SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Bom) 351510

HIGH COURT OF BOMBAY
HON'BLE SHRI JUSTICE N. J. JAMADAR
VAISHNAVI ENGINEERS AND DEVELOPERS PVT LTD THR ITS AUTHORIZED REPRESENTATIVE NAVIN K SINGH – Appellant
Versus
NAVNATH RAMKRISHNA MHATRE AND ORS – Respondent
WP/5611/2024



IN THE HIGH COURT OF JUDICATURE AT BOMBAY APPELLATE SIDE CIVIL JURISDICTION WRIT PETITION NO.5611 OF 2024 M/s. Vaishnavi Engineers and Developers Private Limited (Through its Authorized Representative Navin Singh) ...Petitioner vs.

Navnath Ramkrishna Mhatre and Others ...Respondents VISHAL SUBHASH PAREKAR Mr. A.A. Karva, for the Petitioner.

Digitally signed by V PA IS R H E A K L A R SUBHASH Mr. Hemant Gadigaonkar a/w. Mr. Devidas Bhoir and Ms. Ashwini Date: 2025.02.21 19:55:46 +0530 Mhatre, for the Respondents.

CORAM : N. J. JAMADAR, J.

RESERVED ON : JANUARY 30, 2025 PRONOUNCED ON : FEBRUARY 21, 2025 JUDGMENT :

1. Rule. Rule made returnable forthwith. With the consent of the learned counsel for the parties, heard finally at the stage of admission.

2. The challenge in this petition is to an order dated 22nd February, 2024 passed by the learned Civil Judge, Kalyan whereby an application preferred by the respondent/ original defendant to condone the delay of 9 years 4 months and 18 days in preferring an application to recall the order dated 20th April, 2013 permitting the petitioner/ plaintiff to withdraw the suit being R.C.S. No. 782 of

2012, came to be allowed.

3. The background facts leading to this petition can be summarized as under:-

(a) The petitioner is a company incorporated under the Companies Act, 1956. It was engaged in the business of real estate development. On 31st May, 2008 a Development Agreement was executed by the respondents and Janak Pandurang Mhatre and Motiram Kachru Mhatre is favour of the petitioners, thereby granting development rights in respect of the suit properties. The plaintiff claimed to have parted with consideration of Rs. 47 lakhs under the said agreement, and been put in possession of the suit properties.

(b) Asserting that the defendants were causing obstruction to the possession and enjoyment of the plaintiff over the suit properties and also committed encroachment thereon, the petitioner instituted a suit for declaration that the said agreement was subsisting and binding on the defendants and the defendants had no right to disturb the possession of the plaintiffs over the suit properties, the notice dated 18th May, 2012 addressed by the defendants professing to cancel the said agreement was unlawful and the consequential reliefs of injunction.

(c) In the said suit, initially an order of status-quo was passed on 31st October, 2012. By an order dated 17th April, 2013 the said order of status-quo was modified to include utilization of FSI potential over the land belonging to the defendants.

(d) On 20th April, 2013 the plaintiff filed a pursis to withdraw the suit unconditinoally. By an order dated 20th April, 2013 the learned Civil Judge granted permission and the suit was disposed as unconditionally withdrawn.

(e) The respondents/ defendants filed an application on 4th October, 2023 seeking condonation of delay in filing application to recall the aforesaid order dated 20th April, 2013 passed in RCS No. 782 of 2012, on the premise that the said suit was withdrawn by the plaintiff fraudulently. Referring to the order dated 17th April, 2013 whereby the earlier order of status quo was modified to include utilization of FSI potential over the land belonging to the defendants, the defendants contended that the plaintiff surreptitiously withdrew the suit as status-quo was running against the plaintiff. A fraud was played on the Court by seeking withdrawal of the suit on the ground that the matter was amicably resolved between the parties though there was no such settlement. Neither the advocate for the defendants nor the defendants were informed about the motion to withdraw the said suit. It was, therefore, necessary to set aside the said order and restore the suit so that the order of status-quo, as modified by the order dated 17th April 2013, continuous to operate.

(f) As regards the delay, the defendants contended that after the unconditional withdrawal of the said suit the plaintiff did not submit building p

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top