SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Del) 7763

IN THE HIGH COURT OF DELHI AT NEW DELHI
Purushaindra Kumar Kaurav, J
RENEW WIND ENERGY (AP2) PVT. LTD. – Appellant
Versus
SOLAR ENERGY CORPORATION OF INDIA – Respondent
O.M.P.(I) (COMM.) 213/2025



Advocates:
For the Appellants/Petitioners:Mr. Jayant Mehta, Sr. Advocate, Mr. Vishrov Mukherjee, Mr. Girik Bhalla, Ms. Sai Snigdha Nittala, Ms. Juhi Senguttuvan, Ms. Priyanka Vyas, Mr. Yashaswi Kant, Mr. Prayush Singh, Ms. Pallavi Arora
For the Respondents:Mr. M.G. Ramachandran, Sr. Advocate, Ms. Anushree Bardhan, Ms. Srishti Khindaria, Ms. Somya Sahni, Ms. Ritika Singh, Mr. Aneesh Bajaj

CERC has the exclusive power to refer disputes involving generating companies for arbitration, emphasizing the broad scope of Section 79(1)(f) of the Electricity Act over the Arbitration Act.

Headnote:(A) Electricity Act, 2003 - Sections 2(28), 2(39), 9 and 79(1)(f) - Arbitration and Conciliation Act, 1996 - Jurisdiction and maintainability of petition under Section 9 - Referral powers under Section 79(1)(f) are exclusive to the Central Electricity Regulatory Commission (CERC) - CERC has wide powers to refer disputes for arbitration which may not strictly be connected to tariff regulation as specified in Sections 79(1)(a)-(d). The appellant sought interim measures claiming force majeure absolved it from liability for energy shortfall. The respondent argued that jurisdiction lies with CERC and Section 9 of the Arbitration Act is inapplicable. The Court ruled that CERC has exclusive jurisdiction in reviewing disputes involving generating companies and must determine arbitrary referral based on statutory language. A challenge to the subject matter cannot bypass CERC unless no jurisdiction exists under Section 79 - Ruling concludes CERC's referral powers supersede general court powers. (Paras 3, 7, 72-115)

(B) Arbitration - Nature of disputes - Distinction between tariff-related and non-tariff disputes - Pertaining to the scope of arbitration clauses, where disputes do not impact or connect with tariffs, arbitration can be invoked while retaining CERC's regulatory oversight where applicable. (Paras 87-109)

Table of Content
1. petitioner is an energy-generating company seeking protection. (Para 1 , 2 , 3)
2. dispute pertains to the enforcement of ppa clauses. (Para 4 , 5)
3. court determining maintainability and jurisdiction issues. (Para 6 , 7)
4. referral and adjudicatory powers of cerc analyzed. (Para 8 , 9)
5. arguments addressing jurisdiction under electricity act. (Para 10 , 11)
6. judicial scrutiny under section 9 of the arbitration act established. (Para 12 , 13 , 14)
7. powers of cerc to refer disputes defined. (Para 15 , 16 , 17 , 18 , 19)
8. cerc's discretion in adjudication and referral addressed. (Para 20 , 21 , 22)
9. exclusive referral authority of the cerc affirmed. (Para 23 , 24 , 25 , 26 , 27)
10. legislative intent regarding jurisdiction clarified. (Para 28 , 29 , 30)
11. court addresses counterarguments and previous decisions. (Para 31 , 32 , 33)
12. final discussion on implications of the referral powers. (Para 34 , 35 , 36)
13. conclusions on jurisdiction of parties and statutory rights. (Para 37 , 38 , 39 , 40)
14. overall judgment effect on arbitration accessibility. (Para 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52)
15. cerc’s exclusive arbitration referral power clarified. (Para 53 , 54 , 55 , 56)
16. conclusion on maintainability of the petition. (Para 115 , 116)

JUDGMENT

The petitioner, an energy ―generating company‖ within the meaning of Section 2(28) of the Electricity Act , 2003 (hereinafter ― Electricity Act ‖), has filed the instant petition under Section 9 of the Arbitration and Conciliation Act , 1996 (hereinafter ―Arbitration Act‖) praying for an order restraining/injuncting the respondent, a ―licensee‖ within the meaning of Section 2(39) of the Electricity Act , from unilaterally deducting amounts from the petitioner‘s monthly invoices.

I. FACTUAL MATRIX

2. The petitioner operates a 300 MW wind power project in Kutch, Gujarat. The respondent, Solar Energy Corporation of India (‗SECI‘), is a Renewable Energy Implementing Agency (‗REIA‘) designated by the Ministry of New and Renewable Energy (‗MNRE‘).

3. The petitioner was selected by the respondent through a Request for Selection (‗RFS‘) process and had executed a Power Purchase Agreement (‗PPA‘) dated 23.05.2018 for the supply of 300 MW of power for 25 years from the Scheduled Commissioning Date i.e., 24.11.2019.

4. On 02.05.2025, SECI issued a notice to the petitioner alleging non- fulfilment of the minimum energy requirement of 946.08 MUs for the Financial Year 2024-25 and demanded, as compensation under Article 4.4.1 of the PPA, 75% of the cost of shortfall in energy terms, failing which, it claimed, the applicable amount would be deducted from the next month‘s energy invoice of the petitioner.

5. The petitioner states that the shortfall of generation to 632 MUs during FY 2024-25 occurred solely on account of force majeure events, which under Article 4.4.3 of the PPA, absolve the petitioner from liability of compensation. Apprehending coercive recovery before the constitution of the arbitral tribunal, the petitioner has approached this Court under Section 9 of the Arbitration Act seeking urgent interim protection by way of restraint against the operation of the impugned letter and any consequential deductions.

6. Upon issuance of notice, the respondent filed a comprehensive reply, raising several objections. The primary objection of the respondent pertains to the maintainability of the instant petition in light of Section 79(1)(f) of the Electricity Act .

7. For examining the maintainability of the present petition, this Court has analysed the referral and adjudicatory powers of the CERC. This Court has found that the instant petition is not maintainable on the ground that CERC has the exclusive power of referring disputes involving generating companies or transmission licensee for arbitration. The referral power of the CERC under Section 79(1)(f) of the Electricity Act , has been found to prevail over Section 11 and 8 of the Arbitration Act.

8. Fo

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top