SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Chh) 7364

IN THE HIGH COURT OF CHHATTISGARH AT BILASPUR
Bibhu Datta Guru, J
D.K. Bhuiya – Appellant
Versus
A. K. Sinha – Respondent
ARBA No. 4 of 2023



Advocates:
For the Appellants/Petitioners: Sweksha Sharma
For the Respondents: Punit Ruparel

Limitation for challenging an arbitral award under Section 34(3) of the Arbitration and Conciliation Act, 1996, commences only from the date the party receives a signed copy of the award as mandated by Section 31(5), not from the date of the award's pronouncement.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 31(5), 34(3), 36 and 37 - Limitation Act - Section 5 - Limitation for setting aside arbitral award - Delivery of signed copy of award is mandatory - Limitation of three months under Section 34(3) must be reckoned from the date on which the party received a signed copy of the award as mandated by Section 31(5) - In absence of finding on service of award, rejection of application solely on the basis of the date of the award is not legally sustainable. (Paras 7, 8, 10, 12 and 14)

Facts of the case:
An appellant purchased a flat from a developer, leading to construction disputes. While a consumer dispute was settled amicably, the respondent obtained an ex parte arbitral award dated 18.08.2016. The appellant claimed non-receipt of the signed award and gained knowledge of it only during execution proceedings in July 2019. An application under Section 34 was filed on 04.01.2022, which was rejected by the District Court on grounds of limitation.

Findings of Court:
The court found that the District Court erred by reckoning limitation from the date of pronouncement of the award rather than the date of receipt of the signed copy. Without establishing compliance with Section 31(5) through cogent material, the application cannot be rejected purely based on the date of the award.

Issues: Whether the rejection of the Section 34 application on the ground of limitation was justified without verifying the date of receipt of the signed copy of the award under Section 31(5).

Ratio Decidendi: If the signed copy of the arbitral award is not delivered to the party, it does not amount to compliance with Section 31(5), and the three-month limitation period under Section 34(3) must be computed from the date the party actually receives the signed copy, not from the date of the award's pronouncement.

Result: Appeal allowed.

C A V Judgment

1. This Appeal under Section 37 of the Arbitration and Conciliation Act,

1996 (henceforth ‘the Act, 1996’) is directed against the order dated

05.11.2022 passed by the learned II Additional District Judge, Durg

(C.G.) in M.J.C. Civil No. 17/2022, whereby the learned Court has

2

ARBA No. 4 of 2023

rejected the application preferred by the appellant under Section 34 of

the Act, 1996 on the ground of limitation by declining to condone the

delay, and consequently affirmed the arbitral award dated 18.08.2016

passed by the learned Sole Arbitrator.

2. (a) Briefly stated facts of the case are that the appellant purchased

Flat No. 21 situated on the second floor of “Kanchanpuram Apartment”

from the respondent/developer pursuant to an agreement dated

19.12.2007 for a total sale consideration of ₹16,50,000/-, which amount

was admittedly paid through cheques. Subsequently, the said amount

reached upto ₹25,00,000/- owing to interior, furniture, putti work, etc.

According to the appellant, despite receipt of the entire consideration,

the respondent failed to provide the promised amenities and delivered

possession of a flat suffering from serious construction defects,

including deficient finishing work, non-functional lift facility, etc.

thereby compelling the appellant to institute Consumer Complaint No.

CC/14/69 before the District Consumer Disputes Redressal Forum,

Durg, on 12.03.2014 alleging deficiency in service and unfair trade

practice. The District Forum, upon appreciation of the material on

record, allowed the complaint vide order dated 22.08.2015 and awarded

compensation of ₹4,55,000/- in favour of the appellant. In appeal

preferred by the respondent, the State Commission remanded the matter

for technical inspection. Thereafter, upon reconsideration and in light of

the inspection report, the District Forum once again awarded

compensation of the same amount of ₹4,55,000/- by order dated

3

ARBA No. 4 of 2023

19.12.2016. The respondent carried the matter in further appeal,

whereupon the State Commission, vide order dated 22.04.2017, partly

modified the award and reduced to ₹3,23,000/- (Rs.2,23,000/- towards

compensation and Rs.1,00,000/- towards mental harassment). The

respondent herein thereafter filed Revision Petition No. 1421/2017

(Arvind Sinha @ A.K. Sinha v Dilip Kumar Bhuiyan) before the National

Commission, New Delhi, wherein the respondent herein personally

appeared before the Forum and the appellant herein represented through

his counsel and made a submission that the parties arrived at an amicable

settlement for a sum of ₹2,23,000/-, and the proceedings were finally

disposed of on 06.02.2018 in terms of the compromise, thus bringing the

consumer dispute between the parties to a quietus.

(b) It is the appellant/buyer’s case that notwithstanding the aforesaid

proceedings, disputes purportedly arising out of the same agreement

dated 19.12.2007 were referred to arbitration, and the learned Sole

Arbitrator proceeded ex parte to pass an award dated 18.08.2016

directed the appellant/buyer to pay an amount of Rs.4,03,000/- along

with interest at the rate of 18% per annum to the respondent/developer.

The appellant asserts that no signed copy of the arbitral award was ever

delivered to him in the manner contemplated under Section 31(5) of the

Act, 1996, and that he remained unaware of the said award. According to

him, knowledge of the award was acquired for the first time on

23.07.2019 during the course of execution proceedings initiated by the

respondent under Section 36 of the Act in Execution Case No. 267/2017.

4

ARBA No. 4 of 2023

Immediately upon gaining such knowledge, the appellant, acting bona

fide and within the statutory period computed from the date of

knowledge, filed an application under Section 34 of the Act, 1996 on

07.09.2019, however, the said application was inadvertently filed in the

pending execution proceedings instead of by way of an independent

application. The application was subsequently withdrawn on 21.12.2021,

and thereafter a properly constituted applic

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top