2025 Supreme(Online)(Cal) 4827

CALCUTTA HIGH COURT
S. S. CONSTRUCTION – Appellant
Versus
THE WEST BENGAL ELECTRICITY DISTRIBUTION COMPANY LIMITED AND ORS – Respondent


S/L 27

23.12.2025 Court. No. 25 sourav WPA 11047 of 2025 S. S. Construction Vs.

West Bengal State Electricity Distribution Company Limited & Ors.

Mr. Satyam Mukherjee Ms. Sayani Ahmed Mr. P.S. Ghosh Mr. Saibal Rakshit … for the petitioner.

Dr. Modhusudan Saharay Ms. Debangana Dey … for W.B.S.E.D.C.L.

Mr. Pannalal Bandyopadhyay Mr. Abhijit Ghoh … for the respondent no. 5.

Mr. Abhijit Mondal Ms. Puja Goswami … for the respondent nos. 6 to 11.

1. The petitioner has filed the present writ application praying for a direction upon the respondent nos. 3 and 4 for taking appropriate steps for installation of new electric connection in the property being “Gulmohar Villa” situated at Mouza – Khoradabahera, J.L. No. 06, R. S. Dag Nos. 334 and 335, L. R. Dag No. 1079, L.R. Khatian No. 1065, under P.S. –

Uttarpara, District – Hooghly.

2. The petitioner submits that the petitioner has applied for grant of electric connection and accordingly, the authorities have issued the quotations and as per the quotations, the petitioner has paid the amount, but in spite of the payment of the amount, the authorities have not provide the electric connection because of there is an objection from the villagers.

3. Learne

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top