2026 Supreme(Online)(Chh) 18456
IN THE HIGH COURT OF CHHATTISGARH AT BILASPUR
Bibhu Datta Guru, J
Kanhaiya Lal Prasad – Appellant
Versus
Indrajit Uikey – Respondent
CONT No. 72 of 2026 | W.P.(S) No.5395 of 2024
Important Points
Subject
Civil - Contempt of Court
Act Referred
Headnote
For the Appellants/Petitioners: Sandeep Shrivastava
For the Respondents: Rakesh Kumar Jha
| Table of Content |
|---|
| 1. allegation of willful disobedience of court directions regarding retiral dues. (Para 1 , 2 , 3) |
| 2. verification of factual compliance with the direction to take a decision. (Para 4 , 5 , 6 , 7) |
| 3. distinction between compliance of an order and the correctness of the resulting decision. (Para 8 , 9) |
| 4. discharge of rule and dismissal of contempt petition upon satisfaction of compliance. (Para 10 , 11) |
Order on Board
Heard.
1. The present contempt petition has been filed alleging wilful and deliberate disobedience of the order dated 17.02.2025 passed by this Court in W.P.(S) No.5395 of 2024.
2. The brief facts of the case are that the petitioner had earlier approached this Court by filing W.P.(S) No.5395 of 2024 questioning the recovery of two advance increments allegedly granted to him and the consequential withholding of a part of his retiral dues. Upon consideration of the rival submissions, this Court disposed of the writ petition by order dated 17.02.2025 with the following direction:
"8….Thus, considering the facts and circumstances of the case,
the respondents No.2 to 5 are directed to take an appropriate
decision on the claim of the petitioner for settlement of his
retiral dues particularly in respect of non releasing of 10
percent of retiral dues which has been withheld. Let an
appropriate decision be taken within an outer limit of 60 days
from the date of receipt of copy of this order. While taking a
decision, the concerned respondents shall take into
consideration the circular of the erstwhile Madhya Pradesh
State Government dated 04.04.1987 in respect of increment
which has been granted to the petitioner in the year 2001."
3. The allegation in the present contempt petition is that the aforesaid direction has not been complied with and, therefore, the respondents have rendered themselves liable for action under the Contempt of Courts Act, 1971.
4. This Court has carefully examined the order passed in W.P.(S) No.5395 of 2024 as well as the documents annexed by the petitioner himself along with the present contempt petition. A plain reading of the order dated 17.02.2025 would show that this Court did not issue any specific direction for release of the withheld retiral dues or for grant of any particular relief in favour of the petitioner. The direction issued by the writ Court was limited in nature, namely, to take an appropriate decision on the petitioner's claim while taking into consideration the circular dated 04.04.1987.
5. Vide covering memo the petitioner has filed a copy of the communication dated 21.04.2026 issued by the Office of the Joint Director, Treasury, Accounts and Pension, Bilaspur Division, Bilaspur. The said communication reveals that the case of the petitioner was examined with reference to the circular dated 04.04.1987 and the service particulars of the petitioner. The authority concerned considered the question as to whether the petitioner was entitled to the benefit of advance increments on account of acquisition of M.A. (English) qualification and recorded its conclusions thereon.
6. By the same covering memo the petitioner also placed a copy of communication dated 24.04.2026 issued by the Executive Engineer, Hasdeo Barrage Project, Rampur, Korba to the Chief Engineer, Minimata (Hasdeo) Bango Project. From bare perusal of the same it is evident that copy of the same has been endorsed to the petitioner. The said communication specifically refers to the order passed by this Court in W.P.(S) No.5395 of 2024 and also takes note of the opinion/decision communicated by the Joint Director, Treasury, Accounts and Pension, Bilaspur Division. The communication records that upon examination of the matter, the petitioner was found not entitled to the benefit claimed by him under the circular dated 04.04.1987.
7. Therefore, from the documents filed by the petitioner himself, it is evident that subsequent to the order dated 17.02.2025, the competent authorities examined the petitioner's claim, consid