SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Article Pause Article
judgment-img

2021 Supreme(Online)(DEL) 2968

$~1(Original Side)

* IN THE HIGH COURT OF DELHI AT NEW DELHI + ARB.P. 294/2021 MAYANK AGRAWAL ..... Petitioner Through: Mr. PK Agrawal & Mr.

Rishabh Tomar, Advs.

versus JAIPRAKASH ASSOCIATES LIMITED ..... Respondent Through: Mr. Anil Dutt, Mr. Sumeet Sharma & Ms. Debolina Roy, Advs.

CORAM:

HON'BLE MR. JUSTICE C.HARI SHANKAR

O R D E R (ORAL)

% 13.09.2021 (Video-Conferencing)

1. The petitioner seeks reference of the disputes with the respondent to arbitration.

2. Mr. Anil Dutt, learned counsel for the respondent, has opposed the petition essentially on the following three grounds:

(i) This Court does not possess territorial jurisdiction to decide the present petition.

(ii) By virtue of Clause 2 of Sub-lease Deed dated 18th April, 2019, executed between the petitioner and the respondent, all claims of the petitioner stood settled. No arbitrable dispute, therefore, survives for consideration.

(iii) Clause 7.9 of the aforesaid Sub-lease Deed vested exclusive jurisdiction, in disputes pertaining thereto, with courts at Gautam Budh Nagar, and with the High Court at Allahabad. For this reason, too, this court is coram non judice in the present matter.

3. Clearly, the first and third objections are interlinked.

4. The dispute between the parties pertains to allotment, to the petitioner, by the respondent, of Apartment No. K-10/1103, Jaypee Greens, Sector 128, Noida. A provisional letter of allotment dated 19th September, 2009, was issued to the petitioner by the respondent, against a consideration of ₹ 1,46,02,720/-. The standard terms and conditions in the application for allotment were treated as a part of the provisional allotment letter.

5. The petitioner alleges that there was delay in construction of the aforesaid project, and, consequently, delay in grant of possession, to the petitioner, of the apartment. It is alleged that after nine years, possession of an incomplete apartment was granted to the petitioner by the respondent on 13th November, 2018. It is further asserted that, left with no option, the petitioner executed a Sub-lease Deed, pertaining to the said Apartment in favour of the petitioner, on 18th April, 2019. Thereafter, on 28thJanuary, 2020, it is stated that the respondent offered an amount of ₹8,42,000/- to the petitioner, for completion of the work relating to the apartment, by the petitioner itself. In these circumstances, the petitioner submits that it was driven to take possession of the aforesaid apartment and have the apartment completed out of its own resources.

6. Even so, according to the petitioner, an amount of ₹ 15,12,862/-

was payable by the respondent to the petitioner.

7. Apart from this, the petitioner claims, from the respondent, liquidated damages to the tune of ₹31,47,209.10 and ₹50 lakhstowards damages. The total claim of the petitioner,therefore works out to ₹1,05,02,071/-.

8. It is this dispute that the petitioner seeks reference to arbitration. 9. In this background, I mayadvertto the three objections raised by Mr. Anil Dutt, learned counsel for the respondent.

10. The first objection relates to territorial jurisdiction. Mr.Dutt, submits that, by operation of Clause 10.6 of the Standard Terms and Conditions (hereinafter, “STC”), and Clauses 7.8 and 7.9 of the Sub- lease Deed, this court is divested of jurisdiction to decide the present matter, such jurisdiction vesting exclusively in courts in Gautam Budh Nagar or with the High Court of Allahabad.

11. I am unable to agree.

12. For ready reference, Clauses 10.6 and 10.9 of the STC, and Clauses 7.8 and 7.9 of the Sub-lease Deed maybe reproduced thus:

“10.6 Governing Law and Jurisdiction: The Provisional Allotment shall be governed and interpreted by and construed in accordance with the Laws of India, without giving effect, applicable, to the principles of conflict of laws, thereof or there under and subject to the provisions of Clause 10.9 hereof, the Courts at GautamBudh Nagar, U.P., India shall have jurisdiction over all matters arising out of or relating to this Provisional Allotment.

10.9 Dispute Resolution:Any and all disputes arising out of or in connection with or in relation hereto shall so far as possible, in the first instance, be amicably settled between theCompany and the Applicant. In the event of disputes, claim and/or differences not being amicably resolved such

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top