2023 Supreme(Online)(DEL) 13786
DELHI HIGH COURT
METCON INDIA REALTY AND INFRASTRUCTURE PVT. LTD. – Appellant
Versus
DELHI METRO RAIL CORPORATION LTD. – Respondent
ARB.P.-1140/2022
NEUTRAL CITATION NO: 2023/DHC/000744
ARB.P. 1140/2022
Page 1 of 33
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Reserved on:
16th December, 2022
Pronounced on: 2nd February, 2023
+
ARB.P. 1140/2022
METCON INDIA REALTY AND INFRASTRUCTURE PVT.
LTD.
..... Petitioner
Through:
Mr. Ankur Sood, Advocate
versus
DELHI METRO RAIL CORPORATION LTD. ..... Respondent
Through:
Mr. V. S. R. Krishna and
Mr. V. Shashank Kumar,
Advocates
CORAM:
HON’BLE MR. JUSTICE CHANDRA DHARI SINGH
J U D G M E N T
CHANDRA DHARI SINGH, J.
1.
The instant petition has been filed by the Petitioner seeking the
appointment of an independent Arbitral Tribunal under Section 11(6) of
the Arbitration & Conciliation Act, 1996 (hereinafter referred to as “the
Act”), and has inter-alia prayed for the following reliefs:
Digitally Signed By:GAURAV
SHARMA
Signing Date:02.02.2023
18:18:53
Signature Not Verified
NEUTRAL CITATION NO: 2023/DHC/000744
ARB.P. 1140/2022
Page 2 of 33
case.”
FACTUAL MATRIX
2.
The Petitioner is a firm engaged in civil contracting, land &
property development, and real estate sectors. The Respondent is a
Centre-State Joint Venture responsible for operating the Delhi Metro and
the scope of its work involves planning and implementation of metro rail,
monorail, and high-speed rail projects in India and abroad.
3.
The Petitioner, on 08.09.2015, submitted its bid for Contract CC-
95, pertaining to the construction of the viaduct, and roof portal along
with finishing the work for the automatic walkaway/travelators at Dhaula
Kuan and Rajouri Garden Interchange Stations of Line-7, Phase III of the
Delhi MTRS.
4.
Subsequently, in pursuance of the submitted bid, the Respondent
on 11.01.2016 issued a Letter of Acceptance (hereinafter referred to as
the “LOA”) to the Petitioner for the said contract at a total cost of Rs.
55,07,87,249/-. Furthermore, the LOA stipulated the timeline for the
competition of the work which was 15 months commencing from 1st
February 2016.
5.
The Petitioner’s contention is that the Respondent had added extra
work and had changed the scope of work provided for by the contract,
and the same was undertaken by them on the Respondent’s assurance that
due payments will be made for the extra work. The Petitioner further
Digitally Signed By:GAURAV
SHARMA
Signing Date:02.02.2023
18:18:53
Signature Not Verified
NEUTRAL CITATION NO: 2023/DHC/000744
ARB.P. 1140/2022
Page 3 of 33
submits that while it had duly executed all the work and raised timely
bills, the same was not honoured by the Respondents, despite their prior
understanding on the same.
6.
The Petitioner invoked arbitration by its notice dated 09.06.2022
whereby the Petitioner had inter alia sought the payment of claim amount
of Rs. 55,50,91,763.36 including interest for the extra items/extra work
done by the Petitioner and has accordingly, sought to refer the dispute to
arbitration. However, the Respondent rejected the same on the ground
that the Petitioner’s notice had exceeded the prescribed time limit under
Clause 17.4 of the GCC.
7.
The Respondent further stated in its notice that the Petitioner had
submitted the No Claims Declaration dated 19.03.2021, as per which
once the final payment under the contract is released, then the contractual
agreement including the arbitration clause would be instantly discharged
and rescinded. However, it is contested by the Petitioner that the No
Claims Declaration had been obtained by the Respondent under economic
duress and coercion by refusing to release any payment which was due to
the Petitioner, and thus, the No Claim Declaration should be rejected by
the court.
8.
The Petitioner has preferred this instant petition under Section
11(6) of the Act pertaining to the dispute regarding extra work that was
assigned to the Petitioner.
Digitally Signed By:GAURAV
SHARMA
Signing Date:02.02.2023
18:18:53
Signature Not Ve