HIGH COURT OF BOMBAY
RAJENDRA RAMNATH ZODGE – Appellant
Versus
THE STATE OF MAHARASHTRA AND OTHERS – Respondent
APPLN 3937/2013
['Brahme Shailesh P', 'COPY SERVED ON PP', 'PP FOR R NOS 1', '3', '4 & 5', 'R NO 2 SERVED', 'Bhalerao Sudhir G']
1
Cri.Appln.Nos.3944/2013 &
3937/2013
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD
CRIMINAL APPLICATION NO.3944/2013
Keshav Trimbakrao Aghav & Anr.
APPLICANTS
VERSUS
The State of Maharashtra & Ors.
RESPONDENTS
*****
Mr.PM Shah, Sr.Counsel i/b Mahesh S.Deshmukh,
Advocate for Applicant;
Mr.BV Wagh, APP for State;
Mr.Sudhir Bhalerao, Adv. For Resp.No.2
with
CRIMINAL APPLICATION NO.3937/2013
Rajemndra Ramnath Zodge
APPLICANT
versus
The State of Maharashtra & Ors.
RESPONDENTS
*****
Mr.Shailesh P.Brahme, Advocate for Applicant;
Mr.BV Wagh, APP for State;
Mr.Sudhir Bhalerao, Adv. For Resp.No.2
*****
CORAM :
K.U.CHANDIWAL &
A.I.S.CHEEMA,JJ.
DATE : 4th OCTOBER,2013.
PER COURT :
1)
Heard Mr.Shah, learned Sr.Counsel; Mr.Brahme
learned Counsel and learned APP for respective
parties in respective criminal applications.
2)
By Writ Petition No.3944/2013, the
contractor and transporter have urged to quash charge
sheet No.1/2012 being RCC No.17/2013 for offence
2
Cri.Appln.Nos.3944/2013 &
3937/2013
under Section 329 r/w 34 of Indian Penal Code.
3)
By Criminal Application No.3937/2013, the
applicants are transporters engaged by M/s Tirupati
Constructions, belonging to applicant in Criminal
Application No.3944/2013.
4)
Since in both the criminal applications,
common grounds are raised, questioning RCC No.
17/2013, both the criminal applications are disposed
of together by common order.
5)
M/s Tirupati Construction was entrusted the
work of construction of internal road of Majalgaon
project which is part of Godawari Marathwada
Irrigation Development Corporation. Administrative
sanction illustrates the work order royalty was to be
paid by the contractor through a challan at the time
of receiving running bill.
6)
Pursuant to such excavation, indeed Rs.
15,00,000 (Rupees fifteen lakhs) was deducted from
running bill of contractor towards royalty of minor
mineral murum. Such cheque was forwarded to the
learned Tahsildar, Majalgaon.
This has been
communicated to the Executive Engineer regarding
excavation of muroom for the purpose of Government
work only.
.
Mr.Shah, learned Sr.Counsel, clarifies, it
is not Rs.15,00,000/, but till this date, an amount
of Rs.35,00,000/ are deposited by the contractor
towards the royalty.
7)
Respondent No.2 – Executive Engineer, has
intimated to the Tahsildar as to quantity of muroom
3
Cri.Appln.Nos.3944/2013 &
3937/2013
and vehicles to be used, including numbers of the
vehicles by communication dated 26.7.2012. On
2.8.2012, learned Tahsildar accorded permission to
respondent No.4, disclosing about such permission.
8)
A notice was slapped on 4.8.2012 upon the
contractor for illegal excavating 8000 brass of
muroom. Same was replied and circumstances were
explained, including documents to satisfy that it was
under a valid permission to excavate muroom on
payment of royalty.
9)
Learned Tahsildar was not satisfied and he
imposed fine by applying the provisions of Section 48
of Maharashtra Land Revenue Code to the extent of Rs.
88,00,215/. With such accusations, Circle Officer
lodged the FIR dated 25.09.2012 and after
investigation, charge sheet was filed on 12.1.2013.
10)
The excavation of muroom from the respective
sites, as earmarked to the contractor through the
channel of transporter, is not in controversy. It is
to be seen that such excavated muroom is used for the
purpose of laying internal roads or work meant for
rehabilitation of project affected locality. The
entire activities were monitored by Executive
Engineer of the concerned depa