SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Del) 9031

IN THE HIGH COURT OF DELHI AT NEW DELHI
Anil Kshetarpal, Harish Vaidyanathan Shankar, JJ
JAGDISH KAUR – Appellant
Versus
JASBIR SINGH SANDHU & ORS. – Respondent
FAO (COMM) 205/2024|CM APPL. 60557/2024



Advocates:
For the Appellants/Petitioners:Ms. Aastha Dhawan, Adv.|For the Respondents: Mr. Bipin Kumar Prabhat and Mr. Kislaya Prabhat, Advs.

Arbitral awards may be modified by courts to rectify computational errors, allowing adjustments even if such errors were not raised during initial proceedings, underscoring the limited, supervisory role of judicial review under Section 37.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34 and 37 - Appeal against the dismissal of Section 34 Petition challenging Arbitral Award - Appellant claims that the learned Arbitrator failed to adjust overpayment against the final sum awarded - The Court examined if arithmetic errors could be corrected despite no objection raised earlier - Judicial review under 37 is supervisory, not de novo. (Paras 1-2, 30-42)

(B) Arbitral Awards - Judicial scrutiny limited to patent illegality or procedural irregularities - Errors apparent on the face of the record can be corrected even if not raised at the initial stage, allowing for rectification of mathematical discrepancies in the Award to align results with underlying findings. (Paras 21-27, 36-38)

Facts of the case:
Appellant entered into a construction contract with the Respondent for residential property valued at Rs. 62,14,000/-. Disputes arose over payments and unfinished work, leading the Respondent to invoke arbitration. The Arbitrator awarded amounts to both parties, but Appellant claimed a computational error existed.

Findings of Court:
The Court found that the Arbitrator committed a calculative error regarding the adjustment for overpaid sums, requiring modification of the Award.

Issues: Whether arithmetical errors in the Award could be corrected in appeal; the scope of judicial intervention under Section 37.

Ratio Decidendi: The court emphasized the limited jurisdiction when assessing arbitral decisions but affirmed the authority to amend clear mathematical errors to bring it in line with established findings in the Award.

Result: Appeal partly allowed, modifying the Award to adjust overpayments.

Table of Content
1. jurisdiction under section 37 and errors in arbitral awards. (Para 1 , 2 , 3)
2. factual background of the case involving arbitration. (Para 4 , 5 , 6 , 7 , 8 , 9 , 10)
3. findings and conclusions in the arbitration award. (Para 12 , 13 , 14)
4. parties’ arguments regarding the arbitral award. (Para 16 , 17 , 18)
5. court's scrutiny and standard of review under section 34. (Para 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28)
6. discussion of computational errors in the arbitral award. (Para 29 , 30 , 31 , 32 , 33 , 34)
7. modification of the arbitral award for correction of errors. (Para 39 , 40 , 41 , 42)
8. final conclusion and order of the court. (Para 43 , 44)

JUDGMENT

ANIL KSHETARPAL, J.

1. Through the present Appeal under Section 37 , [ Section 37 .] of the Arbitration and Conciliation Act, 1996 , [A&C Act.], the Appellant (Petitioner before the learned District Judge) assails the correctness of the Judgment and Order dated 18.07.2024 [hereinafter referred to as ‘Impugned Order’], whereby the learned District Judge dismissed the petition [hereinafter referred to as ‘ Section 34 Petition’] filed by the Appellant under Section 34 , [ Section 34 .] of the A&C Act and upheld the Award dated 05.06.2020 [hereinafter referred to as ‘Award’] passed by the learned Arbitrator.

2. Herein, the Appellant contends that the learned District Judge, while passing the Impugned Order, failed to appreciate the patent illegality apparent on the face of the Award, inasmuch as the learned Arbitrator omitted to adjust the amount overpaid by the Appellant against the value of the work executed while determining the final awarded sum. However, readjustment of the amount overpaid was not pleaded before the learned District Judge.

3. Accordingly, the issue that falls for consideration before this Court is whether an arithmetical or computational error in the Arbitral Award can be corrected in proceedings under Section 37 , notwithstanding that no such objection had been urged before the Court exercising jurisdiction under Section 34 .

FACTUAL MATRIX:

4. In order to comprehend the issues involved in the present case, relevant facts in brief are required to be noticed.

5. The Appellant, Respondent No. 2 and the Late Mr. Harvinder Singh, entered into an Agreement dated 10.04.2020 [hereinafter referred to as ‘the Agreement’] with Respondent No. 1/Claimant for the construction of their residential property bearing No. E-90, Greater Kailash Enclave-I, New Delhi [hereinafter referred to as the ‘subject premises’].

6. Along with the Agreement, Respondent No. 1 furnished a provisional estimate for the construction of the subject premises in the sum of Rs. 62,14,000/-, which was agreed upon by the parties. In addition thereto, the specifications of the works to be undertaken by Respondent No. 1, along with the materials proposed to be utilized, were also provided. Further, as reflected in the programme schedule executed between the parties, the entire construction was required to be completed by Respondent No. 1 on or before 10.01.2011. It is pertinent to note that the aforesaid documents, namely the Agreement, the provisional estimate, and the time schedule, stand admitted by both parties.

7. Pursuant to the execution of the aforesaid documents, Respondent No. 1 commenced the construction work at the subject premises. However, it is the case of the Appellant that Respondent No. 1 not only failed to complete the construction within the stipulated period but also abandoned the work midway, thereby compelling the Appellant and Respondent Nos. 2 to 5, who are the legal representatives of the Late Mr. Harvinder Singh, to engage other contractors to complete the remaining works.

8. Thereafter, Respondent No. 1 invoked arbitration proceedings against the Appellant and Respondent Nos. 2 to 5, the joint owners of the subject premises, and asserted various claims in respect of the amounts allegedly payable to him for the purported works executed at the subject premi

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top