2026 Supreme(Online)(Bom) 4952
HIGH COURT OF BOMBAY
HON'BLE SHRI JUSTICE SANDEEP V. MARNE
SANKLECHA CONSTRUCTIONS PVT LTD – Appellant
Versus
NITIN MADHUKAR SHEWALE – Respondent
SAST/8825/2025
(28)
##PAGE1##
CNR No : HCBM010143392025
2026:BHC-AS:39337 IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION SECOND APPEAL (STAMP) NO.8825 OF 2025
1. Sanklecha Constructions Pvt. Ltd.
2. Vijay Kachardas Sanklecha 3. Dilip Kachardas Sanklecha
4. Puneet Ajit Sanklecha ....Appellants V/S
1. Nitin Madhukar Shewale
2. Shital Nitin Shewale
3. Bhimashankar Laxman Janmali
4. Shrikrishna Laxman Janmali
5. Sitabai Laxman Janmali
6. Pushpa Jaggannath Janmali
7. Devemdra Jaggannath Janmali
8. Anil Laxman Janmali
9. Dinkar Laxman Janmali ....Respondents WITH INTERIM APPLICATION NO.7869 OF 2025 IN SECOND APPEAL (STAMP) NO.8825 OF 2025 (FOR STAY)
1. Sanklecha Constructions Pvt. Ltd.
2. Vijay Kachardas Sanklecha 3. Dilip Kachardas Sanklecha
4. Puneet Ajit Sanklecha ....Applicants V/S
1. Nitin Madhukar Shewale
2. Shital Nitin Shewale
3. Bhimashankar Laxman Janmali
4. Shrikrishna Laxman Janmali
5. Sitabai Laxman Janmali
6. Pushpa Jaggannath Janmali
##PAGE2##7. Devemdra Jaggannath Janmali
8. Anil Laxman Janmali
9. Dinkar Laxman Janmali ....Respondents _________
Mr. Abhishek Pungaliya for the Appellants/Applicants.
Mr. Akshay R. Kapadia for Respondent Nos.1 and 2.
__________
CORAM : SANDEEP V. MARNE, J.
RESERVED ON : 17 SEPTEMBER 2026.
PRONOUNCED ON : 28 SEPTEMBER 2026.
J U D G M E N T
THE CHALLENGE
1. This Appeal is filed under provisions of Section 58 of the Real Estate (Regulation and Development) Act, 2016 (RERA) by the Appellants—Promoters, challenging the judgment and order dated 7 November 2023 and Review Order dated 28 November 2024 passed by the Maharashtra Real Estate Appellate Tribunal, Mumbai, (Appellate Tribunal) partly allowing the Appeal preferred by the allottees and modifying the order dated 24 August 2021 passed by the Maharashtra Real Estate Regulatory Authority (MahaRERA). By the impugned Order, the Appellate Tribunal has withdrawn the option granted to them by MahaRERA to return the paid consideration to the allottees alongwith interest after obtaining occupation certificate (OC) for the project.
2. The Appeal involves the Appellants-Promoters being aggrieved by the ultimate direction for refund of the entire amount to the allottees along with interest thereon with effect from 1 January 2018. Since the ultimate direction contemplates immediate return of amounts with interest to the allottees and since option of returning the amount at the time of securing OC is deleted, the Appellants have filed the present Appeal.
##PAGE3##3. It must be observed at the very outset that the Appellate Tribunal has rather passed confusing orders posing challenge to comprehend the same. Initially, MahaRERA had granted option to the promoter to refund the paid consideration to the allottee along with interest after securing OC for the project. By the main judgment and order dated 7 November 2023, the Appellate Tribunal withdrew that option by directing deletion of portion of direction from MahaRERA’s Order and directed that the promoter must refund the paid consideration with interest from the dates of receipt of payments within 23 days of the Order. The main Order is later reviewed by the Appellate Tribunal deleting the direction for payment of interest from the date of receipt of payments. Thus, the net effect of the Order passed by MahaRERA as modified twice by the Appellate Tribunal is that the promoter needs to ‘forthwith’ refund the paid consideration with interest w.e.f. 1 January 2018.
4. Appellants are not aggrieved per se by the direction for return of amount and interest to the allottees. They are willing to return the amount with interest, however, after obtaining the OC for the project. The Appeal is filed contending that there are mitigating circumstances beyond the control of the Promoters which have resulted in delay in completion of the project and they desire that option of returning the amount with interest after obtaining OC for the project must be made available to them. Thus, the limited scope of inquiry in the Appeal is whether the Appell