Ravindra Kumar Agrawal, J
Paras Jain – Appellant
Versus
Steel Authority Of India Limited – Respondent
WP227 No. 506 of 2026



Important Points

Summary eviction proceedings under the relevant statute cannot be stalled by private civil litigation if the occupant fails to demonstrate a lawful source of title or valid authorization from the owner. Supervisory jurisdiction will not interfere where findings are supported by record and natural justice is afforded.

Subject

Property Law - Public Premises Eviction

Act Referred

Headnote

(A) Public Premises (Eviction of Unauthorised Occupants) Act, 1971 - Sections 4, 5-A, and 7 - Eviction from public premises - Summary eviction proceedings - Scope of supervisory jurisdiction under Article 227 - Parties claiming interest in public premises must establish lawful authority, such as valid allotment or lease - Mere possession or pendency of private civil litigation does not confer legal right or justify stay of eviction proceedings - Principles of natural justice satisfied where party has notice and opportunity to participate in proceedings. (Paras 20, 23, 26, 31)

(B) Transfer of Property Act, 1882 - Section 53-A - Doctrine of part performance - Applicability - Cannot be invoked to support occupation of public premises in absence of valid, enforceable contract derived from a person with transferable interest - Doctrine does not create independent title where basic entitlement is non-existent. (Paras 17, 28)

Facts of the case:
The petitioner challenged an appellate order confirming an eviction notice and assessment of damages from public premises. The petitioner claimed interest through an agreement for sale from an original allottee who had allegedly completed financial obligations but failed to obtain a registered lease. The authority initiated proceedings against unauthorized occupants after detecting illegal construction. The petitioner sought to stay these proceedings pending the outcome of a civil suit for specific performance.

Findings of Court:
The court observed that the petitioner failed to produce any valid allotment order or lease granted by the competent authority. The civil suit regarding specific performance was already decided against the petitioner, and its pendency in appeal did not negate the authority's power to act under the relevant statute. The procedural requirements had been met, as the petitioner had been given ample opportunity to present her case.

Issues: Whether the initiation of summary eviction proceedings against alleged unauthorized occupants in the presence of pending civil litigation is legally sustainable, and whether the petitioner’s continued occupation is protected under the doctrine of part performance.

Ratio Decidendi: Summary eviction proceedings under the statute are not precluded by the mere pendency of private civil disputes when the occupant fails to establish a prima facie lawful title or valid authorization from the public authority. The supervisory jurisdiction of the High Court is limited to correcting jurisdictional errors or patent perversity rather than re-appreciating evidence.

Result: Writ petition dismissed.

Advocates:
For the Appellants/Petitioners: Prafull N. Bharat, Maulik Bhansali
For the Respondents: Pankaj Singh

Table of Content
1. historical background and procedural history of property eviction dispute. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. petitioner argues for legitimacy of possession and procedural flaws in eviction. (Para 7 , 8 , 9 , 10 , 11 , 12 , 13)
3. respondent contends unauthorized occupation, citing lack of valid leasehold interest. (Para 14 , 15 , 16 , 17 , 18)
4. court upholds legality of eviction due to absence of valid conferment of leasehold rights. (Para 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33)
5. dismissal of the writ petition due to lack of merit. (Para 34 , 35)

Order on Board

1. The petitioner has filed the present writ petition against the order dated 08.04.2026, passed by the learned Principal District Judge, Durg, in MCA Case No. 39/2021, whereby the Misc. Civil Appeal filed by the petitioner has been dismissed, and the order dated 07.10.2021, passed by the Estate Officer, under the Public Premises (Eviction of Unauthorized Occupants) Act, 1971, Bhilai Nagar, District Durg, in Case No. 93/2017, is affirmed. The petitioner prayed for the following reliefs in the present writ petition:-

“A. A writ and/or an order in the nature of appropriate writ setting aside the Impugned Appellate Order dated 08.04.2026 passed by the Ld. Principal District Judge, Durg in MCA No. 39/2021 (Annexure P-1) Eviction Order dated 07.10.2021 passed by Estate Officer (Annexure P-2).

B. Purely as an interim measure, during the pendency and final hearing of the present Writ Petition, stay the execution, operation, and effect of the Impugned Orders, and restrain the Respondents from forcibly evicting the Petitioner or recovering the alleged damages of Rs. 27,52,489/-.

C. Any other relief which this Hon'ble Court may deem fit in facts & circumstances of the present case.

D. Cost of the petition may also be awarded.”

2. The genesis of the present dispute traces back to the allotment of Plot No.151, admeasuring 1000 square metres, situated at New Civic Centre, Bhilai, pursuant to an advertisement issued by Respondent No.1, Bhilai Steel Plant, on 18.05.1987. In the said process, Respondent No. 2 was declared the successful bidder and an Offer Letter dated 17.07.1989 was issued in his favour. Thereafter, Respondent No.2 deposited the entire premium and other charges as demanded by Respondent No.1, the last payment having been made on 04.05.1990. Upon completion of all requisite formalities, a lease deed was prepared and corrected from time to time, which was executed by Respondent No.2 on 29.03.1994 and was duly approved and signed by the competent authority of Respondent No.1 on 29.09.1994, as reflected in the official note sheets No. 14/N, maintained by Bhilai Steel Plant. Thus, all substantive requirements for the creation of leasehold rights stood fulfilled, and only the ministerial act of registration remained pending, which was not completed for reasons wholly attributable to the authorities of Respondent No.1.

3. After having acquired leasehold rights in the subject property, Respondent No.2 entered into an Agreement for Sale dated 13.04.1994 in favour of the Petitioner for the consideration of Rs. 1,20,000/-, and simultaneously handed over the possession of the subject property to the Petitioner. A Power of Attorney was also executed in favour of the Petitioner's husband authorizing him to undertake all acts necessary for the protection and management of the property. Since the date of the said transaction, the Petitioner has remained in settled, open, continuous and peaceful possession of the subject property. The possession and interest of the Petitioner were not concealed from Respondent No.1 and, in fact, the same stood expressly acknowledged in the internal records of Bhilai Steel Plant (28/N) as early as 27.11.1995. Despite having complete knowledge of the transfer and the Petitioner's possession, Respondent No.1 neither objected to the same nor initiated any proceedings for cancella