2026 Supreme(Online)(Chh) 21849

HIGH COURT OF CHHATTISGARH AT BILASPUR
Ramesh Sinha, CJ, Ravindra Kumar Agrawal, J
M/s. DYNAMI ENTERPRISES – Appellant
Versus
UNION OF INDIA – Respondent
WPC No. 3783 of 2026



Important Points

Blacklisting a contractor is a punitive measure causing grave civil consequences ("civil death") and requires a specific show-cause notice disclosing the proposed penalty to satisfy the principles of natural justice, regardless of whether the underlying contract is terminated.

Subject

Civil - Government Contract

Act Referred

Headnote

The petitioner, a partnership firm, challenged a composite order dated 01.04.2026 issued under the General Conditions of Contract, which terminated its contract for providing diesel-operated forklifts and debarred it from future tenders for two years. The petitioner sought relief under Article 226 of the Constitution of India, alleging that the termination was contrary to contractual stipulations and the blacklisting was passed without a mandatory show-cause notice, violating the principles of natural justice. The primary issues were whether a writ petition is maintainable despite an arbitration clause in the agreement and whether the order of blacklisting was legally sustainable. The court reasoned that while disputes regarding contractual performance are generally relegated to arbitration, the action of blacklisting is a punitive administrative measure that visits a contractor with grave civil consequences, akin to "civil death." Consequently, such actions are subject to judicial review under Article 226 to ensure fairness and adherence to the principles of natural justice, requiring a specific show-cause notice that explicitly discloses the proposed penalty of blacklisting. Resultantly, the writ petition is partly allowed. The impugned order dated 01.04.2026 is upheld to the extent it terminates the contract, leaving it open to the petitioner to avail the contractual remedy under Clause 8.2 of the agreement. However, the impugned order is set aside to the extent it debars/blacklists the petitioner for a period of two years.

Advocates:
For the Appellants/Petitioners: Abhishek Vinod Deshmukh
For the Respondents: Ramakant Mishra

Table of Content
1. background of contract award and subsequent termination and blacklisting of the petitioner. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. rival contentions regarding the violation of natural justice and the maintainability of the writ petition. (Para 7 , 8 , 9 , 10 , 11 , 12)
3. writ jurisdiction is maintainable despite an arbitration clause when administrative actions are arbitrary or violate natural justice. (Para 13 , 14 , 15 , 16 , 18)
4. blacklisting is a punitive measure requiring a specific show-cause notice, distinct from contractual termination. (Para 17 , 19 , 20 , 21 , 22 , 23)
5. termination is referred to arbitration, while blacklisting is quashed for lack of procedural fairness. (Para 24 , 25 , 26 , 27 , 28)

Order on Board

Per Ramesh Sinha , Chief Justice

1. Heard Mr. Abhishek Vinod Deshmukh, learned counsel for the petitioner as well as Mr. Ramakant Mishra, learned Deputy Solicitor General, appearing for the respondents.

2. Though the matter is listed as a fresh case, considering the submission of learned counsel appearing for the respondents that no reply is required to be filed in the present matter as the agreement contains an arbitration clause and that no show-cause notice has been issued to the petitioner, accordingly, with the consent of learned counsel for the parties, the matter is heard finally at the admission stage itself.

3. By filing the present petition under Article 226 of the Constitution of India, the petitioner calls in question the termination letter dated 01.04.2026, whereby its contract has been terminated and it has also been debarred/blacklisted from participating in future tenders for a period of two years. The petitioner has prayed for following relief(s) :-

“1] That, this Hon'ble Court may kindly be pleased to writ/writs, order/orders, direction/directions quashing the termination notice dated 01.04.2026 issued by the Respondent No. 3, whereby the Contract of the Petitioner has been terminated and the Petitioner has been debarred for a period of 2 years from participating in the bids;

2] That, this Hon'ble Court may kindly be pleased to grant any other relief(s), which is deemed fit and proper in the aforesaid facts and circumstances of the case.”

4. Briefly stated, the petitioner is a partnership firm engaged in providing services to the Indian Railways. The respondents issued a Notice Inviting Tender for hiring two diesel-operated 3T forklifts along with operators at ROH Depot, PP Yard, Bhilai for a period of two years. The petitioner participated in the tender process and, having emerged as the successful bidder, was awarded the contract vide agreement dated 26.05.2025 for execution of the said work.

5. Pursuant to the award of the contract, the petitioner deployed the requisite machinery, operators and supervisory staff and commenced execution of the work. According to the petitioner, it kept the respondents informed regarding deployment of equipment, appointment of personnel, readiness to commence operations and other operational requirements. It is further the petitioner's case that whenever any difficulty arose during execution of the contract, including repair of machinery or submission of requisite documents, the same was duly intimated to the respondents and necessary permissions were sought. The petitioner also claims to have brought to the notice of the respondents instances of unauthorized use of the deployed vehicles and sought permission to install CCTV cameras for effective monitoring.

6. It is the petitioner's case that while the contract was being performed, the respondents issued a performance notice dated 27.02.2026 alleging deficiencies in execution of the work. Thereafter, without issuing the mandatory seven days' notice contemplated under the General Conditions of Contract and without affording any opportunity to explain the alleged deficiencies or to show cause against the proposed debarment/blacklisting, the respondents

1