SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Bom) 3691

HIGH COURT OF BOMBAY
Abhay Ahuja, J
Man Infraconstruction Limited – Appellant
Versus
State Of Maharashtra – Respondent
COMMERCIAL EXECUTION APPLICATION NO. 67 OF 2025 | INTERIM APPLICATION NO. 2536 OF 2025 | INTERIM APPLICATION NO. 2398 OF 2023



Advocates:
For the Appellants/Petitioners: Mukesh Vashi, Sheetal Roghani, Manisha Desai, M.P. Vashi & Associates
For the Respondents: Zal T. Andhyarujina, Jyoti Chavan, Ishani Khanwilkar

A deposit of funds into court does not constitute satisfaction of a money decree or stop interest accrual unless it adheres to the procedure prescribed under civil procedure law. Unnecessary litigation following a recorded settlement constitutes 'undue delay,' entitling the decree-holder to recovery of interest.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Code of Civil Procedure, 1908 - Order XXI Rule 1 - Execution of consent terms - Meaning of 'undue delay' - Parties submitted to consent terms for settlement of an arbitral award - Subsequent attempt by debtor to challenge the settled terms after partial performance constitutes excessive and unwarranted conduct - Mere deposit of decretal amount in court without adherence to procedural requirement under civil procedure code does not satisfy the decree nor does it operate to stop the accrual of interest - Interest continues to accrue until the amount is actually received by the decree-holder. (Paras 35, 37, 42, 43, 48)

Facts of the case:
The parties entered into consent terms to resolve a dispute arising from an arbitral award. The debtor made a partial payment and obtained necessary approvals but subsequently sought to contest the validity of the settlement. The amount was eventually deposited with the court registry during the pendency of contempt proceedings. The decree-holder sought execution of the remaining award, alleging that the debtor caused undue delay, and claimed interest up to the date of actual receipt of funds.

Findings of Court:
The court found that the conduct of the debtor in backtracking on the settled terms, despite having obtained budgetary approval and part-performance, was unjustified and resulted in 'undue delay'. The court held that such delay entitles the decree-holder to interest at the prevailing bank rate. It further clarified that a deposit in court does not stop interest accrual unless it conforms to the specific legal procedure for certifying satisfaction of a money decree.

Issues: The main issues were whether the deposit of settlement funds in court constitutes full satisfaction of the decree, whether the conduct of the debtor amounted to undue delay under the consent terms, and the entitlement of the decree-holder to continued interest on the unpaid balance.

Ratio Decidendi: 'Undue delay' is defined as conduct that is excessive, unwarranted, and not merited by the circumstances of the case. A money decree is only satisfied upon the actual receipt of funds by the judgment creditor, and attempts to litigate the validity of a recorded settlement do not suspend the debtor's liability to pay interest during the pendency of such litigation.

Result: Execution application and associated interim applications allowed; debtor directed to pay interest at prevailing bank rates; existing attachment to continue until final satisfaction.

Table of Content
1. background facts regarding arbitration award, consent terms, and subsequent government procedural history. (Para 1 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11)
2. parties' contentions regarding the interpretation of 'undue delay' and the status of the consent decree satisfaction. (Para 2 , 3 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33)
3. court's analysis defining 'undue delay' and determining state liability for interest on delayed payments. (Para 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48)
4. the determination that unwarranted litigation conduct by the state constitutes undue delay under the consent terms. (Para 49 , 50)
5. final orders directing calculation of outstanding dues, interest, and the release of attachment on government accounts. (Para 51 , 52 , 53 , 54 , 55)

ORDER :

1. These execution proceedings have been instituted by Man Infraconstruction Limited seeking execution in terms of Column J to the Execution Application dated 30th June 2023.

2. Mr.Vashi, learned Senior Counsel appearing for the Applicant submits that the limited issue is whether the Judgment Debtor / Respondent State has unduly delayed the payment to the Applicant as per Clause 12 of the Consent Terms dated 10th December 2019 (the “said Consent Terms”).

3. Mr.Vashi has submitted that the Respondent State being the Judgment Debtor has unduly delayed the payment by more than twenty months from 6th January 2020 till September 2021 and the Applicant is therefore entitled to the execution of the Award to the extent of the remaining dues of the Award Sum described in the said Consent Terms taken on record on 12th December 2019.

4. However, before proceeding further, certain background facts would be necessary.

5. Since the State of Maharashtra viz. the Public Works Department (PWD), admittedly had not complied with its obligations under the contract agreement signed between the parties, the Applicant invoked arbitration clause which was referred to the sole arbitration of a retired Judge of this Court. After a trial, the sole arbitrator awarded an amount of Rs.332,66,39,870/- as on 16th August 2018 with future interest at the rate of 15% per annum.

6. The Respondent State of Maharashtra challenged the Award by filing an application under Section 34 of the Arbitration and Conciliation Act, 1996 before the District Court, Pune. Since there was no stay granted, the Applicant had put the Award in execution. In the execution proceedings negotiations took place between the Applicant and the Respondent and a negotiated settlement amount of Rs.358,79,18,000/- as on 15th November 2019 was arrived at. The Respondent State’s PWD put up a note for approval of several senior officers of the Respondent State and approvals were granted by the Additional Chief Secretary (PWD) and the Chief Secretary to the Government on 20th November 2019. Mr.Vashi, learned Senior Counsel has submitted that by way of a negotiated settlement, the Applicant had granted a concession of Rs.22,80,20,918/- to the Respondent which was reflected in the Consent Terms and that the said concession was in public interest of which the Respondent also benefited.

7. After filing of the Consent Terms, the Respondent State acted upon the said Consent Terms by first making a payment of Rs.1,00,00,000/- to the Applicant on 19th December 2019 and also thereafter withdrew the proceedings/application under Section 34 of the Arbitration and Conciliation Act, 1996 filed before the District Court, Pune.

8. Mr.Vashi, learned Senior Counsel, has submitted that on 27th December 2019, the Respondent State also obtained budgetary approval from both the houses of legislature for payment of the decretal amount.

9. Since no payment was received under the Consent Terms, the Applicant filed contempt proceedings being Contempt Petition (Lodging) No.9 of 2020 on 17th January 2020 and on 27th January 2020, the Respondent State

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top