HIGH COURT OF BOMBAY
KISAN DHAWLA RAWATE – Appellant
Versus
THE STATE OF MAHARASHTRA AND OTHERS – Respondent
WP 12023/2016
['SHINDE S K', 'COPY SERVED ON GP', '', 'SURWASE B R', 'GP']
wp11956&2.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO. 11953 OF 2016
1.
Amruta Dagadu Lahamge
Age 85 years, Occu:Agri
2.
Datta Amruta Lahamge,
Age 37 years, Occu:Agri
Both R/o Rajur Tq. Akole
Dist. Ahmednagar
...
Petitioners
WRIT PETITION NO. 12023 OF 2016
Kisan Dhawla Rawate
Age 75 years, Occu: Agri.
R/o Rajur, Tq. Akole,
Dist. Ahmednagar
... Petitioner
WRIT PETITION NO. 11956 OF 2016
1.
Shantaram Nana Pandit (died)
Through legal heirs.
1-A Ganesh Shangaram Pandit
Age 50 years, Occu: Agri
1-B Yinayak Shantaram Pandit
Age 37 years, Occu: Agri
Both R/o Rajur Tq. Akoli
Dist. Ahmednagar
...
Respondents
VERSUS
1. The State of Maharashtra,
Through its Secretary,
Revenue & Forest Department,
Mantralaya, Mumbai 32
2.
The Additional Commissioner,
Nashik Division, Nashik
3.
The Collector, Ahmednagar,
Dist. Ahmednagar
…
Respondents.
4.
The Land Acquisition Officer
No.13, Ahmednagar,
1/6
wp11956&2.odt
5.
The Executive Engineer,
Uppar Pravara Dam Division,
Sangamner (Ghulewadi)
Tq. Sangamner, Dist.
Ahmednagar
... Respondents in
all the
matters.
Mr. S. K. Shinde, Advocate for Petitioners
Mr. A. R. Kale, Mrs. M. A. Deshpande and Mr. S. B.
Joshi, AGPs for Respondents 1 to 4 State in the
respective petitions.
Mr. B. R. Survase, Advocate for Respondent No. 4 in all
the matters.
CORAM
: R. M. BORDE &
K. L. WADANE, JJ.
DATE
:
20th April, 2017
JUDGMENT (Per R. M. Borde, J.):
1.
Rule. Rule made returnable forthwith.
2.
With the consent of the parties, taken up for
final disposal at the admission stage.
3.
The petitioners are praying for quashment of
acquisition proceedings and final awards passed on
20.03.1987 and 24.01.92 in respective petitions. The
land belonging to the petitioners have been acquired
for Nilwande Dam-2. It is stated that though the awards
were declared and the petitioners were paid amount of
compensation, however, the possession of the acquired
property has not be taken over by the acquiring body.
The petitioners as such, contend that in view of
operation of Section 24(2) of the Right to Fair
2/6
wp11956&2.odt
Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013, the
proceedings in respect of acquisition initiated under
the Land Acquisition Act 1894 shall be deemed to have
lapsed. The petitioners have also expressed their
willingness to refund the amount of compensation
received by them with interest @ 6% per annum from the
date of receipt of such amount till the date of
repayment.
4.
In response to the notice issued by this
Court, the acquiring body has caused appearance and
presented affidavit in reply. It is stated in the
affidavit in reply that due to change in alignment of
Nilwande Dam, the acquired lands cannot be utilized for
the project. It is specifically contended that the
acquired lands cannot be used for the purpose for which
those were acquired. It is further stated that since
there is a proposal for handing over the possession of
the land in favour of one Government Industrial
Institution, Rajur, request made by the petitioners
cannot be considered. It is also further stated that
the State Government has not communicated anything in
this regard. The acquiring body has expressed
willingness to relinquish the lands on refund of amount
3/6
wp11956&2.odt
of compensation together with interest as may be
prescribed by the High Court.
5.
It is pointed by the learne