HIGH COURT OF BOMBAY
RAJENDRA RAMNATH ZODGE – Appellant
Versus
THE STATE OF MAHARASHTRA AND OTHERS – Respondent
APPLN 3937/2013



Advocates:
['Brahme Shailesh P', 'COPY SERVED ON PP', 'PP FOR R NOS 1', '3', '4 & 5', 'R NO 2 SERVED', 'Bhalerao Sudhir G']

1

Cri.Appln.Nos.3944/2013 &

3937/2013

IN THE HIGH COURT OF JUDICATURE OF BOMBAY

BENCH AT AURANGABAD

CRIMINAL APPLICATION NO.3944/2013 

Keshav Trimbakrao Aghav & Anr.

     ­ APPLICANTS

      VERSUS

The State of Maharashtra & Ors.    

­ RESPONDENTS 

*****

Mr.PM Shah, Sr.Counsel i/b Mahesh S.Deshmukh, 

Advocate for Applicant;

Mr.BV Wagh, APP for State;

Mr.Sudhir Bhalerao, Adv. For Resp.No.2

with

CRIMINAL APPLICATION NO.3937/2013

Rajemndra Ramnath Zodge

­ APPLICANT

versus

The State of Maharashtra & Ors.    

­ RESPONDENTS 

*****

Mr.Shailesh P.Brahme, Advocate for Applicant;

Mr.BV Wagh, APP for State;

Mr.Sudhir Bhalerao, Adv. For Resp.No.2

*****

                

CORAM :

K.U.CHANDIWAL &

A.I.S.CHEEMA,JJ.

   

DATE  :  4th OCTOBER,2013. 

PER COURT :

1)

Heard Mr.Shah, learned Sr.Counsel; Mr.Brahme 

learned   Counsel   and   learned   APP   for   respective 

parties in respective criminal applications.

2)

By   Writ   Petition   No.3944/2013,   the 

contractor and transporter have urged to quash charge 

sheet   No.1/2012   being   RCC   No.17/2013   for   offence 

2

Cri.Appln.Nos.3944/2013 &

3937/2013

under Section 329 r/w 34 of Indian Penal Code.

3)

By   Criminal   Application   No.3937/2013,   the 

applicants  are transporters  engaged  by M/s Tirupati 

Constructions,   belonging   to   applicant   in   Criminal 

Application No.3944/2013.

4)

Since   in   both   the   criminal   applications, 

common   grounds   are   raised,   questioning   RCC     No.

17/2013, both the criminal applications are disposed 

of together by common order.

5)

M/s Tirupati Construction was entrusted the 

work   of   construction   of   internal   road   of   Majalgaon 

project   which   is   part   of   Godawari   Marathwada 

Irrigation   Development   Corporation.     Administrative 

sanction illustrates the work order royalty was to be 

paid by the contractor through a challan at the time 

of receiving running bill.

6)

Pursuant   to   such   excavation,   indeed   Rs.

15,00,000   (Rupees   fifteen   lakhs)   was   deducted   from 

running bill of contractor towards royalty of  minor 

mineral   murum.     Such   cheque   was   forwarded   to   the 

learned   Tahsildar,   Majalgaon.  

  This   has   been 

communicated   to   the   Executive   Engineer   regarding 

excavation   of   muroom   for   the   purpose   of   Government 

work only.

.

Mr.Shah,   learned   Sr.Counsel,   clarifies,   it 

is not Rs.15,00,000/­, but till this date, an amount 

of   Rs.35,00,000/­   are   deposited   by   the   contractor 

towards the royalty.

7)

Respondent   No.2   –   Executive   Engineer,   has 

intimated to the Tahsildar as to quantity of muroom 

3

Cri.Appln.Nos.3944/2013 &

3937/2013

and   vehicles   to   be   used,   including   numbers   of   the 

vehicles   by   communication   dated   26.7.2012.     On 

2.8.2012,   learned   Tahsildar   accorded   permission   to 

respondent No.4, disclosing  about such permission.

8)

A notice was slapped on 4.8.2012 upon the 

contractor   for   illegal   excavating   8000   brass   of 

muroom.     Same   was   replied   and   circumstances   were 

explained, including documents to satisfy that it was 

under   a   valid   permission   to   excavate   muroom   on 

payment of royalty.  

9)

Learned Tahsildar was not satisfied and he 

imposed fine by applying the provisions of Section 48 

of Maharashtra Land Revenue Code to the extent of Rs.

88,00,215/­.   With such  accusations,  Circle  Officer 

lodged   the   FIR   dated   25.09.2012   and   after 

investigation, charge sheet was filed on 12.1.2013.

10)

The excavation of muroom from the respective 

sites,   as   earmarked   to   the   contractor   through   the 

channel of transporter, is not in controversy.  It is 

to be seen that such excavated muroom is used for the 

purpose  of laying  internal  roads  or work  meant for 

rehabilitation   of   project   affected   locality.     The 

entire   activities   were   monitored   by   Executive 

Engineer of the concerned depa

1
2
3
4
5
6
7
8
9
10
11