SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Del) 7580

IN THE HIGH COURT OF DELHI AT NEW DELHI
Jasmeet Singh, J
MECWEL CONSTRUCTIONS PVT. LTD. – Appellant
Versus
GE POWER SYSTEMS INDIA PVT. LTD. – Respondent
O.M.P. (T) (COMM.) 38/2025 & I.A. 12346/2025 | O.M.P. (T) (COMM.) 39/2025 & I.A. 12348/2025 | O.M.P. (T) (COMM.) 40/2025 & I.A. 12350/2025



Advocates:
For the Appellants/Petitioners: Dr. Amit George, Shashwat Kabi, Ibansara Syiemlieh, Adhishwar Suri, Vaibhav Gandhi, Kartikay Puneesh
For the Respondents: Mr. Akshay Sapre, Mr. Abhijeet Swaroop, Mr. Vinam Gupta, Ms. Shivani Karmakar

Orders under Section 25(a) of the Arbitration Act terminating proceedings for non-compliance are procedural and do not constitute an 'award'; thus petitions for continuation are maintainable upon compliance.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 14, 15, and 25(a) - Substitution and appointment of arbitrator - Petitioner sought appointment due to the arbitrator closing proceedings for non-filing of statement of claims - Court acknowledged the arbitrator's order for default termination as lacking adjudication on rights - Maintained that no award was rendered as the decision was procedural - The arbitration proceedings were ordered to continue upon compliance with fee directions. (Paras 8, 9, 19, 20)

(B) Arbitrator's authority and obligations - The proceedings can be terminated if the claimant fails to act against the directions provided - Orders of default under section 25(a) cannot be equated with awards, as they do not resolve substantive issues. (Para 20)

Facts of the case:
The petitioners submitted bids for subcontracting work related to Thermal Power Projects, which were later awarded by the respondent. Due to delays, the respondent issued termination notices. The arbitrator closed proceedings for petitioner’s non-compliance with fee matters and statement of claims. (Paras 3-6)

Findings of Court:
The court ruled that the previous order closing arbitration proceedings lacked substantive adjudication and wasn't an Award, thus, petitions were allowed for arbitration to continue upon compliance. (Paras 20-22)

Issues: The key issue was whether the arbitrator's order constituted an Award under the Act and the maintainability of the petition given the circumstances. (Paras 10, 36)

Ratio Decidendi: It was decided that procedural orders arising from non-compliance do not equate to substantive awards; therefore, the arbitration can be revived upon the petitioner's compliance with fee directions. (Para 19)

Result: Petitions allowed - Arbitration proceedings to continue.

Table of Content
1. petitions for arbitrator appointment (Para 1 , 2 , 3 , 4)
2. arbitral proceedings closure procedural issues (Para 5 , 6)
3. nature of awards and appeals under section 34 (Para 9 , 10 , 11)
4. judgments on arbitration proceedings complexity (Para 15 , 16 , 17 , 18 , 19 , 20 , 21)
5. arbitration proceedings to continue (Para 22)

JASMEET SINGH, J (ORAL)

1. These are petitions filed under Section 14 and 15 of the Arbitration and Conciliation Act, 1996 seeking the seeking substitution and/or appointment of an Arbitrator and/ or pass an order enabling the Arbitrator to continue proceedings.

2. The brief facts are that the projects relating to erection, testing, commissioning and handover of steam turbine & generator auxiliaries for various Thermal Power Projects were awarded to GE Power Systems India Pvt. Ltd. (“respondent”).

3. The respondent then further invited bids for subcontracting of Erection. and Commissioning of Mechanical & Erection Packages for the said projects. The petitioner submitted its bid which was thereby accepted by the respondent herein vide a Letter of Award. Accordingly, the work was subcontracted to the petitioner herein and the respondent herein issued a purchase order in favour of the petitioner dated 07.08.2020, 10.06.2019, 02.04.2019 respectively.

4. Since there were delays in completion of work, a notice of termination issued by the respondent dated 29.08.2022, 26.07.2022, 06.03.2023. The petitioner initially filed petitions under Section 9 of 1996 Act at District Court in Vijaywada and subsequently before this Court being OMP(I)(COMM) 6/2024, OMP(I)(COMM) 7/2024 and OMP(I)(COMM) 8/2024 seeking a direction to restrain the respondents from encashing the subject bank guarantees.

5. Subsequently, this Court vide Order dated 08.01.2024, disposed the said petitions with the direction that the respondent shall be entitled to receive pay outs by way of invocation of the bank guarantees but keep the amounts in FDRs and was further pleased to appoint the Arbitrator to adjudicate the disputes between the parties. The Arbitrator entered reference.

6. The Arbitrator vide Order 18.11.2024, was pleased to close the arbitration proceedings, since the petitioner had not filed its statement of claims and not paid portion of the arbitral fee under Section 25 (a) of the Arbitration and Conciliation Act, 1996 . The said Order is the genesis of the present petition. The operative portion reads as under:-

“7. The Arbitrator has duly considered the matter. In absence of SOC for such long time and in absence of compliance of direction regarding fee, the Arbitrator is unable to proceed and is constrained to close the proceedings subject to window of opportunity for compliance being availed. The fee already paid (total Rs. 15 lacs by both the parties) stands appropriated towards fee for the proceedings so far in four sittings.

8. Accordingly, proceedings will stand closed under section 25(a) of the Arbitration and Conciliation Act, 1996 subject to the window of further opportunity for compliance in next one month. If compliance is done in terms of deposit of fee and filing of SOC, date for further hearing will be fixed.”

7. Thereafter, the Arbitrator passed another dated 18.12.2024, where the Arbitrator was pleased to observe that the Arbitrator was open to hearing the parties in case they promptly comply with the earlier directions. The operative portion reads as under:-

“4. The Arbitrator has today received two Emails from Mr. Prasada Rao P, on behalf of Mecwel. In first, he has stated that he would deposit fee by 20.12.24 and file requisite pleadings by 25.01.25. On that basis, prayer is that proceedings be continued and date be fixed. Second email forwards SOC in one of the cases (in other two SOCs have already been filed) and other documents in other two cases.

5. Considering the above, the Arbitrator is open to consider the matter further, after hearing the parties, if the parties promptly comply with the earlier directi

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top