2025 Supreme(Online)(Chh) 20463

IN THE HIGH COURT OF CHHATTISGARH AT BILASPUR
Mrs. Poonambala Jaiswal – Appellant
Versus
State Of Chhattisgarh – Respondent
Case No : CR/26/2017



2025:CGHC:5346 AFR HIGH COURT OF CHHATTISGARH AT BILASPUR CIVIL REVISION NO. 26 OF 2017

1. Mrs. Poonambala Jaiswal, W/o Late Shri Anil Jaiswal, aged aout 48 years, R/o Awanti Vihar, Sector 2, S-33 Raipur, District Raipur, Chhattisgarh.

2. Janmejay Karan, S/o Anil Jaiswal, aged about 24 years, R/o Awanti Vihar, Sector 2, S-33, Raipur, District Raipur, Chhattisgarh.

3. Janmejay Kanisha, D/o Anil Jaiswal, aged about 22 years, R/o Awanti Vihar, Sector 2, S-33, Raipur, District Raipur, Chhattisgarh.

... Petitioner(s)

Versus

1. State of Chhattisgarh, through: the Secretary, Panchayat and Grameen Vikas Vibhag, Mantralaya, Naya Raipur, District Raipur, Chhattisgarh.

2. Chief Engineer, C.G. Rural Road Development Agency, Civil Lines, Raipur, District Raipur, Chhattisgarh.

3. Executive Engineer, Project Implementation Unit No.

05, P.M.G.S.Y. Dongargarh, District Rajnandgaon, Chhattisgarh.

... Respondent(s)

----------------------------------------------------------------------------------

For Petitioner :- Ms. Astha Shukla, Advocate.

For Respondent-State :- Mr. Rahul Tamaskar, Govt. Advocate and Mr. Sharad Mishra, Panel Lawyer.

----------------------------------------------------------------------------------

[ Single Bench ]

Hon'ble Shri Justice Sanjay K. Agrawal

Order on Board

(29-01-2025)

1. This Civil Revision is directed against the Award dated

22.11.2016 passed by Chhattisgarh Madhyastham Adhikaram, Raipur ('Adhikaran' for brevity) in Reference Case No.9/2014, rejecting the claim of the Petitioners for refund of security amount, cost of maintenance, damages and interest etc.

2. The aforesaid challenge has been made on the following factual background of the case:-

(i) In September, 2008 the State of Chhattisgarh had floated Notice Inviting Tender for construction and maintenance of 11 Rural Roads under Pradhan Mantri Gram Sadak Yojana, Package No. CG-15-82 of District Rajnandgaon for the year 2008-09. As per the tender, the total amount of contract value was Rs. 843.32 Lakh and the contract period was for 12 months for completion of work till 14.10.2009.

(ii) The original Petitioner Late Anil Kumar Jaiswal being the lowest bidder was awarded the contract and the Agreement was executed between the parties on

1.10.2008 and the accepted value of work was Rs. 659.88 Lakh. The price of the contract was further revised to Rs. 570.61 Lakh. The extension was granted for completion of work till 15.1.2010 on account of naxal problem in executing the work.

(iii) The Petitioners completed 9 out of 11 roads, as one road i.e., Chhuikhadan to Budhanbhat, was already completed by the Public Works Department. However, the road relating to 'Tendubhata to Sarodhi' could not be completed on account of naxal problem. Hence, the Petitioners requested the Respondents for the foreclosure of the contract in light of clause 55.1 of the Agreement. The Executive Engineer wrote a letter to the Superintending Engineer for the foreclosure of the contract under clause 55.1, pursuant to which the Superintending Engineer in turn also wrote a letter (Annexure P-3/4) to the Chief Executive Officer for the foreclosure of the contract under clause 55.1 of the Agreement.

(iv) On 26.5.2010 (Ex. P-3), permission was granted by the Chief Executive Officer for the foreclosure of the contract for package No.15-82 as per Clause 55.1 of the Agreement with certain conditions that the Petitioners will complete the construction of the said road under a separate piece-rated work agreement as the main agreement was agreed to be foreclosed.

(v) Ultimately, on 28.5.2010 (Ex. P-3/2) the work was completed by the Petitioners and Work Completion Certificate was issued by the Executive Engineer-cum- Member Secretary, PUI-5, Pradhan Mantri Gram Sadak Yojna. Thereafter, the Petitioners requested for finalization of the final bill amounting to Rs.7,80,917/- which could not be finalized by the Respondents, but the Respondents issued notice to the Petitioners for recovery of Rs.28.211 Lakh towards imposed liquidated

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top