2023 Supreme(Online)(Del) 22503
DELHI HIGH COURT
IRCON INTERNATIONAL LIMITED – Appellant
Versus
DELHI METRO RAIL CORPORATION – Respondent
OMP_(COMM)-165_2023
O.M.P. (COMM) 165/2023 Page 1 of 17
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on
: 21.07.2023
%
Pronounced on
: 09.10.2023
+
O.M.P. (COMM) 165/2023
IN THE MATTER OF:
IRCON INTERNATIONAL LIMITED
..... Petitioner
Through:
Mr. Suman K. Doval, Mr. Hari
Krishan Pandey and Mr. Preetpal
Singh, Advocates.
versus
DELHI METRO RAIL CORPORATION
..... Respondent
Through:
Mr. Tarun Johri and Mr. Ankur
Gupta, Advocates
CORAM:
HON'BLE MR. JUSTICE MANOJ KUMAR OHRI
JUDGMENT
MANOJ KUMAR OHRI, J.
1. By way of present petition instituted under Section 34 of the
Arbitration and Conciliation Act, 1996 (hereafter, the ‘A&C Act’), the
petitioner (hereafter, ‘Contractor’) seeks partial setting aside of the Award
dated 22.11.2022 (hereafter, the ‘impugned award’) in relation to Claim
Nos. 2, 3, 4 and 12 delivered by the Arbitral Tribunal (hereafter, the ‘AT’).
2. The impugned award came to be passed in the context of disputes
Digitally Signed
By:NIJAMUDDEEN ANSARI
Signing Date:09.10.2023
18:14:55
Signature Not Verified
O.M.P. (COMM) 165/2023 Page 2 of 17
arising w.r.t the work of ‘Supply, Installation, Testing and commissioning of
MRTS Project of Phase-III’.
3. The respondent (hereafter, ‘DMRC’) invited bids for the said work,
which was awarded to the Contractor vide Letter of Award dated 17.02.2015
for a total contract value of INR 153,65,61,349/- + USD72,65,823/-. The
Contract period was of 24 months with scheduled date of start as 23.02.2015
and scheduled date of completion as 22.02.2017. A formal Contract was also
executed between the parties. The work was completed on 06.08.2018 i.e.,
after a delay of 18 months. DMRC had granted extensions of time
(hereafter, ‘EOT’) for the entire prolongation of contract without levy of any
liquidated damages.
DISPUTES BEFORE THE AT
4. The Contractor filed its statement of claims (hereafter, ‘SOC’) thereby
raising as many as 12 claims.Claim Nos.2, 3, 4 and 12, that are in issue in
the present proceedings, are extracted hereinbelow:-
Claim No.
Description of Claim
Amount
2(a)
Claim on account of extra
Cost
on
increased
Establishment
Cost
including
Overheads,
Salary of Regular and
Contractual
Staff,
Inspection Vehicle hire
Charges,
etc.
due
to
prolongation of contract
Rs.6,05,50,281.00
Digitally Signed
By:NIJAMUDDEEN ANSARI
Signing Date:09.10.2023
18:14:55
Signature Not Verified
O.M.P. (COMM) 165/2023 Page 3 of 17
2(b)
Claim on account of extra
cost due to payment of
bank charges for repeated
extension
of
Performances
Bank
Guarantee
beyond
stipulated
completion
date
Rs. 43,035.00
2(c)
Claim on account of extra
cost due to extension of
CAR and WC Insurance
Policy
Rs.65,04,290.00
2(d)
Claim on account of Loss
of
Profit
because
of
prolongation of contract
Rs.8,67,59,946.00
2(e)
Claim on account of
Extra
cost
due
to
depreciation
due
to
prolongation of contract
period
Rs. 12,43,393.00
3
Claim on account of
additional cost due to use
of
04 bolt
fastening
system for radius beyond
700 mt.
Rs.1,28,87,297.00
& USD64,987.00
4
Claim on account of
abnormal
increase
in
quantity
of
track
fastenings
INR 1,47,44,999.00
& USD64,987.00
12 Claim on account of
Additional GST burden
Rs.56,40,553.00
5. The Contractor contended that under the Contract, DMRC was
obligated under the Contract to provide the project site progressively. For
the delay of 18 months in completion of the project, the Contractor laid the
entire blame on DMRC. It was contended that DMRC not only delayed in
handing over the project site but also unilaterally changed the design which
Digitally Signed
By:NIJAMUDDEEN ANSARI
Signing Date:09.10.2