2023 Supreme(Online)(DEL) 11513
FAO(OS) (COMM) 315/2019
Page 1 of 25
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Judgment reserved on: 03 November 2023
Judgment pronounced on: 30 November 2023
+
FAO(OS) (COMM) 315/2019 & CM Nos. 47880/2019 &
47884/2019
ANIL KUMAR GUPTA
..... Appellant
Through:
Dr. Amit George, Mr. Aditya
Chibber,
Mr.
Rayadurgam
Bharat & Mr. Arkaneil Bhaumik,
Advs.
versus
MUNICIPAL CORPORATION
OF DELHI & ANR.
..... Respondents
Through:
Mr. Sunil Goel, SC with Ms.
Akshita jain, Mr. Himanshu
Goel, Advocates with Mr. Bhanu
Pratap Yadav, A.E. (Project),
Narela Zone.
CORAM:
HON'BLE MR. JUSTICE YASHWANT VARMA
HON’BLE MR. JUSTICE RAVINDER DUDEJA
YASHWANT VARMA, J.
1.
The appellant / claimant assails the judgment and orders dated 12
December 2018 and 08 August 2019 passed by the learned Single
Judge on the Section 34 petition instituted by the respondent under the
Arbitration & Conciliation Act, 19961.
1 1996 Act
Digitally Signed
By:KAMLESH KUMAR
Signing Date:30.11.2023
13:15:27
Signature Not Verified
Page 2 of 25
2.
It would appear from the record that in terms of the judgment
which was rendered on 12 December 2018, the learned Single Judge
while partly allowing the Section 34 petition had reduced the rate of
interest awarded in favour of the appellant / claimant passed by the
Arbitral Tribunal2 from 18% to 12% and further restricting the
application of interest from the date of accrual of cause of action,
namely, 08 March 2004 and providing it to commence from the date of
invocation of arbitration, namely, 06 July 2008.
3.
After the Section 34 petition had been finally disposed of on 12
December 2018, an application for modification came to be moved by
the respondent and which was accepted and disposed of in terms of the
order dated 08 August 2019. Dealing with the issues which appear to
arise on the appeal and on hearing learned counsel for respective
parties, we had, on 15 September 2023, passed the following order:
1. The instant appeal questions the judgment and order dated 08
August 2019 and 12 December 2018 passed by the learned Single
Judge on a petition preferred under Section 34 of the Arbitration and
Conciliation Act, 1996 [“the Act”].
2. As would be manifest from the record, the Section 34 petition
came to be disposed of on 12 December 2018 in the following
operative terms: -
“14. The stand that extension of time was not granted is not
correct. Thus as per Clause 10CC, escalation is liable to be
granted in any contract even during the extended period and
the contractor is entitled to escalation. Coming to the
question as to whether any evidence was lead on payments
made under Clause 10CC – it is the settled position that 10
CC prescribes a formula for calculation of escalation. It
stipulates the manner in which escalation is calculated.
Once the escalation is awarded, the manner of calculation is
done as per the said Clause itself. In any case, during the
2 AT
Digitally Signed
By:KAMLESH KUMAR
Signing Date:30.11.2023
13:15:27
Signature Not Verified
Page 3 of 25
period during which escalation was claimed, the work was
under progress. The fact that the work was continuing and
was also completed itself is proof of material, labour etc.,
being employed. Thus, the award of escalation under Clause
10CC is not liable to be interfered with.
15. Para 20 and 21 of Municipal Corporation of Delhi v.
Rakesh Brothers 2005(2) Arb. LR 257 (Delhi) are apt and
are set out herein below:
“20. Claim No.5 in sum of Rs.1.35 lacs was based on
Clause 10(CC) of the contract provided for escalation
as per formula provided therein. Clause 10(CC) has
been incorporated in the contract at Serial No. 26 of
the general conditions of the contract. Submission of
the MCD before the learned arbitrator was that
compensation under Clause 10(CC) had to be paid on
the basis of actual occurrence of the escalation with
return proof. Learned arbitrator has rejected the
same by bolding that this would defeat the mandatory
provision of the agreement.
21. Two Division Benches of this Court in the
decisions reported as 1998 (VII) AD (Delhi)
300=1999(1) Arb. LR 88(Del.) (DB) – DDA vs. U.
Kashyap and 2001 (II) AD (Delhi) 116 – DDA vs.
K.C. Goyal, have held that where a clause in a
contract provides a formula to give escalation, award
of escalation on the basis of actual increase in price
of material would be impermissible. Opposition
before the learned arbitrator to Claim No.5 is based
on a wrong notion of law and the learned arbitrator
has rightly held that escalation has to be as per
statutory formula. Decision of the learned arbitrator
is in complete harmony with decisions of this Court.
Learned arbitrato