2025 Supreme(Online)(Del) 7617
IN THE HIGH COURT OF DELHI AT NEW DELHI
Jasmeet Singh, J
M/S AMD ESTATES AND DEVELOPERS PVT LTD. – Appellant
Versus
M/S VSR INFRATECH PVT LTD. – Respondent
O.M.P.(I)(COMM.) 438/2024 & CCP(O) 10/2025 & CCP(O) 34/2025 & CCP(O) 55/2025 & CCP(O) 85/2025 & O.M.P.(I)(COMM.) 231/2025
Important Points
Subject
Arbitration - Interim Relief
Act Referred
Headnote
(B) Where interim protection is sought, established principles include a prima facie case, balance of convenience and risk of irreparable harm. The court found Owner's claims credible, given ongoing disputes and delays, warranting continued restraining orders. (Paras 35 to 38)
Facts of the case:
The parties entered into a Collaboration Agreement for property development, which faced numerous delays attributed to both parties. The Developer claimed encroachment caused delays while the Owner cited Developer's financial mismanagement and failure to meet project timelines. (Paras 6, 22, 39, 40)
Findings of Court:
The court found a strong prima facie case for the Owner's claims, confirming that the Developer had not operationalized agreed financial safeguards and that ongoing disputes may lead to irreparable harm if not addressed. (Paras 44, 48)
Issues: The main issues included the enforceability of the Developer's right of first refusal and the ongoing delays in project completion. (Paras 39, 64)
Ratio Decidendi: The court ruled that the Developer failed to enforce its right of first refusal and clarified that alienation of the Owner’s units without adhering to agreed contractual terms would be injurious. (Paras 69, 74)
Result: The petition by the Developer was dismissed, affirming the Owner's legal possession and the continuation of protective orders. (Paras 76)
For the Appellants/Petitioners: Mr. Sandeep Sethi, Mr. Rajshekhar Rao, Mr. Anurag Ahluwalia, Sr. Advs. with Mr. Ravi Kapoor, Ms. Vishakha Gupta, Mr. Akshit Mago, Ms. Shreya Kunwar, Ms. Riya Kumar
For the Respondents: Mr. Amit Sibal, Sr. Adv. with Ms. Karuna Sharma, Mr. Ankit Tripathi, Mr. Sandeep Phogat, Ms. Mehak, Mr. Gaurav Jain, Mr. Atul Malhotra, Advs.
1. At the outset, the parties were offered that the petitions can be transferred to Arbitral Tribunal as the same stood constituted on 02.09.2025. However, both the parties state that substantial arguments have been heard, hence, this Court may decide the present petitions. In this view, learned senior counsels appearing for the parties have been heard at length and thereafter, the judgment had been reserved on 04.09.2025.
2. Since the parties herein are common in both the petitions, the same are decided by this common judgment.
3. The present petitions have been filed under section 9 of the Arbitration and Conciliation Act , 19961 seeking interim reliefs against each other.
O.M.P.(I) (COMM.) 438/2024
FACTUAL ASPECT
4. AMD Estates & Developers Pvt. Ltd.2 is a company registered under the Companies Act, 1956, having its registered office at 18, Pusa Road, Karol Bagh, New Delhi 110005. M/s. VSR Infratech Pvt. Ltd.3 is a company registered under the Companies Act, 1956, having its registered office at A-22, Hill View Apartments, Vasant Vihar, New Delhi and is inter alia, involved in the real estate business and construction of flats and commercial units.
5. The Owner and the Developer entered into a Collaboration Agreement dated 26.04.2011 for development of land situated in the revenue estate of Bajhghera, Sector 114, Tehsil and District, Gurgaon, Haryana owned by the Owner into a commercial project known as “114 Avenue”4 by the Developer. The possession of the Project land was handed over by the Owner to the Developer. On the same date, the Owner executed a General Power of Attorney5 in favour of the Developer.
6. As per Clause 2.6 of the Collaboration Agreement, the Project was to be completed within 40 months from the commencement of the development of the 60-meter-wide road. As per the information gathered in the Project area, the development of the said road commenced in and around Oct, 2013 and, accordingly, the Project was to commence in and around the same date and was to be completed by February 2017. However, as there was delay in completion of the Project, the Owner and Developer executed a Supplemental Collaboration Agreement on 15.03.20166 wherein the timeline for Project completion was extended to 30 months from the date of the said Agreement i.e. upto September, 2018. It was also agreed that in case of another delay, the Developer would pay compensation of Rs. 40 per sq. ft. per month for the Owner’s unsold share. As there was further delay in completion of the Project, another Supplemental Agreement-II on 18.02.2021 was executed.
7. Again the timelines were not met and the Project was still not completed, Memorandum of Understanding on 31.05.20227 was executed which established an escrow mechanism to ensure proper utilization of funds and accountability in the completion of the Project. The conditions stipulated in the MOU-Escrow concerning the escrow account, necessitated the execution of Supplemental Agreement-III dated 16.06.2022 between the Owner and Developer.
8. With regard to the allocation of shares, as the final revised building plan of the Project was approved on 02.12.2019, the parties entered into a Final Allocation Document dated 15.07.2020, allocating respective units to the Owner and Developer.
9. On 11.04.2012, an agreement titled “Heads of Terms-Sales Agreement for Part of AMD Share in 114 Avenue”8 was executed between the Owner and the Developer. It provided for the proposed sale of small portion / part of Owner’s allocated share to the Developer for further sale. This comprised of 27 units involving 16,258. 66 sq. ft., out of which 20 units were still pending conclusion (“Balance Booked Units”). As per the Owner, the Developer has paid an amount of Rs. 5.56 Crores, while an outstanding balance of Rs. 9.89 Crores remains unpaid.
10. On 21.05.2022, the Owner and the Developer entered into an Addendum to the allocation understanding, pursuant to which the allocation was revised to the Owner’s