IN THE HIGH COURT OF DELHI AT NEW DELHI % Judgment delivered on: 07.04.2022 + O.M.P. (COMM) 95/2019 & IA No.3385/2019 MINISTRY OF YOUTH AFFAIRS & SPORTS ..... Petitioner versus AGILITY LOGISTIC PVT. LTD. ..... Respondent Advocates who appeared in this case:
For the Petitioner : Mrs. Bharathi Raju, Adv.
For the Respondent : Mr. Abhay Raj Varma, Ms. Priyanka Ghosh & Ms. Vidhi Jain, Advs.
CORAM HON’BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
VIBHU BAKHRU, J
1. The Ministry of Youth Affairs and Sports (hereinafter ‘MYAS’) has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the A&C Act’) impugning an Arbitral Award dated 29.10.2018 (hereinafter ‘the impugned award’) delivered by the Arbitral Tribunal comprising of three members - Justice (Retd.) Shri R.C. Lahoti, Justice (Retd.) Shri D.P. Wadhwa, and Justice (Retd.) Shri S.C. Agrawal as the Presiding Arbitrator (hereinafter ‘the Arbitral Tribunal’).
2. The impugned award was delivered by the Arbitral Tribunal in respect of disputes that had arisen between the parties in connection with the Logistics Service Provider Sponsorship and Services Agreement dated 16.07.2010 (hereinafter ‘the Agreement’).
Factual Context
3. In 2009, the Organising Committee of Commonwealth Games, 2010 (hereinafter the ‘OC’) issued a Request for Proposal (hereinafter ‘RFP’) inviting bids for appointing a Logistics Service Provider for the OC and Queens Baton Relay on the terms and conditions stipulated therein.
4. Pursuant to the RFP, the respondent (hereinafter ‘Agility’) submitted its bid and was declared the successful bidder. Thereafter, by a Letter of Intent dated 10.03.2010 (hereinafter ‘LOI’), the contract for providing the Logistic Services was awarded to Agility. Subsequently, the LOI was revised and amended on 11.03.2010.
5. In terms of the LOI, Agility was to provide Value-in-Kind (hereinafter ‘VIK’) services for an amount of ₹11 crores and Value-in- Cash (hereinafter ‘VIC’) for an amount of ₹1.5 crores. Further, Agility was required to furnish a Performance Bank Guarantee (PBG) to the tune of 10% of the VIK, that is, ₹1.10 crores; and, Corporate Guarantee/Indemnity to the tune of 100% of the value of the VIK, that is, ₹11 crores. However, according to the Arbitral Tribunal, the amended LOI dated 11.03.2010 did not contain the pre-condition of providing PBG of 10% of the VIK.
6. The OC directed Agility to begin logistics support for various supporting events that were scheduled as test events. However, the services provided during the test events were not covered under the scope of services provided in the RFP or any other document. Thus, it was claimed by Agility that a specific assurance and promise was made by the OC to duly and adequately compensate Agility for the services so provided.
7. On 16.07.2010, the Agreement was executed between Agility and the OC.
8. Thereafter, by a communication dated 13.10.2010, Agility requested that it be provided the signed copy of the Agreement. However, Agility claims that it was provided a photocopy of the Agreement on 21.12.2010.
9. Agility had submitted its bid aggregating ₹12.5 crores. The same comprised of two components – VIK services of the value of ₹11 crores and VIC services for a sum of ₹1.5 crores. Agility had agreed to provide the said services in consideration of the sponsorship as offered in terms of the RFP. Clause 31.1 of the RFP indicated the rationale for the bidders to offer logistics services in consideration for being the official logistics sponsor. The said clause is set out below:
“31.1 The Sponsorship Offer of the Logistics Tender is a unique feature of the Tender. Since the Organising Committee of the Commonwealth Games, Delhi 2010, will be providing a huge International Platform to the Logistics Service Provider as the Logistics Partner for the Games.
It is required that the Organising Committee also gets a value in return.”
10. Disputes arose between the parties in relation to the said Agreement. Agility claimed that its rights as an exclusive logistics service provider were breached on various grounds. Disputes also arose between the parties in relation to non-payment of legitimate dues, which included the work done outside the scope of the Agreement, that is, work done for the test events. Additionally, Agility claimed that there were various breaches of obligation by the OC as they did not grant exclusive spons
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.