JANE ALAM SHEKH @ JANE ALAM SK AND ANR – Appellant
Versus
STATE OF WEST BENGAL AND ORS. – Respondent
FMA 768 / 2025



IN THE HIGH COURT AT CALCUTTA CIVIL APPELLATE JURISDICTION APPELLATE SIDE Present:

The Hon’ble Justice Debangsu Basak And The Hon’ble Justice Prasenjit Biswas FMA 768 of 2025 With IA No.: CAN 1 of 2025 Jane Alam Shekh @ Jane Alam Sk. & Anr.

Vs.

The State of West Bengal & Ors.

For the Appellants : Mr. Golam Mastafa, Advocate Mr. Tarasankar Samanta, Advocate Mr. Ashrafur Rahman, Advocate For the State : Mr. Ashim Kumar Ganguly, Ld. AGP Mr. Tarak Karan, Advocate For the Respondent Nos.3A & 4: Mr. Uttam Kumar Bhattacharyya, Advocate For the Respondent Nos.7 to 10: Mr. Dyutiman Banerjee, Advocate Mr. Bodhisotto Halder, Advocate Mr. Vishal Mallick, Advocate Mr. Salil Kumar Maity, Advocate Hearing & Judgment on : August 11, 2025 DEBANGSU BASAK, J.:-

1. Appellants are the writ petitioners.

2. Appeal is directed against an order dated March 19, 2025 passed by the learned Single Judge in WPA 5436 of 2025.

3. By the impugned order, the learned Single Judge found that, ingress and egress of the writ petitioners were not affected. The District Magistrate took into account that, there was no encroachment on the land in question. Therefore, learned Single Judge did not find any reason to interfere with the order impugned passed by the District Magistrate.

4. Learned Advocate appearing for the appellants submits that, appellants complained of unauthorized construction to the District Magistrate. In this regard, he refers to the letter dated March 28, 2024. He submits that, the District Magistrate misdirected the enquiry and, therefore, came to an erroneous finding. He submits that, the District Magistrate proceeded on the basis that, the occupation of the private respondents in the land in question was authorized by the Zilla Parishad and that, the appellants were enjoying a right of ingress and egress to its property. He submits that, such was not the claim before the District Magistrate made by the appellants.

5. Learned Advocate appearing for the respondent nos.7 to 10 submits that, the writ petition is not maintainable since, there is a provision for appeal under the West Bengal Public Land (Eviction of Unauthorized Occupants)

Act, 1962. In this regard, he refers to Section 7 thereof.

6. Learned Advocate appearing for the respondent nos.7 to 10 refers to various documents annexed to the affidavit-in-opposition. He submits that, his clients received possession of the property from the Zilla Parishad on lease. At the time of obtaining lease, there were existing structures. His client did not make any further construction on the existing structures. His clients are not responsible to answer whether the existing structures were authorized or unauthorized.

7. State is represented.

8. It is submitted on behalf of the Zilla Parishad that, the respondent nos.7 to

10 were granted lease of the immovable property concerned. He submits that, there were existing structures on which renovations were done by the respondent nos.7 to 10.

9. We find from the records that, the appellants approached the District Magistrate with an allegation of unauthorized construction by the letter dated March 28, 2024.

10. Court is informed that, the immovable property concerned is located under a Panchayat area and is governed by the West Bengal Panchayat Act, 1973. Under the provisions of the Act of 1973, allegations of unauthorized constructions are to be considered and decided by the Sub-Divisional Officer.

11. In the facts and circumstances of the present case, since the allegation is of unauthorized construction, the same does not fall within the purview of the West Bengal Public Land (Eviction of Unauthorized Occupants) Act, 1962. Consequently, Section 7 of the Act of 1962 is not attracted. In any event, District Magistrate misapplied the provisions of Section 1962 in returning a finding as recorded in his order dated January 20, 2025. The allegation of unauthorized construction remains unattended to till date. It is required to be decided upon by the Sub-Divisional Officer under