2023 Supreme(Online)(Del) 25167
DELHI HIGH COURT
M/S ORIENTAL STRUCTURAL ENGINEERS PVT.LTD.-M/S KMC-JOINT VENTURE – Appellant
Versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA (NHAI) – Respondent
OMP_(COMM)-455_2018
O.M.P. (COMM) 455/2018
Page 1 of 19
$~P-1
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
Decided on: 09.11.2023
+
O.M.P. (COMM) 455/2018 & I.A. 3244/2023.
M/S ORIENTAL STRUCTURAL ENGINEERS PVT.LTD.-M/S
KMC-JOINT VENTURE
..... Petitioner
Through:
Ms. Kiran Suri, Senior Advocate with
Mr. Hitendra Nath Rath and Ms.
Aishwarya Kumar, Advocates.
versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA
(NHAI)
..... Respondent
Through:
Mr. Manish K. Bishnoi, Mr. Nirmal
Prasad and Ms. Pallavi Singh Bishnoi,
Advocates.
CORAM:
HON’BLE MR. JUSTICE PRATEEK JALAN
J U D G M E N T
1.
By way of this petition under Section 34 of the Arbitration and
Conciliation Act, 1996 [hereinafter, “the Act”], the petitioner assails an
arbitral award dated 21.04.2018, by which a three-member Arbitral Tribunal
has adjudicated disputes between the parties under a Contract Agreement
dated 04.11.2004 [hereinafter, “the Contract”].
A. Facts
2.
The Contract was awarded by the respondent-National Highways
Authority of India [hereinafter, “NHAI”] to the petitioner for construction of
part of a road known as the “Allahabad Bypass Project”. BCEOM-LASA JV
[hereinafter, “the Engineer”] was nominated by NHAI as the Engineer under
the Contract.
According to the petitioner, work under the Contract was
Digitally Signed By:SHITU
NAGPAL
Signing Date:09.11.2023
18:20:19
Signature Not Verified
O.M.P. (COMM) 455/2018
Page 2 of 19
substantially completed by 15.10.2009 and notice was given to the Engineer
for taking over the work on 15.11.2009. The Engineer issued Taking Over
Certificate under Clause 48.1 of the General Conditions of Contract
[hereinafter, “GCC”] on 11.12.2009. By a communication dated 15.11.2011,
the Engineer enumerated a list of pending work to the petitioner prior to
issuance of the Defects Liability Certificate.
3.
A joint meeting was held on 25.11.2011 with regard to the remaining
work to be completed. The petitioner agreed to complete the remaining work
and remedy the defects. The minutes of the aforesaid meeting contain
specific provisions with regard to claims for additional costs due to
reduction in scope of chain link fencing and crash barrier. The consequence
of these provisions is the subject matter of controversy in this petition and
they will be dealt with in detail later in this judgment.
4.
The Engineer issued the Defects Liability Certificate on 12.01.2012,
under Clause 62.1 of the GCC. Pursuant thereto, the petitioner submitted
supporting documents for draft final bill on 25.04.2012. On 06.05.2013, the
Engineer issued Interim Payment Certificate No. 57 [hereinafter, IPC No.
57] against the statement submitted by the petitioner, wherein it determined
the amount due to the petitioner. It recommended payment of a sum of Rs.
1,98,30,849/- against the petitioner’s final bill.
5.
It appears from the record that the respondent, thereafter, by a
communication dated 20.06.2013, pointed out certain discrepancies to the
Engineer, which resulted in a report of the Engineer dated 12.08.2013,
stating that the Defects Liability Certificate was issued after joint inspection
on 05.01.2012 and that IPC No. 57 was issued after detailed measurement of
each item. The record reveals that a meeting was thereafter held between the
Digitally Signed By:SHITU
NAGPAL
Signing Date:09.11.2023
18:20:19
Signature Not Verified
O.M.P. (COMM) 455/2018
Page 3 of 19
Engineer and the respondent on 09.04.2014, pursuant to which the Engineer
issued a letter dated 06.05.2014, revising IPC No. 57 downwards.
Significantly, the petitioner was admittedly not party to the documents and
meetings dated 20.06.2013, 12.08.2013, 09.04.2014, and 06.05.2014.
6.
Unaware of these developments, the petitioner sent to the respondent
a letter dated 28.09.2015, demanding payment of the amount due in terms of
the Engineer’s certification dated 06.05.2013 [original IPC No. 57]. The
petitioner relied upon Sub-Clauses 60.8(a)(i), 60.8(b) and 60.11 of the
Conditions of Particular Application [hereinafter, “COPA”]. As the said