2024 Supreme(Online)(Del) 33391
IN THE HIGH COURT OF DELHI AT NEW DELHI
M/S REINFORCED EARTH INDIA PVT LTD – Appellant
Versus
RK INFRACORP PRIVATE LIMTED & ANR. – Respondent
ARB.P.-1382/2024
$~12 * IN THE HIGH COURT OF DELHI AT NEW DELHI % Date of Decision : 06.12.2024 + ARB.P. 1382/2024 M/S REINFORCED EARTH INDIA PVT LTD .....Petitioner Through: Mr. Gurinder Pal Singh and Ms.
Maryam Beg, Advocates.
versus RK INFRACORP PRIVATE LIMTED & ANR. .....Respondents Through: Mr. Brijesh Kumar Goel, Mr. Rajeev Kumar and Mr. Sajal Goel, Advocate for R-1 (through VC)
CORAM:
HON'BLE MR. JUSTICE SACHIN DATTA SACHIN DATTA, J. (Oral
1. The present petition under Section 11(5) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the A&C Act’) seeks constitution of an arbitral tribunal to adjudicate the disputes between the parties.
2. The disputes between the parties have arisen in the backdrop of work relating to construction of melli yard works including earthwork in cutting, filling, development of drainage system, sloe stabilization, retaining structures, reinforced soil wall system, construction of bridge no.10 on pile foundation, bridge no.11 and other ancillary works between 26.570 km to 27.540 km in connection with construction of Sivok-Rangpo New BG Railway Line Project which was awarded by Ircon International Limited to the respondent no.1.
Signature Not Verified Digitally Signed By:ROHIT ARB.P. 1382/2024 Page 1 of 4
3. In pursuance thereto, the respondent no.1 sub-contracted to the petitioner the execution of the part of the works vide sub-contract agreement dated 27.11.2021.
4. Thereafter, on 06.05.2022, the aforesaid sub-contract agreement was partially amended.
5. While the petitioner continued to perform its part of the obligations under the sub-contract, the respondent no.1 assigned the responsibility of releasing payments to the petitioner under the sub-contract agreement dated 27.11.2021 and its subsequent amendment dated 06.05.2022 to the respondent no.2. A tripartite agreement was accordingly executed on 06.02.2023 between the petitioner, the respondent no.1 and the respondent no.2.
6. According to the petitioner, in terms thereof, both the respondent no.1 and the respondent no.2 are jointly and severally liable for release of all outstanding payments to the petitioner.
7. Disputes between the parties have arisen on account of alleged non-
payment of the petitioner’s outstanding dues.
8. Consequently, the petitioner invoked the arbitration clause contained in the tripartite agreement for the purpose of adjudication of disputes between the parties vide invocation notice dated 24.06.2024.
9. Admittedly, the tripartite agreement contains an arbitration clause as under :-
“8. The parties, i.e., RKIPL, Suryodaya and REIPL hereto shall make every reasonable effort to settle amicably between themselves any dispute or difference arising out of this Tripartite Agreement within a reasonable period of 30 days. In the event they are being unable to settle such dispute/s the same shall be referred to arbitration in accordance with the provisions of the Arbitration and Conciliation Act, 1996 to be referred to Signature Not Verified Digitally Signed By:ROHIT ARB.P. 1382/2024 Page 2 of 4 the Sole Arbitrator. The jurisdiction shall be of New Delhi Courts only. The venue of Arbitration shall be Hyderabad and New Delhi on a rotational basis, the first venue starting from Delhi. The Award shall be final and binding on all the parties.”
10. Learned counsel for the respondent no.1 does not dispute the existence of the arbitration agreement and accedes to the appointment of a sole arbitrator by this Court to adjudicate the disputes between the parties.
11. None appears for the respondent no.2. However, it is pointed out by the learned counsel for the petitioner and the respondent no.1 that the respondent no.2 has participated in mediation proceedings pursuant to initial order dated 12.11.2024 passed by this Court.
12. Even though the mediation has failed, no reply has been filed on behalf of the respondent no.2 opposing the prayer/s sought in the present petition.
13. In any event, since the existence of the arbitration agreement i