2025 Supreme(Online)(Del) 5671
IN THE HIGH COURT OF DELHI AT NEW DELHI
Prathiba M. Singh, Rajneesh Kumar Gupta, JJ
MANDEEP MANN – Appellant
Versus
DELHI DEVELOPMENT AUTHORITY – Respondent
W.P.(C) 9756/2025
For the Appellant: Appearance not given
For the Respondents: Mr. Arjun Mahajan, SC with Mr.Apoorv Upmanyu and Mr. Harsh Vashisht, G.S.Oberoi, SC with Mr. Ankur Sharma, Ms. Shaifali Jain and Mr.J.S.Oberoi, Ms. Urvi Mohan
Consent regarding unauthorized construction requires adherence to statutory regulations; enforcement of building norms is critical for public safety.
Headnote:(A) Constitution of India - Article 226 - Writ petition seeking various reliefs regarding unauthorized constructions in a cooperative housing society, highlighting violations of building regulations and non-compliance with Delhi Development Act. Key issues include unauthorized construction, lack of response to stop notices, and failure to fix Floor Area Ratio (FAR). (Paras 3, 4, 6, 8, 9)
(B) Cooperative Societies - Grievances concerning local issues and disputes with the Management Committee necessitate adequate remedies under applicable laws.
Facts of the case:
A petition filed by the owner alleging illegal constructions in a cooperative housing society and seeking intervention against the DDA regarding unauthorized activities and management issues.
Findings of Court:
The DDA is permitted to take necessary action as per law given the established stop construction notice.
Issues: Main questions addressed included the authority to cease constructions contrary to safety and regulatory compliance, and remedies available to the petitioner.
Ratio Decidendi: Court upheld the authority of the DDA to act against unauthorized constructions, reiterating that the petitioner may seek further remedies under the Multi State Cooperative Societies Act.
Result: Petition stands disposed of. Pending applications are also disposed of.
| Table of Content |
|---|
| 1. allegations of unauthorized construction and grievances regarding action by authorities. (Para 3) |
JUSTICE PRATHIBA M. SINGH JUSTICE RAJNEESH KUMAR GUPTA Prathiba M. Singh, J. (Oral)
1. This hearing has been done through hybrid mode.
CM APPL. 40778/2025 (Exemption)
2. Allowed,subject to all just exceptions.Theapplication stands disposed of.
W.P.(C) 9756/2025
3. The present petition has been filed by the Petitioner-Mandeep Mann under Article 226 of the Constitution of India, inter alia, seeking various reliefs in respect of the Sadbawna Cooperative Group Housing Society Ltd (hereinafter, ‘Society’). The prayers in the present petition are as under:
“a. Issue an appropriate Writ, Order or Direction, Signature Not Verified Signed By:NAMITA W.P.(C)9756/2025 Page1of4 including a Writ of Mandamus, directing Respondent No.1 (DDA) and Respondent No.2 (MCD) to forthwith halt all ongoing unauthorized construction activities being carried out in Sadbhawna CGHS Ltd., Plot No. 11, Sector 11, Dwarka, New Delhi–110075 (Respondent No.4), which are in violation of the sanctioned building plans, MBBL-2016, MPD-2021 and other applicable building regulations; and b. Direct Respondents No.1 and 2 to undertake demolition of all structures erected in excess or in deviation from the sanctioned layout and building plans, and to ensure compliance with the statutory provisions of the Delhi Development Act , 1957 and Unified Building Bye-Laws for Delhi, 2016; and c.DirectRespondentsNo.1and2toinitiatedisciplinaryand legal proceedings against all erring officers, developers, architects, and members of the managing/executive committee of Respondent No.4 Society for having colluded in the grant and execution of illegal construction and for furnishing false/forged structural and other documents and for their failure to act on the Petitioner’s complaints; and d. Direct the Respondents to place on record the complete record of Floor Area Ratio (FAR) sanctioned by DDA/competent authority for Respondent No.4 Society for the period 2017 to 2025, along with the basis of such allocation in terms of MPD-2021 and MBBL-2016; and e. Direct the Respondents to furnish a block-wise/tower- wise breakup of the FAR allocation to the various constituent buildings/blocks within Respondent No.4 Society, and the rationale adopted in proportioning the same; and f. Direct the Respondents to submit a status report of all actionstakenbetween2017 and 2025,whereverFAR-based construction was halted, and the grounds of such suspension or withdrawal of work permissions, if any; and g. Pass appropriate directions to the Respondents to duly classify the Petitioner’s property asfallingunder Category- D in accordance with the applicable norms under the Signature Not Verified Signed By:NAMITA W.P.(C)9756/2025 Page2of4 Master Plan for Delhi, 2021 and other prevailing regulations, and to ensure the allocation of maximum permissible Floor Area Ratio (FAR) in a proportionate and equitable, at par with similarly situated residents of Respondent No. 5/Society, strictly in accordance with law;and h. Direct Respondents No.1 to 3 to blacklist, de-empanel, and take penal action under applicable law against the Architects, Builders, Developers, Structural Engineers, and any other individuals or entities responsible for illegal, unsafe, or unauthorized construction within Respondent No.4 Society, including for violations of public safety, environmental norms, and building codes; and i. Direct the appointment of an independent court- monitored technical agency, comprising experts in civil engineering, fire safety, and urban planning, to conduct a comprehensive structural and regulatory audit of the entire construction in Respondent No.4 Society, and to submit a report regarding: (i) conformity with sanctioned plans, (ii) safety of existing structures, and (iii) proper allocation and utilizationofFARaspertherecordsofDDAandapplicable law; and j. Direct Respondents 3-5 to refrain from carrying out