D/L.13.
September 25, 2025.
MNS.
CO No. 966 of 2024
West Bengal State Electricity Distribution
Company Limited and another
Vs.
M/s G.D.A. Cement Industry Private
Limited
Mr. Debjit Mukherjee,
Ms. Susmita Chatterjee
… for the petitioners.
Mr. Sujit Banerjee, Mr. Nilay Sengupta
…for the opposite party.
1. The affidavit-of-service filed in Court today
be kept on record.
2. The present revisional application arises
from an order whereby the Appellate Court reversed the order of the Trial Court rejecting the injunction application of the plaintiff/opposite party and granting
injunction till disposal of the suit.
3. The suit, which is the genesis of the
present litigation, has been filed for declaration and permanent injunction, raising a billing dispute regarding electricity charges for a connection given by the
defendant no. 1/Distribution Company to the plaintiff/opposite party.
4. The revisionists/petitioners raised an objection before the learned Trial Judge during hearing of the temporary injunction application that the suit is not maintainable in view of the operation of Section 145 of the Electricity Act, 2003 (in short “the 2003 Act”) and the extant Regulations enacted by the West Bengal Electricity Regulatory Commission (WBERC), whereby the appropriate forum designated for deciding billing disputes is the concerned Regional Grievance Redressal Officer (RGRO).
5. On such premise, the injunction application was dismissed on contest. Subsequently, an appeal was preferred by the plaintiff/opposite party against such order, where the learned District Judge, who admitted the appeal initially, granted an order of mandatory injunction to the effect that the defendant/Distribution Company shall restore the power supply to the opposite party within twenty-four hours, subject to deposit of Rs. 10,00,000/- by the plaintiff/opposite party.
6. However, learned counsel for both the parties submit that the tenor of the said order was erroneous to the extent that disconnection of power supply was never effected. Only a notice of disconnection was issued by the Distribution Company to the opposite party.
7. Be that as it may, both parties proceeded on the premise that the said ad interim order was a prohibitory order restraining the defendant no. 1 / Distribution Company from disconnecting the electricity supply of the plaintiff, subject to deposit of Rs. 10,00,000/- by the latter. Such deposit having been made, the disconnection has not yet been effected.
8. Learned counsel for the petitioners argues that the learned Appellate Judge, while allowing the miscellaneous appeal, mechanically reiterated the ad interim order of the learned District Judge and made the same absolute, without entering into the merits of the matter and/or ascertaining the maintainability of the suit at all.
9. Learned counsel further submits that, taking undue advantage of the said order, the plaintiff/opposite party is also not paying the current electricity charges.
10. Learned counsel for the plaintiff/opposite party submits that there is no injunction on the Distribution Company/revisionist petitioner no. 1 to raise bills regarding current consumption of electricity on the opposite party.
11. It is further submitted by the plaintiff/opposite party that the appropriate relief of the defendants/petitioners would at best be an application under Order VII Rule 11 of the Code of Civil Procedure. The Court, while deciding the injunction application, it is submitted, cannot decide the question of maintainability of the suit.
12. Heard both sides.
13. There is a cardinal fallacy in the arguments of the opposite party. It is well-settled that if an objection is raised regarding the maintainability of the suit on the ground of inherent lack of jurisdiction before the Civil Court, the same forms a component to be decided by the court within the contemplation of whether the defendants/petitioners have a prima facie case for grant of injunction.
14. Maintainability of the suit is an essential element of a
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.