IN THE HIGH COURT OF DELHI AT NEW DELHI
Purushaindra Kumar Kaurav, J
RENEW WIND ENERGY (AP2) PVT. LTD. – Appellant
Versus
SOLAR ENERGY CORPORATION OF INDIA – Respondent
O.M.P.(I) (COMM.) 213/2025
| Table of Content |
|---|
| 1. petitioner is an energy-generating company seeking protection. (Para 1 , 2 , 3) |
| 2. dispute pertains to the enforcement of ppa clauses. (Para 4 , 5) |
| 3. court determining maintainability and jurisdiction issues. (Para 6 , 7) |
| 4. referral and adjudicatory powers of cerc analyzed. (Para 8 , 9) |
| 5. arguments addressing jurisdiction under electricity act. (Para 10 , 11) |
| 6. judicial scrutiny under section 9 of the arbitration act established. (Para 12 , 13 , 14) |
| 7. powers of cerc to refer disputes defined. (Para 15 , 16 , 17 , 18 , 19) |
| 8. cerc's discretion in adjudication and referral addressed. (Para 20 , 21 , 22) |
| 9. exclusive referral authority of the cerc affirmed. (Para 23 , 24 , 25 , 26 , 27) |
| 10. legislative intent regarding jurisdiction clarified. (Para 28 , 29 , 30) |
| 11. court addresses counterarguments and previous decisions. (Para 31 , 32 , 33) |
| 12. final discussion on implications of the referral powers. (Para 34 , 35 , 36) |
| 13. conclusions on jurisdiction of parties and statutory rights. (Para 37 , 38 , 39 , 40) |
| 14. overall judgment effect on arbitration accessibility. (Para 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52) |
| 15. cerc’s exclusive arbitration referral power clarified. (Para 53 , 54 , 55 , 56) |
| 16. conclusion on maintainability of the petition. (Para 115 , 116) |
JUDGMENT
The petitioner, an energy ―generating company‖ within the meaning of Section 2(28) of the Electricity Act , 2003 (hereinafter ― Electricity Act ‖), has filed the instant petition under Section 9 of the Arbitration and Conciliation Act , 1996 (hereinafter ―Arbitration Act‖) praying for an order restraining/injuncting the respondent, a ―licensee‖ within the meaning of Section 2(39) of the Electricity Act , from unilaterally deducting amounts from the petitioner‘s monthly invoices.
I. FACTUAL MATRIX
2. The petitioner operates a 300 MW wind power project in Kutch, Gujarat. The respondent, Solar Energy Corporation of India (‗SECI‘), is a Renewable Energy Implementing Agency (‗REIA‘) designated by the Ministry of New and Renewable Energy (‗MNRE‘).
3. The petitioner was selected by the respondent through a Request for Selection (‗RFS‘) process and had executed a Power Purchase Agreement (‗PPA‘) dated 23.05.2018 for the supply of 300 MW of power for 25 years from the Scheduled Commissioning Date i.e., 24.11.2019.
4. On 02.05.2025, SECI issued a notice to the petitioner alleging non- fulfilment of the minimum energy requirement of 946.08 MUs for the Financial Year 2024-25 and demanded, as compensation under Article 4.4.1 of the PPA, 75% of the cost of shortfall in energy terms, failing which, it claimed, the applicable amount would be deducted from the next month‘s energy invoice of the petitioner.
5. The petitioner states that the shortfall of generation to 632 MUs during FY 2024-25 occurred solely on account of force majeure events, which under Article 4.4.3 of the PPA, absolve the petitioner from liability of compensation. Apprehending coercive recovery before the constitution of the arbitral tribunal, the petitioner has approached this Court under Section 9 of the Arbitration Act seeking urgent interim protection by way of restraint against the operation of the impugned letter and any consequential deductions.
6. Upon issuance of notice, the respondent filed a comprehensive reply, raising several objections. The primary objection of the respondent pertains to the maintainability of the instant petition in light of Section 79(1)(f) of the Electricity Act .
7. For examining the maintainability of the present petition, this Court has analysed the referral and adjudicatory powers of the CERC. This Court has found that the instant petition is not maintainable on the ground that CERC has the exclusive power of referring disputes involving generating companies or transmission licensee for arbitration. The referral power of the CERC under Section 79(1)(f) of the Electricity Act , has been found to prevail over Section 11 and 8 of the Arbitration Act.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.