SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Del) 7455

IN THE HIGH COURT OF DELHI AT NEW DELHI
Anil Kshetarpal, Harish Vaidyanathan Shankar, JJ
M/S B S ENVIRO N INFRACON PRIVATE LIMITED – Appellant
Versus
VIJ CONTRACTS PVT. LTD. – Respondent
RFA (COMM) 132/2024



Advocates:
For the Appellants/Petitioners: Mr. Robin George, Mr. Yogesh Bhatt
For the Respondents: Mr. L. K. Singh

Acceptance of lesser sums as full settlement precludes additional claims without evidence of further entitlements, affirming accord and satisfaction under the Indian Contract Act.

Headnote:(A) Code of Civil Procedure, 1908 - Section 96 - Commercial Courts Act, 2015 - Accord and satisfaction - Allegations of non-payment for subcontracted work - Trial Court held that a document dated 26.09.2019 constituted full and final settlement of claims - Acceptance of part payment by Appellant confirmed discharge of claims to the extent recorded - Sections 62 and 63 of the Indian Contract Act, 1872 applied - Appeal dismissed as claims were settled; further claims not established. (Paras 20-35)

(B) Accord and Satisfaction - Nature of acceptance of payment - Acceptance of payment as acknowledgment of settlement rather than conditional payment - Legal implications of signing documents recording payments, with acknowledgment of conditions of release of funds - Established principle that acceptance of lesser amounts precludes subsequent claims without evidence of further entitlement (Paras 25-33)

Facts of the case:
The Appellant supplied materials under a subcontract, claiming unpaid dues post a settlement recorded in a document dated 26.09.2019, which was disputed regarding its interpretation as full and final settlement.

Findings of Court:
The document indicated accord and satisfaction, rejecting additional claims from the Appellant based on evidence and acceptance of previous payments.

Issues: The principal issue was whether the document served as a full and final settlement of all accrued claims, alongside contentions regarding alleged unbilled amounts and the basis for retention sums.

Ratio Decidendi: The court concluded that acceptance of payments under recorded terms established accord and satisfaction, overriding any assertions of procedural withdrawal conditionality. The document contained explicit conditions that negated further claims unless the conditions were met.

Result: Appeal dismissed.

Table of Content
1. factual background regarding contract and payments. (Para 3 , 4 , 5)
2. contentions from the appellant regarding the nature of the settlement. (Para 9 , 10 , 11)
3. respondent's position on the accord and satisfaction of claims. (Para 14 , 15)
4. court's examination of the evidence and documents related to the claims. (Para 20 , 22)
5. legal reasoning behind the accord and satisfaction ruling. (Para 25 , 34)
6. final outcomes of the appeal. (Para 35 , 36)
ANIL KSHETARPAL, J.

1. The issue that arises for consideration in the present Appeal is whether the learned Trial Court was right in concluding that the document dated 26.09.2019 (Ex. PW1/D2 /Annexure-A9) recorded a full and final settlement, in respect of the claims that had accrued up to that date, and whether, on the evidence on record, any interference with the findings of the Trial Court can be warranted.

2. The present Appeal filed under Section 96 of the Code of Civil Procedure , 1908 [hereinafter referred to as “CPC”] read with Section 13 of the Commercial Courts Act , 2015 assails the correctness of the judgment and decree dated 03.01.2024 [hereinafter referred to as “Impugned Judgment”] passed by the Trial Court, whereby the suit instituted by the Appellant for recovery of Rs.50,41,835/- (along with interest and costs) was dismissed.

FACTUAL MATRIX

3. The salient facts, as pleaded by the parties and recorded by the Trial Court, may be briefly stated. The Appellant is a company engaged in supply, installation, testing and commissioning of Sewage Treatment Plants [hereinafter referred to as “STP”], which had subcontracted certain works from the Respondent. The Respondent is the principal contractor awarded the work of supply, installation, testing and commissioning of an 800 KLD STP at Haryana Vishwakarma Skill University, Dudhola, Palwal by IRCON Infrastructure and Services Ltd. (IISL). The dispute arises from alleged non-payment by the Respondent for materials supplied and services rendered by the Appellant under the subcontract agreement.

4. On 01.03.2019, the Respondent issued a Letter of Intent [hereinafter referred to as “LOI”] to the Appellant for the above-stated work for a contract value of Rs.1,15,00,000/- plus GST. The Bill of Quantity [hereinafter referred to as “BOQ”] annexed to the LOI provided for staged payments – Rs.10,00,000/- (advance) as per BOQ, 85% on supply/delivery of material (within 10 days of receipt), 10% on installation and 5% on testing & commissioning. Clause 7 of the LOI provided for retention money (10% of running bills, subject to a maximum of 5% of contract value) refundable after the Defect Liability Period (36 months after completion). Payments were to be made on a back-to-back basis, as IRCON was the principal releasing funds to the Respondent for onward disbursement to the Appellant.

5. The Appellant raised Tax Invoices Nos.236, 237 and 238 dated 27.03.2019 for materials aggregating to Rs.1,00,22,272/- [Ex. PW1/4 Colly /Annexure A5 (Colly)]. The Appellant asserted that it supplied the materials to the site (receipts recorded on 29.03.2019 and 31.03.2019), submitted requisite shop/plot/P&ID drawings and test reports, and appointed supervisory staff. It alleged that the Respondent failed to complete civil works or provide space/clearance for installation, thereby preventing completion of installation/testing components and the raising of further invoices.

6. As recorded in Paragraph No.2.4 of the Impugned Judgment, the total contract value under the LOI was Rs.1,15,00,000/- plus GST, i.e., Rs.1,28,80,000/-. Out of this, the Respondent had paid Rs.78,38,165/-, leaving a balance of Rs.50,41,835/- claimed by the Appellant.

7. The Respondent, in its written statement, recorded that the Appellant was a registered Micro, Small and Medium Enterprise (MSME) under the MSMED Act and that the Appellant had invoked MSME (Samadhaan) proceedings on 10.07.2019 in respect of the billed invoices, claiming Rs.45,42,272/- for Invoice Nos.236,

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top