2023 Supreme(Online)(DEL) 2771

* IN THE HIGH COURT OF DELHI AT NEW DELHI % Date of order : 20th March, 2023 + ARB.P. 1220/2022 ALSORG INTERIORS INDIA PVT. LTD. ..... Petitioner Through: Mr. Govind Rishi and Mr. Rohit Taneja, Advocates versus KUNAL SURI & ANR. ..... Respondents Through: Mr. Sandeep Phogat, Advocate CORAM:

HON'BLE MR. JUSTICE CHANDRA DHARI SINGH

O R D E R

CHANDRA DHARI SINGH, J (Oral)

1. The instant petition under Section 11 of the Arbitration and Conciliation Act, 1996 has been filed on behalf of the petitioner seeking the following reliefs:

“(i) Appoint an impartial arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 to decide the disputes between the parties; and (ii) pass any other further orders/directions as this Hon'ble Court may deem fit and proper in the facts and circumstances of the present case.”

FACTUAL MATRIX

2. The facts relevant for the adjudication of the instant petition is that vide Lease Agreement dated 14th September 2018, the petitioner company entered into a lease for the suit property bearing no. GS-I 05, First Floor, DLF Grand Mall, MG Road, Gurgaon, admeasuring 1151 square meter (hereinafter referred as 'Suit Property') with the erstwhile owner namely, Mrs. Geeta Devi. The period of the lease under the terms and conditions of the Agreement was 5 years commencing from 1st July 2018 with 24 months lock-in period on a monthly rent of INR 75,000 excluding electricity, water, and maintenance charges to be paid to the maintenance agency of the DLF Grand Mall.

3. The terms and conditions provided that the petitioner had to pay rent every month and the lessor had the right to terminate the lease if the lessee defaulted in making the payment of rent or maintenance charges for a continuous period of two months after serving 15 days‟ notice to the lessee in writing.

4. Between March 2020 to June 2020, the government imposed a country-wide lockdown due to COVID-19 due to which the petitioner was also affected, and, thus, vide email dated 6th August 2020 requested a complete waiver of rent for the months of April-May-June 2020, for the months July-August-September 2020 a 60% waiver, and for the month October-November-December 2020 a 50% waiver in the monthly rent, which was agreed by the owner vide email dated 8th August 2020.

5. Accordingly, a revised proposal for the monthly rent for the month of January 2021 was then shared with the previous owner and the same was agreed upon in a physical meeting at the revised rate of INR 55 per sq. ft. and the petitioner started paying rent in terms of INR 55 per sq. ft.

till June 2022.

6. Respondents no. 1 and 2 vide Sale Deed dated 8th June 2022 purchased the suit property from Mrs. Geeta Devi. Pursuant to the sale of the property, respondents no. 1 and 2 adorned the attornment of the suit property qua the rights and responsibility arising out of the Lease Deed dated 14th September 2018.

7. The respondent demanded rent from the petitioner as per the terms and conditions of the Lease Deed dated 14th September 2018 for which communications vide emails took place between the parties.

8. On 16th September 2022, after the alleged threats and influence from the respondents, the petitioner vide its notice invoked Arbitration Clause 16.7 of the Lease Deed dated 14th September 2018.

9. A petition under Section 9 of the Arbitration and Conciliation Act, 1996 was also filed before the Patiala House Courts, New Delhi against the respondents and maintenance agency restraining them from disconnecting, discontinuing, and disallowing the amenities of the suit property. In the said matter a stay vide Order dated 20th September 2022 was granted to the petitioner, restraining the respondents from doing the same till the next date of hearing i.e., 31st October 2022.

10. The petitioner has now filed the present petition for the appointment of an Arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 to adjudicate upon the disputes between the parties pursuant to Clause 16.7 of the Lease Deed dated 14th September

2018.

SUBMISSIONS (On behalf of the petitioner)

11. Learned counsel for the petitioner submitted that a proposal for payment of rent for the months of April-May-June 2020, July-August- September 2020 at 60% waiver, and October-November-December 2020 at 50% waiver was mutually decided between the pet

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top