HIGH COURT OF BOMBAY
AHMED SHAIKH MAHEBOOB – Appellant
Versus
THE STATE OF MAHARASHTRA AND OTHERS – Respondent
WP 9540/2013



Advocates:
['QURESHI SHAIKHLAL ABDUL GAFAR', 'COPY SERVED ON G P', '', 'S M GODSAY', 'G P']

1/10

wp 9540, 9531 & 8331.13 final order.sxw

IN THE HIGH COURT OF JUDICATURE AT

BOMBAY.

BENCH AT AURANGABAD.

CIVIL APPELLATE JURISDICTION.

Writ Petition No.9540 Of 2013.

A l o n g w i t h

Writ Petition No.9531 Of 2013.

A n d

Writ Petition No.8331 Of 2013.

W.P. No.9540/13.

Ahmed Shaikh Maheboob

::

Petitioner.

V e r s u s

The State of Maharashtra & Ors.

::

Respondents.

W.P. No.9531/13.

Shaikh Vajir s/o Shaikh Sandu

::

Petitioner.

V e r s u s

The State of Maharashtra & Ors.

::

Respondents.

W.P. No.8331/13.

Mohd.Akram Haji Shaikh Bhikan & Ors.

::

Petitioners.

V e r s u s

The Maha. State Electricity Transmission

Co.Ltd. EHV Construction Sub Divn. 1, A'bad.

Through its Dy. Executive Engineer

& Ors.

::

Respondents.

GAG

2/10

wp 9540, 9531 & 8331.13 final order.sxw

Appearance =>

Mr. S.A.G. Qureshi, Advocate for the Petitioners in W.P.

Nos.9540 & 9531/13.

Mr. S.E. Siddhiquie, Advocate for the Petitioners in

W.P.No.8331/13.

Mr. Satish Godsay, Advocate for Resp. - the Maha. State

Electricity Transmission Co.Ltd.

Mr. G.K. Thigle – Naik, A.G.P. for the State of Maha.

CORAM :

S.S. SHINDE, J.

DATE

:

24th

DECEMBER,

2013.

Per Court :-

Heard the learned counsel appearing for the petitioner/s

in the above three Writ Petitions, learned A.G.P. for the State of

Maharashtra and learned counsel for the Maharashtra State

Electricity Transmission Co.Ltd. (In short, the M.S.E.T.Co.Ltd.) at

length.

(2)

Being aggrieved and dis-satisfied by the order dated 2nd

November, 2013 passed by Respondent No.1 i.e. the learned District

Collector, Aurangabad in Case No.15 filed by the M.S.E.T.Co.Ltd.

U/Section 16 of the Indian Telegraph Act, 1885 read with Section 164

of the Electricity Act, 2003 and Rule/s 3 and 12 of the Maharashtra

Works of Licensee Rule, 2012, petitioner - Ahmed Shaikh Maheboob

has filed W.P. No.9540/13 and petitioner Shaikh Vajir s/o Shaikh

Sandu has filed W.P. No.9531/13.

Being aggrieved and dis-satisfied with the order dated 19th

January, 2013 passed by Respondent No.2 i.e. the learned District

3/10

wp 9540, 9531 & 8331.13 final order.sxw

Collector, Jalana in case No.OW No.2013/RB/Desk-1/Police-1/Kavi,

petitioners - Mohd.Akram Haji Shaikh Bhikan & Ors. have filed W.P.

No.8331/13.

(3)

The learned counsel for the petitioners in WP Nos.

9531/13 & 9540/13 invited my attention to the provisions of Sec.10 of

the Indian Telegraph Act, 1885 and also Part III of the said Act and

submits that the provisions of said Act would have no application so

far as respondent – M.S.E.T.Co. Ltd., who is the licensee under the

Electricity Act, 2003, is concerned. He further submits that, even

without admitting and assuming that the provisions of Sec.10 of the

Indian Telegraph Act, 1885 has application in the facts of present

case, even then, clause (D) of Section 10 has not been complied-with

by the respondents. It is further submitted that, there is standing

crop of cotton and jawar in the agricultural field owned by the

petitioners. According to him, respondent Nos. 2 to 4 have no right to

execute the work without following due procedure of law, as per

Section 4(1) and Section 5 of the Land Acquisition Act, 1894. Thus, he

submits that, respondent Nos. 2 to 4 have no right to enter into the

lands owned by the petitioners to execute the work of alignment of

transmission line and erection of 220 KV tower firstly, without

proper acquisition of said portion of land and secondly, without

making the payment of compensation to the petitioners.

(4)

The learned counsel for the petitioners in W.P. Nos.

9531/13 & 9540/13 invited my attention to the grounds taken in the

Petitions and in particular ground No.IV in WP 9540/13 and submits

that, the petitioner in said Writ Petition is the owner of land Gat

No.160 and without his consent, respondent Nos.2 to 4 have entered

4/10

wp 9540, 9531 &

1
2
3
4
5
6
7
8
9
10
11