SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Del) 71

IN THE HIGH COURT OF DELHI AT NEW DELHI
Amit Bansal, J
RCCIVL-LITL (JV) – Appellant
Versus
Union of India – Respondent
OMP (ENF.) (COMM.) 68/2023 | EX.APPL.(OS) 1123/2023



Advocates:
For the Appellants/Petitioners: Amrita Panda
For the Respondents: Jaswinder Singh

Future interest on an arbitral award must be calculated on the total sum directed to be paid, including both principal and interest components. Liability for such interest accrues starting from the day following the award date if the payment is not satisfied within the tribunal-mandated grace period.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 31(7)(a) and 31(7)(b) - Arbitral award - Enforcement - Pendente lite interest - Future interest - Scope of "sum directed to be paid" - Future interest calculations must include all components of the award, including unquantified monetary claims - Obligations for post-award interest commence upon the failure to satisfy payments within the prescribed grace period. (Paras 33, 35, 39)

(B) Interpretation of Statutes - Principles of Interest - The term "sum" in the context of arbitral awards encompasses any amount of money regardless of whether it is categorized as principal or interest - Post-award interest liability arises from the total sum directed to be paid unless the award provides otherwise. (Paras 34, 35)

Facts of the case:
A petition was filed seeking the enforcement of a final arbitral award. Disputes emerged between the parties concerning the inclusion of specific claims in the interest calculations, the entitlement to pendente lite interest for certain claims, and the appropriate methodology for calculating future interest. Specifically, the parties disagreed on whether future interest should apply to unquantified claims and the exact date from which such interest should accrue following the expiration of a grace period granted by the tribunal.

Findings of Court:
The court determined that the tribunal had not awarded pendente lite interest for the contested claims. However, it held that future interest is applicable to all awarded amounts, as the statutory definition of the "sum" includes all money directed to be paid. Consequently, the judgment debtor's failure to settle the amount within the two-month grace period established the liability for future interest starting from the day following the date of the award.

Issues: Whether the tribunal granted pendente lite interest on the contested claims, what constitutes the "sum directed to be paid" for the purpose of calculating post-award interest, and the determined commencement date for such future interest.

Ratio Decidendi: The court clarified that under the Act, the "sum directed to be paid" is not limited to principal amounts but covers the total monetary liability established by the award, including interest. As the judgment debtor failed to fulfill the payment obligation within the grace period provided, they are liable for future interest on the entire awarded amount from the day immediately following the date of the award.

Result: Enforcement petition disposed of; revised calculation of dues ordered.

Table of Content
1. procedural context of award enforcement and reconciliation of calculation disputes. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8)
2. determination of interest entitlement and quantification of claims based on arbitral interpretation. (Para 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27)
3. application of section 31(7) of the arbitration and conciliation act regarding post-award interest calculation on total sums. (Para 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39)
4. final judicial directions for the payment of outstanding dues under the award. (Para 40 , 41 , 42)

JUDGMENT

AMIT BANSAL, J.

1. The present petition has been filed under Section 36 of the Arbitration and Conciliation Act (‘Act’) seeking enforcement of the final award dated 7th November, 2022 (‘Award’) passed by an Arbitral Tribunal comprising a Sole Arbitrator (‘Arbitral Tribunal’).

2. RCCIVL-LITL (JV), the claimant in the arbitration proceedings, is hereinafter referred to as the ‘decree holder’ and the Union of India, the respondent in the arbitration proceedings, is hereinafter referred to as the ‘judgment debtor’.

3. The Arbitral Tribunal allowed certain claims of the decree holder along with interest and costs of arbitration. The counter claims filed by the respondent were rejected by the Arbitral Tribunal.

4. The judgment debtor filed a petition under Section 34 of the Act seeking setting aside of the Award, which was dismissed on 29th May, 2023. An appeal filed against the said dismissal order under Section 37 of the Act was also dismissed by the Division Bench on 8th July, 2024. Subsequently, an SLP filed by the judgment debtor was also dismissed on 20th December, 2024. Therefore, the Award has attained finality.

5. The judgment debtor deposited a sum of ₹17,79,65,167.54 with the Registrar General of this Court on 7th February, 2024, which has since been released in the favour of decree holder.

6. The decree holder claims that it is entitled to sums beyond the deposited amount before this Court whereas judgment debtor opposes the same. In these circumstances, both sides were directed to file their respective calculation details.

7. This Court vide order dated 9th July, 2025 directed that the discrepancies in the calculation table be mutually reconciled by the officials of the parties. However, the differences with regard to the calculation details could not be reconciled. At the hearing on 11th November, 2025, it was noted that the disputes between the parties only persist in respect of claim no. 2(K), claim no.2(L), claim no.2(O), claim no.2(N) and the future interest.

8. Submissions on behalf of counsel were heard on 9th December, 2023 and the judgment was reserved.

9. At first, I will consider the differences between the parties in relation to claim nos.2(K) and 2(L). For the ease of reference, the said claims are set out below:-

“Claim No. 2 (K): Ser No 11 of “Disputed” part of Final Bill:

Reimbursement of compensation on Short/ Less payment of RARs amount amounting to Rs.5,77,19,935.40

Claim No. 2 (L): Ser No 12 of “Disputed” part of Final Bill:

Reimbursement of compensation on delayed payment of RARs amounting to Rs 3,24,69,263.12”

10. In respect of the aforesaid claims, the Arbitral Tribunal held that the claimant (decree holder) did not bring any evidence to prove that it had actually suffered any losses. However, it was noted that there was unjustifiable delay in payments and therefore, the decree holder would be entitled to interest.

11. Accordingly, the Arbitral Tribunal awarded interest at the rate of 8% on the delayed payments. The operative paragraph 144 of the Award is set out below:-

“144. It is noted that except for the calculations referred to in Appendix ‘A’, the Claimant has not brought on record any evidence to prove that it had actually suffered any losses to be entitled to justify its claims under Section 73 of the Contract Act. However, unjustifiably delayed payments whi

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top