2025 Supreme(Online)(DEL) 333
HIGH COURT OF DELHI
Purushaindra Kumar Kaurav, J
LEVITATE MOBILE TECHNOLOGIES PVT LTD – Appellant
Versus
STANDARD CHARTERED BANK AND ANR – Respondent
CS(COMM)-169/2018
Important Points
Subject
Civil Law - Commercial Disputes
Act Referred
Indian Evidence Act, 1872 : S.138
Commercial Courts Act, 2015
Headnote
(A) Code of Civil Procedure, 1908 - Order XI Rule 1 and 5, Order XVIII Rule 17, Section 151 - Indian Evidence Act, 1872 - Section 138 - Application for permission to place additional documents on record - Plaintiff sought to introduce documents post-deposition of witness, citing voluminous nature of records - Court emphasized the necessity of establishing reasonable cause for non-disclosure of documents at the time of filing the plaint - Application dismissed for lack of due diligence and reasonable cause. (Paras 1, 11, 70, 71)
(B) Commercial Courts Act, 2015 - Purpose and objectives - The Act aims to expedite the resolution of high-value commercial disputes - The court highlighted the importance of adhering to procedural timelines to uphold the legislative intent. (Paras 18, 22, 70)
Facts of the case:
The plaintiff company filed a civil suit against the defendant bank for recovery of ₹4,46,50,000/- along with interest, stemming from a dispute over a mobile application development agreement initiated in 2012. The plaintiff claimed losses after the defendants halted the application’s launch. (Paras 2, 4, 6)
Findings of Court:
The court found that the plaintiff failed to demonstrate reasonable cause for not producing additional documents earlier, which were in their possession, thus dismissing the application. (Paras 71, 72)
Issues: The primary issue was whether the plaintiff established reasonable cause for the late introduction of additional documents, which were in their possession at the time of filing the plaint. (Paras 11, 70)
Ratio Decidendi: The court ruled that the plaintiff's failure to produce documents at the appropriate time, despite being in possession, constituted a lack of due diligence, and the voluminous nature of documents did not suffice as a reasonable cause for non-disclosure. (Paras 70, 71)
Result: Application dismissed.
| Table of Content |
|---|
| 1. application for additional documents (Para 1 , 2 , 3) |
| 2. agreement details (Para 4 , 5 , 7 , 8) |
| 3. legal notice served (Para 6) |
| 4. plaintiff's counsel submissions (Para 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31) |
| 5. court's review of the case (Para 17) |
| 6. court's ruling on reasonable cause (Para 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55 , 56 , 57 , 58 , 59 , 60 , 61 , 62 , 63 , 64 , 65 , 66 , 67 , 68 , 69 , 70 , 72 , 73) |
| 7. application dismissed (Para 71) |
JUDGMENT :
I.A. 24359/2023 (application filed on behalf of the plaintiff seeking permission to place additional documents on record and recalling of plaintiff witness-1)
1. This is an application under Order XI Rule 1 and 5 read with Order XVIII Rule 17 and Section 151 of the Code of Civil Procedure, 1908 [‗CPC’] alongwith Section 138 of Indian Evidence Act, 1872 [‗Act of 1872’] seeking permission to place additional documents on record and recalling of plaintiff witness no.1.
2. At the outset, it is pertinent to have a brief sojourn over the controversy involved in the lis. The instant civil suit has been filed by the plaintiff company seeking a decree for recovery of a sum of Rs.4,46,50,000/- along with interest @ 18% p.a. against the defendant-M/s. Standard Chartered Bank which is located in London, United Kingdom with its branch office in Mumbai.
3. The plaintiff is a company registered under the provisions of the Companies Act, 1956 and is dealing in the development, deployment and management of mobile and web-based solutions. The plaintiff claims to have the requisite skill, knowledge, experience and expertise in the field.
4. As per the plaint, in the year 2012, defendant no.1 through its branch office-defendant no.2, approached the plaintiff for the development and management of a mobile application for catering to the online/M-commerce activities to be carried out by the defendants‘ credit and debit card customers.
5. The parties, after the exchange of certain correspondences, appear to have entered into an IT Professional Services Agreement dated 19.02.2013, whereby, the parties inter alia agreed, that the plaintiff would set up the infrastructure, collect data, develop and maintain the mobile application for the defendant no.1 on a review share model in accordance with the terms of the agreement. The mobile application was initially launched in the year 2013, however, after two months, the defendants asked the plaintiff to take down the application from all application stores. Ever since, certain disputes have arisen between the parties entailing them in exchange of various communications through e-mails etc.
6. The plaintiff claims to have suffered the loss of capital and resources, and a legal notice dated 15.04.2015 was served upon the defendants to pay a sum of Rs.4,46,50,000/-. The defendants replied to the same on 15.05.2015 and refuted the claim raised by the plaintiff. The plaintiff, thus, instituted the instant civil suit in the year 2015.
7. After the completion of pleadings, the issues were framed on 16.11.2016 and evidence was commenced. On 07.08.2023, plaintiff witness No.1-Shri Sunil Jasuja completed his deposition. Thereafter, on 18.11.2023, the instant I.A. 24359/2023 came to be filed by the plaintiff.
8. By way of the instant application, the plaintiff seeks to bring on record three sets of documents i.e., (i) e-mails exchanged between the plaintiff and defendants, (ii) the copy of the agreements entered between the plaintiff company and other vendors and (iii) backend data stored in servers.
9. Mr. Sudhir Nandrajog, learned senior counsel, assisted by Mr. Abhimanyu Garg learned counsels, appearing on behalf of the plaintiff, submits that the instant application seeks to place on record the documents which are necessary in the interest of justice for a fair adjudication of the lis between the parties. He subm