2023 Supreme(Online)(Del) 25612
DELHI HIGH COURT
MAHANAGAR TELEPHONE NIGAM LTD – Appellant
Versus
M/S RALHAN CONSTRUCTION COMAPNY – Respondent
FAO-271/2019
Neutral Citation Number : 2023/DHC/000679
FAO 271/2019
Page 1 of 11
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
FAO 271/2019 & CM. APPL. 31033/2019
Reserved on
: 09.11.2022
Pronounced on
: 31.01.2023
IN THE MATTER OF:
MAHANAGAR TELEPHONE NIGAM LTD.
..... Appellant
Through:
Ms. Suruchi Suri, Advocate.
versus
M/S RALHAN CONSTRUCTION COMPANY
..... Respondent
Through:
Ms.Anusuya
Salwan,
Ms.Nikita
Salwan,
Mr.Bankim
Garg
and
Mr.Rachit Wadhwa, Advocates.
CORAM:
HON'BLE MR. JUSTICE MANOJ KUMAR OHRI
JUDGMENT
MANOJ KUMAR OHRI, J.
1. By way of present appeal filed under Section 37(1)(b) of the
Arbitration & Conciliation Act, 1996 (hereinafter, referred to as ‘the
Arbitration Act’), the appellant has assailed order dated 16.04.2019 passed
by the learned ADJ-07, South-East, Saket Courts, New Delhi in Arb. No.
212/2018, whereby its objections under Section 34 of the Arbitration Act to
Award dated 09.05.2018 (and subsequent amendments thereto) were
dismissed.
Digitally Signed
By:SANGEETA ANAND
Signing Date:01.02.2023
11:55:50
Neutral Citation Number : 2023/DHC/000679
FAO 271/2019
Page 2 of 11
2. Though the present appeal was filed by the appellant seeking setting
aside of the order dated 16.04.2019, the Award dated 09.05.2018, and the
subsequent amendments thereto, learned counsel for the appellant, on
instructions, restricted her challenge during the course of submissions only
to respondent’s claim Nos. 2 and 3, which were in relation to release of
balance payment of security deposit lying with the Department, directed to
be released to the respondent vide the Award.
3. Facts of the case, pithily put, are that the appellant had floated a
tender dated 20.11.2007 for the civil and electrical portion of construction of
Automobile Workshop-cum-Administrative building at Rohini, Sector-VI,
Delhi. The said work was awarded to the respondent for a consideration
amount of Rs. 18,68,11,252/-. The time stipulated for completion of the
work was 18 months from the date of issuance of letter of award.
Purportedly, the civil component of the work was completed on 31.12.2011
and the electrical part was completed on 07.06.2013.
A dispute arose between the parties relating to payments under the
agreement, which led the respondent to initiate arbitration proceedings in
terms of Clause 53 thereof. The matter was adjudicated by a Sole Arbitrator,
who passed an Award dated 09.05.2018, allowing all claims of the
respondent either partially or fully, except claim Nos. 18 and 20.
Subsequently, two amendments dated 11.05.2018 and 12.05.2018 were
made to the Award by the Arbitrator.
The appellant filed its objections under Section 34 of the Arbitration
Act before the learned District and Sessions Judge, West, Saket Courts,
praying that the Award dated 09.05.2018 (and the subsequent amendments
Digitally Signed
By:SANGEETA ANAND
Signing Date:01.02.2023
11:55:50
Neutral Citation Number : 2023/DHC/000679
FAO 271/2019
Page 3 of 11
thereto) be set aside. However, the objections were dismissed vide the order
impugned herein, i.e. order dated 16.04.2019.
4. Learned counsel for the appellant contended that the Arbitrator erred
in interpreting Clause H, Special Conditions of Contract in the Agreement
between the parties to conclude that it was the appellant’s responsibility to
file application for obtaining completion/occupancy certificate from local
authorities. It was further contended that in reaching the above conclusion,
the Arbitrator also erred in relying upon the ‘Hand Book of Building Permit
Procedure 2006, Delhi Development Authority’, as the same was not
executed between the parties and was an extraneous document filed by the
respondent. On strength of the aforesaid, it was argued that the impugned
Award was arbitrary, capricious and beyond the scope of mutually agreed
terms in the contract entered between the parties. Learned counsel also
contended t