SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Bom) 3934

HIGH COURT OF BOMBAY
Milind N. Jadhav, J
Om Galaxy Apartment CHS Ltd. – Appellant
Versus
Raj Doshi Exports Pvt. Ltd. – Respondent
INTERIM APPLICATION NO. 4657 OF 2025 | SUIT NO. 217 OF 2025 | INTERIM APPLICATION NO. 6622 OF 2025



Advocates:
For the Appellants/Petitioners: Pralhad Paranjape, Sudhanva S. Bedekar, Aditya Lele, Swapnil Shanbhag
For the Respondents: Mayur Khandeparkar, Prerak A. Sharma, Aishwary Manjrekar, Apurva Dalal

Where an appellate court mandates redevelopment of a consolidated land plot as a composite project, individual plot occupants cannot seek separate demarcation or injunctive relief against development. Adherence to superior judicial directives is paramount, and attempts to relitigate previously rejected claims regarding land exclusion are legally impermissible.

Headnote:(A) Civil Procedure Code, 1908 - Order VII Rule 11 - Rejection of Plaint. Maharashtra Ownership of Flats Act, 1963 - Section 11 - Conveyance of land - Development Control Regulations.

(B) Binding nature of judicial orders - Principle of finality of litigation - Redevelopment scheme of larger land parcel - Premature cause of action - Entitlement to conveyancing only post-completion of composite project.

(C) Appellate hierarchy - Decisions of superior courts regarding land usage and development obligations are binding and preclude contradictory claims in lower forums unless there is a material change in circumstances. (Paras 10, 11, 14, 15)

Facts of the case:
The plaintiff, a registered residential society, challenged the developer's activity on a portion of land, claiming independent ownership rights to a specific area and seeking an injunction against the developer's use of floor space index potential. The developer contended that the land is part of a cluster redevelopment project mandated by superior court orders, which requires composite development and consolidated conveyance only upon total project completion.

Findings of Court:
Superior court orders specifically mandated that the larger land be treated as a single, indivisible plot for redevelopment, with conveyance occurring only after the project’s conclusion. The plaintiff's previous application to carve out a separate land parcel for direct conveyance was rejected by the appellate authority, rendering the current legal attempt for specific injunctive relief fundamentally incompatible with the existing final, binding judicial mandates.

Issues: Whether a constituent housing entity can maintain an injunction for separate land demarcation and conveyance during an ongoing composite redevelopment project authorized by court order, and whether prior challenges to such redevelopment at the apex level preclude subsequent attempts to relitigate the same issues.

Ratio Decidendi: A project mandated by a superior court as a composite development constitutes a binding framework; thus, individual attempts to fragment that land prior to completion are impermissible. Once an appellate forum has rejected a claim for sectoral exclusion, that finding operates to foreclose subsequent litigation seeking the same relief, as judicial finality must be maintained to ensure the execution of the overarching redevelopment timeline.

Result: Application for interim relief rejected and dismissed.

Table of Content
1. establishment of factual background and procedural history. (Para 1 , 2 , 3 , 4)
2. plaintiff claims right to conveyance and fsi protection. (Para 5)
3. defendant asserts suit is premature based on supreme court orders. (Para 6)
4. binding effect of prior supreme court directions on current disputes. (Para 7 , 8 , 9 , 10 , 11 , 12 , 13)
5. injunctive relief denied as it contradicts supreme court directives. (Para 14 , 15 , 16 , 17 , 18)

JUDGEMENT.:

1. Heard Mr. Paranjape, learned Advocate for Applicant, Mr. Khandeparkar, learned Advocate for Defendant No.1 and Mr. Dalal learned AGP for Defendant No.3 – Corporation.

2. Suit is filed on 11.07.2024. Interim Application No.4657 of 2025 is filed by Defendant No.1 under Order VII Rule 11 of Civil Procedure Code, 1908 (for short "CPC") seeking rejection of Plaint. Interim Application No.6622 of 2025 of CPC is filed by Plaintiff seeking interim reliefs. By consent of parties Interim Application No.6622 of 2025 is heard finally for interim reliefs. Parties shall be referred to as Plaintiff and Defendant for convenience. Lis is essentially between Plaintiff and Defendant No.1.

3. Plaintiff is a registered Cooperative Housing Society comprising of 21 members occupying flats in a building situated on Plot No.231, Cadastral Survey No.582, Mahim Division, T.H. Kataria Marg, S. Keer Marg, Matunga (West), Mumbai – 4000016 (for short “larger land”). Defendant No.2 was owner of larger land and by Agreement dated 01.02.1995 assigned right, title and interest of subject land to Defendant No.1 – Developer. Larger land admeasures 6067 square meters out of which Plaintiff – Society claims ownership of 938 square meters. Plaintiff – Society’s building is constructed upon 234.27 square meters and it is in possession of 441 square meters. However in the Suit proceedings Plaintiff claims entitlement to 938 square meters out of the larger land (6067 square meters).

4. Briefly stated, Defendant No.2 was original owner of larger land and applied to Municipal Corporation of Greater Mumbai for approvals of development of the larger land (6067 square meters). After receiving requisite approval and Commencement Certificate, on 04.05.1982 Defendant No.2 began construction on the larger land as per sanctioned plan. On 02.11.1983, Executive Engineer “G” North Ward issued No Objection Certificate and pursuant to all approvals, Defendant No.2 sold flats in the proposed to be constructed thereon buildings between 1983 – 1984 and entered into requisite agreements as per Maharashtra of Ownership of Flats Act, 1963 (for short “MOFA”) with flat purchasers.

4.1. On 15.10.1987, Executive Engineer, Building Proposals of the Corporation issued Occupation Certificate and flat purchasers took possession of their respective flats. On 06.01.1990, Sub – Registrar of Cooperative Societies issued Registration Certification to Plaintiff – Society registering it as a Cooperative Housing Society. In or about 1995, Defendant No.2 transferred right, title and interest of the entire larger land in favour of Defendant No.1. On 30.10.2002, Plaintiff – Society addressed notice to Defendant No.1 seeking conveyance of the Suit property.

4.2. In or about 2006, certain occupants on larger land filed Writ Petition in this Court seeking redevelopment of larger land. This Court decided the Writ Petition and order passed by this Court was challenged before the Supreme Court in Civil Appeal No.9878 of 2016. By order dated 12.04.2017 Supreme Court directed Defendant No.1 to develop entire larger property (6067 square meters) within a period of 42 months from 12.04.2017. In view of non-compliance of order dated 12.04.2017, the tenants / occupants on larger land filed Contempt Petition (Civil) No.442 of 2021 wherein Supreme Court passed order dated 19.04.2022 directing Defendant No.1 to develop entire larger land within 36 months.

4.3. Defendant No.1 addressed letter dated 10.05.2022 informing Plaintiff – Society

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top