2024 Supreme(Online)(DEL) 24988
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI JUDGMENT RESERVED ON: 21.12.2023 JUDGEMENT PRONOUNCED ON:24.01.2024 + ARB.P. 667/2023 VINGRO DEVELOPERS PVT. LTD. ..... Petitioner Through: Mr. Mohit Potalia, Adv. (VC)
versus NITYA SHREE DEVELOPERS PVT. LTD. THROUGH ITS PRINCIPAL OFFICER & ORS. ..... Respondents Through: Mr.Nityanand Singh and Ms.Aachal Sah, Advs. CORAM:
HON'BLE MR. JUSTICE DINESH KUMAR SHARMA
J U D G M E N T
DINESH KUMAR SHARMA, J.
1. The present petition has been filed under section 11 of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator for adjudication of the disputes inter-se having been arisen between the parties out of agreements dated 18.11.2016 and 08.02.2017 with respect to the purchase of plots in the Respondent‟s project.
2. A bare perusal of the material on record reflects that Respondent No.1 being engaged in the business of development and construction of real estate entered the two Builder Buyer Agreements dated 18.11.2016 and Signature Not Verified Digitally Signed ARB.P. 667/2023 Page 1 of 15
08.02.2017 with the Petitioner with respect to the Respondent‟s Residential Township Project namely “RLF City” situated at Khasra No. 118, Khasra No. 120 & Khasra No. 431/119 at Village Salarpur, Tehsil Tijara, District Alwar Rajasthan 301019. The Respondent no. 2 and 3 are the directors and authorised representatives of Respondent No.1 and thereby, in this capacity, Respondent No.2 signed the Builder Buyer Agreements on behalf of Respondent no.1.
3. The parties executed 8 Builder Buyer Agreements dated 18.11.2016 for 8 plots of land admeasuring 125 sq. yds each and subsequently, 4 additional Builder Buyer Agreements dated 8.02.2017 were executed for four plots of land measuring 125sq. yds each. In total, agreements were executed with respect to 12 plots of land in the project.
4. The clause 29 and 30 of the Builder Buyer Agreements holds as is under:
“29. The Developer shall complete the development of the plot/project latest by December 30, 2016, except for any delay of not more than 60 days due to forcemajeure conditions as mentioned in clause 30 hereunder.”
“30. The Developer shall not be held responsible or liable for not performing any of its obligations or undertaking provided for in this Agreement if such performance is prevented, delayed or hindered by an act of God, Fire, Flood, Explosion, War, Riot, Terrorist acts, Sabotage. The Developer shall not be held liable for any delay in delivery or possession of the said plot to the BUYER if the delay is caused due to carrying out any alternate/ additional work demanded by the BUYER in the said plot at any point of time during development of the said plot.
If for Force Majeure reasons, the whole or part of the project is abandoned or delayed beyond 60 days, no other claim will be preferred except that BUYER will be refunded all amounts paid on demand along with interest @ 10% p.a. (calculated on monthly basis).”
Signature Not Verified Digitally Signed ARB.P. 667/2023 Page 2 of 15
5. In contravention of the terms stipulated within the agreements, the respondent no.1 has not yet handed over the possession of the plots to the petitioners despite many reassurances from the former‟s end. Pursuant to non-delivery, the petitioner sent a legal notice dated 12.10.2022 asking for a refund of the amount paid by the petitioners along with interest. Being not satisfied with the respondent‟s reply, the petitioner sent another notice dated 10.12.2022 for the same, which remained unacknowledged. The petitioner invoked arbitration vide notice dated 16.01.2023 as under Section 21 of the Arbitration & Conciliation Act, 1966 and as stipulated in the arbitration clause of the agreements dated
18.11.2016 and 08.02.2017 which provides as under:
“47. (c) All or any disputes arising out of or touching upon or in relations to the term of this Letter of Allotment including the interpretations and validity of the terms thereof and the respective rights and obligations of the parties shall be settled amicably by mutual discussions failing which the same shall be settled through Arbitrations. The arbitrations proceeding shall be governed by the Arbitration & Conciliations Act, 1996 and/or any statutory amendments/ modifications thereof for the time being in force. The arbitrations proceedings shall be held at an appropriate location in Gurgaon/Delhi. The courts at Del