2026 Supreme(Online)(Chh) 11262

IN THE HIGH COURT OF CHHATTISGARH AT BILASPUR
Bibhu Datta Guru, J
Nidhi Sao – Appellant
Versus
Greenearth Infraventures Private Limited – Respondent
MA No. 173 of 2023



Important Points

The Limitation Act, 1963 does not apply to complaints filed before the Real Estate Regulatory Authority (RERA) under Section 31 of the Real Estate (Regulation and Development) Act, 2016, as RERA is not a 'Court' and the Act does not prescribe a limitation period.

Subject

Real Estate Law - Limitation and Procedure

Act Referred

Headnote

(A) Real Estate (Regulation and Development) Act, 2016 - Section 31(1) and 58 - Limitation Act, 1963 - Article 137 - Applicability of Limitation Act to proceedings before RERA - Whether complaint filed under Section 31(1) is subject to limitation - Held, RERA is a specialized regulatory body and not a ‘Court’ within the meaning of the Limitation Act - Statute does not prescribe any period of limitation for filing a complaint - Appellate Tribunal erred in importing principles of Article 137 to dismiss complaint as time-barred. (Paras 13, 14, 15, 17, 18)

(B) Appellate Procedure - Procedural Irregularity - Tribunal dismissing appeal on a ground (limitation) not raised before the original Authority and for which no issue was framed - Appellate court ought to decide matters on merits rather than introducing fresh grounds without factual or legal basis at the appellate stage. (Paras 23, 24)

Facts of the case:
The appellant entered into a sale agreement for a flat in 2012. Alleging substandard construction and delays, the appellant filed a complaint before the RERA. The RERA dismissed the complaint but directed the promoter to complete finishing work and hand over possession. The appellant appealed to the Real Estate Appellate Tribunal. The Tribunal, sua motu, dismissed the appeal on the ground of limitation.

Findings of Court:
The Court held that the Real Estate (Regulation and Development) Act, 2016 does not prescribe a limitation period for filing complaints under Section 31. The Limtation Act only applies to courts, and RERA is not a court. The Tribunal's dismissal of the appeal on the basis of limitation was erroneous and procedurally irregular.

Issues: Whether the Real Estate Appellate Tribunal erred in dismissing the complaint on the ground of limitation and whether the Limitation Act applies to proceedings before the RERA.

Ratio Decidendi: There is no statutory period of limitation prescribed under the Real Estate (Regulation and Development) Act, 2016. As the RERA is a quasi-judicial regulatory body and not a 'Court', and there is no express provision extending the application of the Limitation Act, proceedings before the RERA are not governed by the Limitation Act, 1963.

Result: Appeal allowed; impugned order set aside and matter remanded for decision on merits.

Advocates:
For the Appellants/Petitioners: Manish Nigam
For the Respondents: Mayank Kumar

Table of Content
1. procedural background and facts leading to the appeal. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7)
2. arguments of the parties regarding limitation and maintainability. (Para 8 , 9 , 10)
3. limitation act non-applicability to rera proceedings. (Para 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21)
4. irregularity in applying limitation at the appellate stage. (Para 22 , 23 , 24)
5. final order remanding the matter for fresh adjudication. (Para 25 , 26)

AFR

Judgment on Board

1. The appellant/allottee has preferred the present appeal under Section 58 of the Real Estate (Regulation And Development) Act, 2016 being aggrieved by the impugned order dated 15/09/2023 passed by the learned Chhattisgarh Real Estate Appellate Tribunal, Raipur (C.G.) (for brevity ‘the Tribunal’) in Appeal No.20/2022 (Smt. Nidhi Sao Vs. Green Earth Infraventures), arising out of the order dated 22.11.2018 passed by the learned Chhattisgarh Real Estate Regulatory Authority, Raipur, C.G. (for brevity ‘the RERA’) Case No. M-PRO-2018-00124 (Smt. Nidhi Sao Vs. Green Earth Infraventures), whereby, it was directed to the respondent/promoter to complete the finishing work of the apartment in question and to hand over possession of the same to the appellant/allottee within a period of two months and also directed that the appellant shall deposit the balance amount.

2. This is an admitted appeal. The following substantial question of law arises for adjudication of the matter :

“Whether the Chhattisgarh Real Estate

Appellate Tribunal erred in law in dismissing

the complaint filed by the appellant/allottee on

the ground of limitation ?”

3. With the consent of learned counsel appearing for the parties, the appeal is heard finally.

4. The appellant/allottee lodged a complaint against the respondent/ promoter before the RERA alleging, inter alia, that the appellant entered into a sale agreement on 26/05/2012, to purchase the Flat No. 210 in Block Orchid-4 situated in “Green Earth City” located in Amleshwar, Durg, developed by the respondent herein. The appellant alleges that the respondent was pressurizing her to take possession of the said apartment while demanding additional payment. The appellant has also complained that the quality of construction of the apartment in question is substandard. Thereafter, the appellant filed a complaint under Section 31 of the Real Estate (Regulation and Development) Authority Act, 2016 (for brevity ‘the Act’) in the prescribed format (Form M), for return of amount and compensation on account of inferior quality of construction and failure of the construction work within time as prescribed in the sale agreement executed between the parties on 26/05/2012.

5. Notice regarding the said complaint was issued to the respondent. The respondent appeared before the RERA and submitted a written reply, denying the allegations made by the appellant. The respondent stated that the appellant failed to make payments within the stipulated time as per the sale agreement dated 26/05/2012. The respondent also denied the allegations regarding inferior quality of construction. It further stated that due to the appellant’s failure to make timely payments, interest was levied on the outstanding amount in accordance with the terms of the sale agreement, and the same was demanded from the appellant. The allegation made by the appellant regarding the pressure to take possession of the apartment was also denied. Additionally, the respondent stated in the reply that the appellant had never raised any complaint or communicated any issue with them regarding the said apartment. The respondent further stated in reply that a completion certificate for the apartment in question was obtained from the competent authority on November 1, 2017.

6. After hearing the parties and upon due appreciation of the entire facts and circumstances of the case, on the basis of material available on record, t