doc
(2) The decision of the Planning Authority on the question of
what is development of a temporary nature shall be final.
7) Admittedly, t