2026 Supreme(Online)(CERC) 186
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI
Petition No. 429/MP/2025
Coram:
Shri Jishnu Barua, Chairperson
Shri Harish Dudani, Member
Shri Ravinder Singh Dhillon, Member
Date of Order: 16.03.2026
In the matter of:
Petition under Section 79(1)(f) of the Electricity Act, 2003 read with Regulation 42 of the Central Electricity Regulatory Commission (Connectivity and General Network Access to the inter-State Transmission System) Regulations, 2022 (as amended) and Connectivity Sharing Agreement dated 24.02.2025 entered between Halvad Renewables Private Limited and Azure India Private Limited for seeking limited modification of in-principle grant of Connectivity issued by Central Transmission Utility of India for 130 MW at Gadag Pooling Station and thereby allowing the Petitioner to construct the dedicated transmission infrastructure.
And
In the matter of:
M/s Halvad Renewables Private Limited
..……..Petitioner
1st Floor, Eastern Wing, Thapar House, 124 Janpath New Delhi- 110001
Versus
Central Transmission Utility of India Limited
…….Respondent 1
Suadamini, 1st Floor, Plot No.2, Sector-29, Gurugram, Haryana-122001
Azure Power India Private Limited ..…..Respondent 2
DSC-304, Second Floor, DLF South Court, Saket District Centre, New Delhi – 110017
Parties Present:
Shri Shashwat Kumar, Advocate, HRPL
Shri Rahul Chouhan, Advocate, HRPL
Shri Harshit Gupta, Advocate, HRPL
Shri Mukut Choudhary, Advocate, HRPL
Shri Rajiv Yadav, Advocate, HRPL
Shri Ajay Mehrotra, HRPL
Ms. Harleen Kaur, HRPL
Shri Shubham Arya, Advocate, CTUIL
Ms. Pallavi Saigal, Advocate, CTUIL
Shri Rishabh Saxena, Advocate, CTUIL
Ms. Muskan Agrawal, CTUIL
Sd/ Sd/ Sd
(Ravinder Singh Dhillon) (Harish Dudani) (Jishnu Barua)
Member Member Chairperson
ORDER
Halvad Renewables Private Limited has filed the instant Petition under Section 79(1)(f) of the Electricity Act, 2003 read with Regulation 42 of the Central Electricity Regulatory Commission (Connectivity and General Network Access to the inter-State Transmission System) Regulations, 2022 and Connectivity Sharing Agreement dated 24.02.2025 entered between Halvad Renewables Private Limited and Azure India Private Limited, seeking modification of in-principle grant of Connectivity issued by Central Transmission Utility of India for 130 MW at Gadag Pooling Station.
2. The Petitioner has made the following prayers in the present Petition:
(a) Admit the present Petition;
(b) Exercise its powers under Regulation 42 of the Central Electricity Regulatory Commission (Connectivity and General Network Access to the inter-State Transmission System) Regulations, 2022 (as amended) so as to direct Respondent No.1, Central Transmission Utility of India Limited, to modify the Connectivity Grant Letter dated 27.01.2025, thereby recognizing the Halvad Renewables Private Limited as the entity which shall develop the dedicated transmission infrastructure as the Lead Generator in accordance with the mutually executed FORMAT-CONN-SHARE Agreement dated 24.02.2025 as per its applicable connectivity timelines ;
(c) Allow the Petitioner to set up the connectivity infrastructure by 31.12.2026 or such extended period as the Hon’ble Commission may grant to the prayer (d) herein;
(d) Exclude the time period with respect to the start date of Connectivity for the Petitioner, accounting for delays arising due to the present litigation, thereby ensuring that the Petitioner does not suffer any adverse regulatory consequences or financial penalties due to circumstances beyond its control; and
(e) Pass such other Order(s) that this Hon’ble Commission may deem fit and proper under the facts and circumstances presented herein in the interest of justice.
Submissions of the Petitioner
3. The petitioner has made the following submissions:
a) On 02.02.2023, the Petitioner, Halvad Renewables Private Limited (HRPL), submitted a Stage-II ISTS Connectivity application for 130 MW at the Gadag PS.
b) During the 17th Consultation Meeting for Evolving Transmission Schemes (CMETS), on 31.03.2023, it was proposed that HRPL be granted Stage-II Connectivity for 130 MW at Gadag PS on a shared basis with Azure Power, considering the available transmission margin was exclusively within the dedicated connectivity infrastructure of Respondent No.2, i.e., Azure Power. Azure Power had already been granted ISTS Connectivity for 170 MW at Gadag PS by CTUIL.
c) HRPL, vide letter dated 09.12.2024, requested CTUIL to grant Connectivity for 130 MW at Gadag PS with a start date of 31.12.2026.
d) A meeting was convened on 13.11.2024 between the representatives of HRPL and Azure Power to deliberate upon the sharing of connectivity infrastructure for their respective 130 MW and 170 MW ISTS Connectivity at Gadag PS, regarding the construction and operation of the 220 kV Dedicated Transmission Line (“DTL”) and the associated switching substation. Both parties mutually agreed that HRPL would take on the role of Lead Generator and would develop the DTL, switching substation, and the necessary infrastructure to ensure seamless connectivity to Gadag PS, incorporating provisions for Azure Power to integrate into the system.
e) CTUIL, vide letter dated 27.01.2025, granted in-principle grant for Connectivity to HRPL for 130 MW at Gadag PS on a sharing basis of DTL with Azure Power with start date of Connectivity as 31.12.2026 as per which DTL, including the 220 kV pooling station at the switchyard of Azure Power and the associated 220 kV Gadag PS single circuit (S/c) transmission line, has to be constructed by Azure Power.
f) HRPL and Azure Power executed the Sharing Agreement on 24.02.2025. HRPL has been designated as the Lead Generator under Regulation 2(y) of the CERC GNA Regulations, 2022,